MT Detailed Schedule - 29-Apr-24

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31

Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
12-Mar-24 06:30 A 14-Oct-24 08:30 1612h 14-Oct-24 ...
A581 EPC McDermott Project (Microtunneling Detail Schedule)
CR-10 Microtunneling Works 12-Mar-24 06:30 A 14-Oct-24 08:30 1612h 14-Oct-24 ...

MILESTONES 12-Mar-24 06:30 A 14-Oct-24 08:30 1612h 14-Oct-24 ...


ML1000 Microtunelling Start for CR10 12-Mar-24 06:30 A 0h Microtunel...
ML1010 Microtunneling Completion for CR10 06-May-24 06:30 0h Microtunne...
ML1020 Pipe Welding Completion for CR-10 26-Jul-24 08:30 0h Pipe Weldi...
ML1025 Completion of HT CR10 04-Sep-24 08:30 0h Completion...
ML1035 Backfilling CR10 14-Oct-24 08:30 0h Backfillin...
GEN 06-May-24 06:30 29-May-24 08:30 232h 29-May-24 ...
A1000 Completion of Microtunneling Works 06-May-24 06:30* 0h Completion...
A1010 Retrive machine ,readininess for InstallationWinch 06-May-24 06:30 09-May-24 16:30 40h Retrive ma...
A1020 Excavation of entry pit 06-May-24 06:30 25-May-24 08:30 192h Excavation...
A1030 Pipe PullingWinch delivery 18-May-24 06:30* 0h Pipe Pulli...
A1040 HDPE pipe clamp installation 25-May-24 08:30 29-May-24 08:30 40h HDPE pipe ...
A1050 HDPE pipe welding 25-May-24 06:30* 0h HDPE pipe ...
A1060 Pulling Head fabrication 09-May-24 06:30* 0h Pulling He...
A1070 Pulling Head Welding with CRA pipe 09-May-24 06:30 14-May-24 16:30 60h Pulling He...
A1080 CRA Pipe bevelled and ready for Lowering( including Spacer installation,Holiday test & repair)25-May-24 06:30* 0h CRA Pipe b...
A1090 HDPE pipe installation TL-15 25-May-24 06:30 27-May-24 16:30 30h HDPE pipe ...
A1100 Delivery of Zinc Ribbon 16-May-24 06:30* 0h Delivery o...
A1110 Inspection of Zinc ribbon & ready for Installation 28-May-24 06:30* 0h Inspection...
TL-15 06-May-24 06:30 13-Jun-24 10:30 384h 13-Jun-24 ...
Pipe 1,2,3( Jt 1 &2) 28-May-24 06:30 01-Jun-24 12:30 46h 01-Jun-24 ...
A1120 Lowering 1st Pipe with pulling head -TL-15(12 mrs) 28-May-24 06:30 28-May-24 08:30 2h Lowering 1...
A1130 Installation of Zinc Rbbon (4 nos) 28-May-24 08:30 28-May-24 10:30 2h Installati...
A1140 Pulling of 1st pipe( 12 mtr) 28-May-24 10:30 28-May-24 12:30 2h Pulling of...
A1150 Lowering 2nd Pipe -TL-15 28-May-24 12:30 28-May-24 14:30 2h Lowering 2...
A1160 Habitat preparation 28-May-24 14:30 28-May-24 16:30 2h Habitat pr...
A1170 Fit up of 1st Joint in pit & Inspection 29-May-24 06:30 29-May-24 08:30 2h Fit up of ...
A1180 Root & Hot Pass Joint No 1 29-May-24 08:30 29-May-24 12:30 4h Root & Hot...
A1190 IVT -Jt-1 29-May-24 12:30 29-May-24 13:30 1h IVT -Jt-1
A1200 IRT-Jt1 29-May-24 13:30 29-May-24 15:30 2h IRT-Jt1
A1210 Lowering 3rd Pipe -TL-15 29-May-24 15:30 30-May-24 07:30 2h Lowering 3...
A1220 RT Fil m processing-Jt1 29-May-24 15:30 30-May-24 07:30 2h RT Fil m p...
A1230 Habitat preparation 30-May-24 07:30 30-May-24 09:30 2h Habitat pr...
A1240 Fit up of 2nd Joint in pit & Inspection 30-May-24 09:30 30-May-24 11:30 2h Fit up of ...
A1250 Root & Hot Pass Joint No 2 30-May-24 11:30 30-May-24 15:30 4h Root & Hot...
A1260 Fill Up & Cap-Jt1 30-May-24 11:30 31-May-24 08:30 7h Fill Up & ...
A1270 AUT-Jt1 31-May-24 08:30 31-May-24 09:30 1h AUT-Jt1
A1280 FBE coating -Jt1 31-May-24 09:30 31-May-24 11:30 2h FBE coatin...
A1290 IVT-Jt2 30-May-24 15:30 30-May-24 16:30 1h IVT-Jt2
A1300 IRT& Film processing-Jt2 30-May-24 17:00 30-May-24 21:00 4h IRT& Film . .
A1310 Fill Up & Cap-Jt2 31-May-24 06:30 31-May-24 13:30 7h Fill Up & ...
A1320 AUT-Jt2 31-May-24 13:30 31-May-24 14:30 1h AUT-Jt2
A1330 FBE coating-Jt-1& 2 31-May-24 14:30 31-May-24 16:30 2h FBE coatin...
A1340 Installation of Zinc Rbbon (8 nos) both Pipes 2&3 01-Jun-24 06:30 01-Jun-24 08:30 2h Installati...
A1350 Pulling of 2nd pipe & 3rd Pipe 01-Jun-24 08:30 01-Jun-24 12:30 4h Pulling of...
Pipe 4,5 (Jt 3&4) 01-Jun-24 13:30 06-Jun-24 12:30 49h 06-Jun-24 ...
A1360 Lowering 4th Pipe -TL-15 01-Jun-24 13:30 01-Jun-24 15:30 2h Lowering 4...
A1370 Habitat preparation 01-Jun-24 15:30 02-Jun-24 07:30 2h Habitat pr...
A1380 Fit up of 3rd Joint in pit & Inspection 02-Jun-24 07:30 02-Jun-24 09:30 2h Fit up of ...

Actual Work Critical Remaining Work Page 1 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A1390 Root & Hot Pass Joint No 3 02-Jun-24 09:30 02-Jun-24 13:00 4h Root & Hot...
A1400 IVT -Jt-3 02-Jun-24 13:00 02-Jun-24 13:30 1h IVT -Jt-3
A1410 IRT & Film processing -Jt3 02-Jun-24 17:00 02-Jun-24 21:00 4h IRT & Fil...
A1420 Lowering 5th Pipe -TL-15 03-Jun-24 06:30 03-Jun-24 08:30 2h Lowering 5...
A1440 Habitat preparation 03-Jun-24 08:30 03-Jun-24 10:30 2h Habitat pr...
A1450 Fit up of 4th Joint in pit & Inspection 03-Jun-24 10:30 03-Jun-24 12:30 2h Fit up of ...
A1455 Root & Hot Pass Joint No 4 03-Jun-24 08:30 03-Jun-24 12:00 4h Root & Hot...
A1460 Fill Up & Cap-Jt3 03-Jun-24 12:30 04-Jun-24 09:30 7h Fill Up & ...
A1470 AUT-Jt3 04-Jun-24 09:30 04-Jun-24 10:30 1h AUT-Jt3
A1500 Pulling of 4th pipe( 12 mtr) 04-Jun-24 10:30 04-Jun-24 12:30 2h Pulling of...
A1520 IVT-Jt4 04-Jun-24 12:30 04-Jun-24 13:00 1h IVT-Jt4
A1530 IRT& Film processing-Jt4 04-Jun-24 17:00 04-Jun-24 21:00 4h IRT& Film . .
A1540 Fill Up & Cap-Jt4 05-Jun-24 06:30 05-Jun-24 13:30 7h Fill Up & ...
A1550 AUT-Jt4 05-Jun-24 13:30 05-Jun-24 14:30 1h AUT-Jt4
A1560 FBE coating-Jt-3&4 05-Jun-24 14:30 05-Jun-24 16:30 2h FBE coatin...
A1570 Installation of Zinc Rbbon (8nos) 06-Jun-24 06:30 06-Jun-24 08:30 2h Installati...
A1580 Pulling of 4th pipe & 5th pipe 06-Jun-24 08:30 06-Jun-24 12:30 4h Pulling of...
Pipe 6,7 (Jt 5&6) 06-Jun-24 13:30 10-Jun-24 12:30 39h 10-Jun-24 ...
A1590 Lowering 6th Pipe -TL-15 06-Jun-24 13:30 06-Jun-24 15:30 2h Lowering 6...
A1600 Habitat preparation 06-Jun-24 15:30 07-Jun-24 07:30 2h Habitat pr...
A1610 Fit up of 5th Joint in pit & Inspection 07-Jun-24 07:30 07-Jun-24 09:30 2h Fit up of ...
A1620 Root & Hot Pass Joint No 5 07-Jun-24 09:30 07-Jun-24 13:00 4h Root & Hot...
A1630 IVT -Jt-5 07-Jun-24 13:00 07-Jun-24 13:30 1h IVT -Jt-5
A1640 IRT & Film processing -Jt5 07-Jun-24 17:00 07-Jun-24 21:00 4h IRT & Fil ...
A1650 Lowering 7th Pipe -TL-15 08-Jun-24 06:30 08-Jun-24 08:30 2h Lowering 7...
A1660 Habitat preparation 08-Jun-24 08:30 08-Jun-24 10:30 2h Habitat pr...
A1670 Fit up of 6th Joint in pit & Inspection 08-Jun-24 10:30 08-Jun-24 12:30 2h Fit up of ...
A1680 Fill Up & Cap-Jt5 08-Jun-24 12:30 09-Jun-24 09:30 7h Fill Up & ...
A1690 AUT-Jt5 09-Jun-24 09:30 09-Jun-24 10:30 1h AUT-Jt5
A1710 Root & Hot Pass Joint No 6 08-Jun-24 12:30 08-Jun-24 16:00 4h Root & Hot...
A1720 IVT-Jt6 08-Jun-24 16:00 08-Jun-24 16:30 1h IVT-Jt6
A1730 IRT& Film processing-Jt6 08-Jun-24 17:00 08-Jun-24 21:00 4h IRT& Film . .
A1740 Fill Up & Cap-Jt6 09-Jun-24 06:30 09-Jun-24 13:30 7h Fill Up & ...
A1750 AUT-Jt6 09-Jun-24 13:30 09-Jun-24 14:30 1h AUT-Jt6
A1760 FBE coating-Jt-5&6 09-Jun-24 14:30 09-Jun-24 16:30 2h FBE coatin...
A1770 Installation of Zinc Rbbon (8nos) 10-Jun-24 06:30 10-Jun-24 08:30 2h Installati...
A1780 Pulling of 6th pipe & 7th pipe 10-Jun-24 08:30 10-Jun-24 12:30 4h Pulling of...
Pipe 8,9 (Jt 7&8) 06-May-24 06:30 13-Jun-24 10:30 384h 13-Jun-24 ...
A1790 Lowering 8th Pipe -TL-15 10-Jun-24 13:30 10-Jun-24 15:30 2h Lowering 8...
A1800 Habitat preparation 10-Jun-24 15:30 11-Jun-24 07:30 2h Habitat pr...
A1810 Fit up of 7th Joint in pit & Inspection 11-Jun-24 07:30 11-Jun-24 09:30 2h Fit up of ...
A1820 Root & Hot Pass Joint No 7 11-Jun-24 09:30 11-Jun-24 13:00 4h Root & Hot...
A1830 IVT -Jt-7 11-Jun-24 13:00 11-Jun-24 13:30 1h IVT -Jt-7
A1840 IRT & Film processing -Jt7 11-Jun-24 17:00 11-Jun-24 21:00 4h IRT & Fil ...
A1850 Lowering 9th Pipe -TL-15 12-Jun-24 06:30 12-Jun-24 08:30 2h Lowering 9...
A1860 Habitat preparation 12-Jun-24 08:30 12-Jun-24 10:30 2h Habitat pr...
A1870 Fit up of 8th Joint in pit & Inspection 12-Jun-24 10:30 12-Jun-24 12:30 2h Fit up of ...
A1880 Fill Up & Cap-Jt-7 12-Jun-24 12:30 13-Jun-24 09:30 7h Fill Up & ...
A1890 AUT-Jt7 13-Jun-24 09:30 13-Jun-24 10:30 1h AUT-Jt7
A1910 Root & Hot Pass Joint No 8 12-Jun-24 12:30 12-Jun-24 16:00 4h Root & Hot...
A1920 IVT-Jt8 06-May-24 06:30 06-May-24 07:00 1h IVT-Jt8

Actual Work Critical Remaining Work Page 2 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A1930 IRT& Film processing-Jt8 06-May-24 17:00 06-May-24 21:00 4h IRT& Film . .
A1940 Fill Up & Cap-Jt8 07-May-24 06:30 07-May-24 13:30 7h Fill Up & ...
A1950 AUT-Jt8 07-May-24 13:30 07-May-24 14:30 1h AUT-Jt8
A1960 FBE coating-Jt-7&8 07-May-24 14:30 07-May-24 16:30 2h FBE coatin...
A1970 Installation of Zinc Rbbon (8nos) 08-May-24 06:30 08-May-24 08:30 2h Installati...
A1980 Pulling of 8th pipe & 9th pipe 08-May-24 08:30 08-May-24 12:30 4h Pulling of...
Pipe 10,11 (Jt 9&10) 08-May-24 13:30 12-May-24 12:30 39h 12-May-24 ...
A1990 Lowering 10th Pipe -TL-15 08-May-24 13:30 08-May-24 15:30 2h Lowering 1...
A2000 Habitat preparation 08-May-24 15:30 09-May-24 07:30 2h Habitat pr...
A2010 Fit up of 9th Joint in pit & Inspection 09-May-24 07:30 09-May-24 09:30 2h Fit up of ...
A2020 Root & Hot Pass Joint No 9 09-May-24 09:30 09-May-24 13:00 4h Root & Hot...
A2030 IVT -Jt-9 09-May-24 13:00 09-May-24 13:30 1h IVT -Jt-9
A2040 IRT & Film processing -Jt9 09-May-24 17:00 09-May-24 21:00 4h IRT & Fil...
A2050 Lowering 11th Pipe -TL-15 10-May-24 06:30 10-May-24 08:30 2h Lowering 1...
A2060 Habitat preparation 10-May-24 08:30 10-May-24 10:30 2h Habitat pr...
A2070 Fit up of 10th Joint in pit & Inspection 10-May-24 10:30 10-May-24 12:30 2h Fit up of ...
A2080 Fill Up & Cap-Jt9 10-May-24 12:30 11-May-24 09:30 7h Fill Up & ...
A2090 AUT-Jt9 11-May-24 09:30 11-May-24 10:30 1h AUT-Jt9
A2110 Root & Hot Pass Joint No 10 10-May-24 12:30 10-May-24 16:00 4h Root & Hot...
A2120 IVT-Jt10 10-May-24 16:00 10-May-24 16:30 1h IVT-Jt10
A2130 IRT& Film processing-Jt10 10-May-24 17:00 10-May-24 21:00 4h IRT& Film . .
A2140 Fill Up & Cap-Jt10 11-May-24 06:30 11-May-24 13:30 7h Fill Up & ...
A2150 AUT-Jt10 11-May-24 13:30 11-May-24 14:30 1h AUT-Jt10
A2160 FBE coating-Jt-9&10 11-May-24 14:30 11-May-24 16:30 2h FBE coatin...
A2170 Installation of Zinc Rbbon (8nos) 12-May-24 06:30 12-May-24 08:30 2h Installati...
A2180 Pulling of 10th pipe & 11th pipe 12-May-24 08:30 12-May-24 12:30 4h Pulling of...
Pipe 12,13 (Jt 11&12) 12-May-24 13:30 17-May-24 12:30 49h 17-May-24 ...
A2190 Lowering 12th Pipe -TL-15 12-May-24 13:30 12-May-24 15:30 2h Lowering 1...
A2200 Habitat preparation 12-May-24 15:30 13-May-24 07:30 2h Habitat pr...
A2210 Fit up of 11th Joint in pit & Inspection 13-May-24 07:30 13-May-24 09:30 2h Fit up of ...
A2220 Root & Hot Pass Joint No 11 13-May-24 09:30 13-May-24 13:00 4h Root & Hot...
A2230 IVT -Jt-11 13-May-24 13:00 13-May-24 13:30 1h IVT -Jt-11
A2240 IRT & Film processing -Jt11 13-May-24 17:00 13-May-24 21:00 4h IRT & Fil...
A2250 Lowering 13th Pipe -TL-15 14-May-24 06:30 14-May-24 08:30 2h Lowering 1...
A2260 Habitat preparation 14-May-24 08:30 14-May-24 10:30 2h Habitat pr...
A2270 Fit up of 12th Joint in pit & Inspection 14-May-24 10:30 14-May-24 12:30 2h Fit up of ...
A2280 Fill Up & Cap-Jt12 14-May-24 12:30 15-May-24 09:30 7h Fill Up & ...
A2290 AUT-Jt12 15-May-24 09:30 15-May-24 10:30 1h AUT-Jt12
A2310 Root & Hot Pass Joint No 12 14-May-24 12:30 14-May-24 16:00 4h Root & Hot...
A2320 IVT-Jt12 15-May-24 10:30 15-May-24 11:00 1h IVT-Jt12
A2330 IRT& Film processing-Jt12 15-May-24 17:00 15-May-24 21:00 4h IRT& Film . .
A2340 Fill Up & Cap-Jt12 16-May-24 06:30 16-May-24 13:30 7h Fill Up & ...
A2350 AUT-Jt12 16-May-24 13:30 16-May-24 14:30 1h AUT-Jt12
A2360 FBE coating-Jt-11&12 16-May-24 14:30 16-May-24 16:30 2h FBE coatin...
A2370 Installation of Zinc Rbbon (8nos) 17-May-24 06:30 17-May-24 08:30 2h Installati...
A2380 Pulling of 12th pipe & 13th pipe 17-May-24 08:30 17-May-24 12:30 4h Pulling of...
TL-21 28-May-24 09:30 23-Jun-24 12:30 263h 23-Jun-24 ...
Pipe 1,2,3( Jt 1 &2) 28-May-24 09:30 02-Jun-24 12:30 53h 02-Jun-24 ...
A2390 Lowering 1st Pipe with pulling head -TL-21(12 mtrs) 28-May-24 09:30 28-May-24 11:30 2h Lowering 1...
A2400 Installation of Zinc Rbbon (4 nos) 28-May-24 11:30 28-May-24 13:30 2h Installati...
A2410 Pulling of 1st pipe( 12 mtr) 28-May-24 13:30 28-May-24 15:30 2h Pulling of...

Actual Work Critical Remaining Work Page 3 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A2420 Lowering 2nd Pipe -TL-21 28-May-24 15:30 29-May-24 07:30 2h Lowering 2...
A2430 Habitat preparation 29-May-24 07:30 29-May-24 09:30 2h Habitat pr...
A2440 Fit up of 1st Joint in pit & Inspection 29-May-24 09:30 29-May-24 11:30 2h Fit up of ...
A2450 Root & Hot Pass Joint No 1 29-May-24 11:30 29-May-24 15:30 4h Root & Hot...
A2460 IVT -Jt-1 29-May-24 15:30 29-May-24 16:30 1h IVT -Jt-1
A2470 IRTRT Film processing-Jt1 29-May-24 17:00 29-May-24 21:00 4h IRTRT Fi...
A2480 Lowering 3rd Pipe -TL-21 30-May-24 08:30 30-May-24 10:30 2h Lowering 3...
A2500 Habitat preparation 30-May-24 10:30 30-May-24 12:30 2h Habitat pr...
A2510 Fit up of 2nd Joint in pit & Inspection 30-May-24 12:30 30-May-24 14:30 2h Fit up of ...
A2520 Root & Hot Pass Joint No 2 30-May-24 14:30 31-May-24 08:30 4h Root & Hot...
A2530 Fill Up & Cap-Jt1 30-May-24 14:30 31-May-24 11:30 7h Fill Up & ...
A2540 AUT-Jt1 31-May-24 11:30 31-May-24 12:30 1h AUT-Jt1
A2560 IVT-Jt2 31-May-24 08:30 31-May-24 09:30 1h IVT-Jt2
A2570 IRT& Film processing-Jt2 31-May-24 17:00 31-May-24 21:00 4h IRT& Film . .
A2580 Fill Up & Cap-Jt2 01-Jun-24 06:30 01-Jun-24 13:30 7h Fill Up & ...
A2590 AUT-Jt2 01-Jun-24 13:30 01-Jun-24 14:30 1h AUT-Jt2
A2600 FBE coating-Jt-1& 2 01-Jun-24 14:30 01-Jun-24 16:30 2h FBE coatin...
A2610 Installation of Zinc Rbbon (8 nos) both Pipes 2&3 02-Jun-24 06:30 02-Jun-24 08:30 2h Installati...
A2620 Pulling of 2nd pipe & 3rd Pipe 02-Jun-24 08:30 02-Jun-24 12:30 4h Pulling of...
Pipe 4,5 (Jt 3&4) 02-Jun-24 12:30 06-Jun-24 12:30 40h 06-Jun-24 ...
A2630 Lowering 4th Pipe -TL-21 02-Jun-24 12:30 02-Jun-24 14:30 2h Lowering 4...
A2640 Habitat preparation 02-Jun-24 14:30 02-Jun-24 16:30 2h Habitat pr...
A2650 Fit up of 3rd Joint in pit & Inspection 03-Jun-24 06:30 03-Jun-24 08:30 2h Fit up of ...
A2660 Root & Hot Pass Joint No 3 03-Jun-24 08:30 03-Jun-24 12:00 4h Root & Hot...
A2670 IVT -Jt-3 03-Jun-24 12:00 03-Jun-24 12:30 1h IVT -Jt-3
A2680 IRT & Film processing -Jt3 03-Jun-24 17:00 03-Jun-24 21:00 4h IRT & Fil ...
A2690 Lowering 5th Pipe -TL-21 04-Jun-24 06:30 04-Jun-24 08:30 2h Lowering 5...
A2700 Habitat preparation 04-Jun-24 08:30 04-Jun-24 10:30 2h Habitat pr...
A2710 Fit up of 4th Joint in pit & Inspection 04-Jun-24 10:30 04-Jun-24 12:30 2h Fit up of ...
A2720 Root & Hot Pass Joint No 4 04-Jun-24 12:30 04-Jun-24 16:00 4h Root & Hot...
A2730 Fill Up & Cap-Jt3 04-Jun-24 12:30 05-Jun-24 09:30 7h Fill Up & ...
A2740 AUT-Jt3 05-Jun-24 09:30 05-Jun-24 10:30 1h AUT-Jt3
A2760 IVT-Jt4 04-Jun-24 16:00 04-Jun-24 16:30 1h IVT-Jt4
A2770 IRT& Film processing-Jt4 04-Jun-24 17:00 04-Jun-24 21:00 4h IRT& Film . .
A2780 Fill Up & Cap-Jt4 05-Jun-24 06:30 05-Jun-24 13:30 7h Fill Up & ...
A2790 AUT-Jt4 05-Jun-24 13:30 05-Jun-24 14:30 1h AUT-Jt4
A2800 FBE coating-Jt-3&4 05-Jun-24 14:30 05-Jun-24 16:30 2h FBE coatin...
A2810 Installation of Zinc Rbbon (8nos) 06-Jun-24 06:30 06-Jun-24 08:30 2h Installati...
A2820 Pulling of 4th pipe & 5th pipe 06-Jun-24 08:30 06-Jun-24 12:30 4h Pulling of...
Pipe 6,7 (Jt 5&6) 07-Jun-24 06:30 11-Jun-24 12:30 46h 11-Jun-24 ...
A2830 Lowering 6th Pipe -TL-21 07-Jun-24 06:30 07-Jun-24 08:30 2h Lowering 6...
A2840 Habitat preparation 07-Jun-24 08:30 07-Jun-24 10:30 2h Habitat pr...
A2850 Fit up of 5th Joint in pit & Inspection 07-Jun-24 10:30 07-Jun-24 12:30 2h Fit up of ...
A2860 Root & Hot Pass Joint No 5 07-Jun-24 12:30 07-Jun-24 16:00 4h Root & Hot...
A2870 IVT -Jt-5 07-Jun-24 16:00 07-Jun-24 16:30 1h IVT -Jt-5
A2880 IRT & Film processing -Jt5 07-Jun-24 17:00 07-Jun-24 21:00 4h IRT & Fil ...
A2890 Lowering 7th Pipe -TL-21 08-Jun-24 09:30 08-Jun-24 11:30 2h Lowering 7...
A2900 Habitat preparation 08-Jun-24 11:30 08-Jun-24 13:30 2h Habitat pr...
A2910 Fit up of 6th Joint in pit & Inspection 08-Jun-24 13:30 08-Jun-24 15:30 2h Fit up of ...
A2920 Fill Up & Cap-Jt5 08-Jun-24 15:30 09-Jun-24 12:30 7h Fill Up & ...
A2930 AUT-Jt5 09-Jun-24 12:30 09-Jun-24 13:30 1h AUT-Jt5

Actual Work Critical Remaining Work Page 4 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A2950 Root & Hot Pass Joint No 6 08-Jun-24 15:30 09-Jun-24 09:00 4h Root & Hot...
A2960 IVT-Jt6 09-Jun-24 09:00 09-Jun-24 09:30 1h IVT-Jt6
A2970 IRT& Film processing-Jt6 09-Jun-24 17:00 09-Jun-24 21:00 4h IRT& Film...
A2980 Fill Up & Cap-Jt6 10-Jun-24 06:30 10-Jun-24 13:30 7h Fill Up & ...
A2990 AUT-Jt6 10-Jun-24 13:30 10-Jun-24 14:30 1h AUT-Jt6
A3000 FBE coating-Jt-5&6 10-Jun-24 14:30 10-Jun-24 16:30 2h FBE coatin...
A3010 Installation of Zinc Rbbon (8nos) 11-Jun-24 06:30 11-Jun-24 08:30 2h Installati...
A3020 Pulling of 6th pipe & 7th pipe 11-Jun-24 08:30 11-Jun-24 12:30 4h Pulling of...
Pipe 8,9 (Jt 7&8) 11-Jun-24 12:30 15-Jun-24 12:30 40h 15-Jun-24 ...
A3030 Lowering 8th Pipe -TL-21 11-Jun-24 12:30 11-Jun-24 14:30 2h Lowering 8...
A3040 Habitat preparation 11-Jun-24 14:30 11-Jun-24 16:30 2h Habitat pr...
A3050 Fit up of 7th Joint in pit & Inspection 12-Jun-24 06:30 12-Jun-24 08:30 2h Fit up of ...
A3060 Root & Hot Pass Joint No 7 12-Jun-24 08:30 12-Jun-24 12:00 4h Root & Hot...
A3070 IVT -Jt-7 12-Jun-24 12:00 12-Jun-24 12:30 1h IVT -Jt-7
A3080 IRT & Film processing -Jt7 12-Jun-24 17:00 12-Jun-24 21:00 4h IRT & Fil ...
A3090 Lowering 9th Pipe -TL-21 13-Jun-24 06:30 13-Jun-24 08:30 2h Lowering 9...
A3100 Habitat preparation 13-Jun-24 08:30 13-Jun-24 10:30 2h Habitat pr...
A3110 Fit up of 8th Joint in pit & Inspection 13-Jun-24 10:30 13-Jun-24 12:30 2h Fit up of ...
A3120 Fill Up & Cap-Jt7 13-Jun-24 12:30 14-Jun-24 09:30 7h Fill Up & ...
A3130 AUT-Jt7 14-Jun-24 09:30 14-Jun-24 10:30 1h AUT-Jt7
A3150 Root & Hot Pass Joint No 7 13-Jun-24 12:30 13-Jun-24 16:00 4h Root & Hot...
A3160 IVT-Jt7 13-Jun-24 16:00 13-Jun-24 16:30 1h IVT-Jt7
A3170 IRT& Film processing-Jt7 13-Jun-24 17:00 13-Jun-24 21:00 4h IRT& Film . .
A3180 Fill Up & Cap-Jt7 14-Jun-24 06:30 14-Jun-24 13:30 7h Fill Up & ...
A3190 AUT-Jt7 14-Jun-24 13:30 14-Jun-24 14:30 1h AUT-Jt7
A3200 FBE coating-Jt-7&8 14-Jun-24 14:30 14-Jun-24 16:30 2h FBE coatin...
A3210 Installation of Zinc Rbbon (8nos) 15-Jun-24 06:30 15-Jun-24 08:30 2h Installati...
A3220 Pulling of 8th pipe & 9th pipe 15-Jun-24 08:30 15-Jun-24 12:30 4h Pulling of...
Pipe 10,11 (Jt 9&10) 15-Jun-24 12:30 19-Jun-24 12:30 40h 19-Jun-24 ...
A3230 Lowering 10th Pipe -TL-21 15-Jun-24 12:30 15-Jun-24 14:30 2h Lowering 1...
A3240 Habitat preparation 15-Jun-24 14:30 15-Jun-24 16:30 2h Habitat pr...
A3250 Fit up of 9th Joint in pit & Inspection 16-Jun-24 06:30 16-Jun-24 08:30 2h Fit up of ...
A3260 Root & Hot Pass Joint No 9 16-Jun-24 08:30 16-Jun-24 12:00 4h Root & Hot...
A3270 IVT -Jt-9 16-Jun-24 12:00 16-Jun-24 12:30 1h IVT -Jt-9
A3280 IRT & Film processing -Jt9 16-Jun-24 17:00 16-Jun-24 21:00 4h IRT & Fil ...
A3290 Lowering 11th Pipe -TL-21 17-Jun-24 06:30 17-Jun-24 08:30 2h Lowering 1...
A3300 Habitat preparation 17-Jun-24 08:30 17-Jun-24 10:30 2h Habitat pr...
A3310 Fit up of 10th Joint in pit & Inspection 17-Jun-24 10:30 17-Jun-24 12:30 2h Fit up of ...
A3320 Fill Up & Cap-Jt9 17-Jun-24 12:30 18-Jun-24 09:30 7h Fill Up & ...
A3330 AUT-Jt9 18-Jun-24 09:30 18-Jun-24 10:30 1h AUT-Jt9
A3350 Root & Hot Pass Joint No 10 17-Jun-24 12:30 17-Jun-24 16:00 4h Root & Hot...
A3360 IVT-Jt10 17-Jun-24 16:00 17-Jun-24 16:30 1h IVT-Jt10
A3370 IRT& Film processing-Jt10 17-Jun-24 17:00 17-Jun-24 21:00 4h IRT& Film . .
A3380 Fill Up & Cap-Jt10 18-Jun-24 06:30 18-Jun-24 13:30 7h Fill Up & ...
A3390 AUT-Jt10 18-Jun-24 13:30 18-Jun-24 14:30 1h AUT-Jt10
A3400 FBE coating-Jt-9&10 18-Jun-24 14:30 18-Jun-24 16:30 2h FBE coatin...
A3410 Installation of Zinc Rbbon (8nos) 19-Jun-24 06:30 19-Jun-24 08:30 2h Installati...
A3420 Pulling of 10th pipe & 11th pipe 19-Jun-24 08:30 19-Jun-24 12:30 4h Pulling of...
Pipe 12,13 (Jt 11&12) 19-Jun-24 12:30 23-Jun-24 12:30 40h 23-Jun-24 ...
A3430 Lowering 12th Pipe -TL-21 19-Jun-24 12:30 19-Jun-24 14:30 2h Lowering 1...
A3440 Habitat preparation 19-Jun-24 14:30 19-Jun-24 16:30 2h Habitat pr...

Actual Work Critical Remaining Work Page 5 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A3450 Fit up of 11th Joint in pit & Inspection 20-Jun-24 06:30 20-Jun-24 08:30 2h Fit up of ...
A3460 Root & Hot Pass Joint No 11 20-Jun-24 08:30 20-Jun-24 12:00 4h Root & Hot...
A3470 IVT -Jt-11 20-Jun-24 12:00 20-Jun-24 12:30 1h IVT -Jt-11
A3480 IRT & Film processing -Jt11 20-Jun-24 17:00 20-Jun-24 21:00 4h IRT & Fil ...
A3490 Lowering 13th Pipe -TL-21 21-Jun-24 06:30 21-Jun-24 08:30 2h Lowering 1...
A3500 Habitat preparation 21-Jun-24 08:30 21-Jun-24 10:30 2h Habitat pr...
A3510 Fit up of 12th Joint in pit & Inspection 21-Jun-24 10:30 21-Jun-24 12:30 2h Fit up of ...
A3520 Fill Up & Cap-Jt11 21-Jun-24 12:30 22-Jun-24 09:30 7h Fill Up & ...
A3530 AUT-Jt11 22-Jun-24 09:30 22-Jun-24 10:30 1h AUT-Jt11
A3550 Root & Hot Pass Joint No 12 21-Jun-24 12:30 21-Jun-24 16:00 4h Root & Hot...
A3560 IVT-Jt12 21-Jun-24 16:00 21-Jun-24 16:30 1h IVT-Jt12
A3570 IRT& Film processing-Jt12 21-Jun-24 17:00 21-Jun-24 21:00 4h IRT& Film . .
A3580 Fill Up & Cap-Jt12 22-Jun-24 06:30 22-Jun-24 13:30 7h Fill Up & ...
A3590 AUT-Jt12 22-Jun-24 13:30 22-Jun-24 14:30 1h AUT-Jt12
A3600 FBE coating-Jt-11&12 22-Jun-24 14:30 22-Jun-24 16:30 2h FBE coatin...
A3610 Installation of Zinc Rbbon (8nos) 23-Jun-24 06:30 23-Jun-24 08:30 2h Installati...
A3620 Pulling of 12th pipe & 13th pipe 23-Jun-24 08:30 23-Jun-24 12:30 4h Pulling of...
TL-17 17-May-24 12:30 15-Jun-24 12:30 290h 15-Jun-24 ...
Pipe 1,2,3( Jt 1 &2) 17-May-24 12:30 26-May-24 12:30 90h 26-May-24 ...
A4865 Removal of Pulling Head from TL-15 & Installtion on TL-17 17-May-24 12:30 20-May-24 12:30 30h Removal of...
A4870 Lowering 1st Pipe with pulling head -TL-17(12 mrs) 20-May-24 12:30 20-May-24 14:30 2h Lowering 1...
A4880 Installation of Zinc Rbbon (4 nos) 20-May-24 14:30 20-May-24 16:30 2h Installati...
A4890 Pulling of 1st pipe( 12 mtr) 21-May-24 06:30 21-May-24 08:30 2h Pulling of...
A4900 Lowering 2nd Pipe -TL-17 21-May-24 08:30 21-May-24 10:30 2h Lowering 2...
A4910 Habitat preparation 21-May-24 10:30 21-May-24 12:30 2h Habitat pr...
A4920 Fit up of 1st Joint in pit & Inspection 21-May-24 12:30 21-May-24 14:30 2h Fit up of ...
A4930 Root & Hot Pass Joint No 1 21-May-24 14:30 22-May-24 08:30 4h Root & Hot...
A4940 IVT -Jt-1 22-May-24 08:30 22-May-24 09:30 1h IVT -Jt-1
A4950 IRTFil m processing-Jt1 22-May-24 17:00 22-May-24 19:00 2h IRTFil m p...
A4960 Lowering 3rd Pipe -TL-17 23-May-24 06:30 23-May-24 08:30 2h Lowering 3...
A4980 Habitat preparation 23-May-24 08:30 23-May-24 10:30 2h Habitat pr...
A4990 Fit up of 2nd Joint in pit & Inspection 23-May-24 10:30 23-May-24 12:30 2h Fit up of ...
A5000 Root & Hot Pass Joint No 2 23-May-24 12:30 23-May-24 16:30 4h Root & Hot...
A5010 Fill Up & Cap-Jt1 23-May-24 12:30 24-May-24 09:30 7h Fill Up & ...
A5020 AUT-Jt1 24-May-24 09:30 24-May-24 10:30 1h AUT-Jt1
A5030 FBE coating -Jt1 24-May-24 10:30 24-May-24 12:30 2h FBE coatin...
A5040 IVT-Jt2 24-May-24 06:30 24-May-24 07:30 1h IVT-Jt2
A5050 IRT& Film processing-Jt2 24-May-24 17:00 24-May-24 21:00 4h IRT& Film...
A5060 Fill Up & Cap-Jt2 25-May-24 06:30 25-May-24 13:30 7h Fill Up & ...
A5070 AUT-Jt2 25-May-24 13:30 25-May-24 14:30 1h AUT-Jt2
A5080 FBE coating-Jt-1& 2 25-May-24 14:30 25-May-24 16:30 2h FBE coatin...
A5090 Installation of Zinc Rbbon (8 nos) both Pipes 2&3 26-May-24 06:30 26-May-24 08:30 2h Installati...
A5100 Pulling of 2nd pipe & 3rd Pipe 26-May-24 08:30 26-May-24 12:30 4h Pulling of...
Pipe 4,5 (Jt 3&4) 26-May-24 13:30 30-May-24 12:30 39h 30-May-24 ...
A5110 Lowering 4th Pipe -TL-17 26-May-24 13:30 26-May-24 15:30 2h Lowering 4...
A5120 Habitat preparation 26-May-24 15:30 27-May-24 07:30 2h Habitat pr...
A5130 Fit up of 3rd Joint in pit & Inspection 27-May-24 07:30 27-May-24 09:30 2h Fit up of ...
A5140 Root & Hot Pass Joint No 3 27-May-24 09:30 27-May-24 13:00 4h Root & Hot...
A5150 IVT -Jt-3 27-May-24 13:00 27-May-24 13:30 1h IVT -Jt-3
A5160 IRT & Film processing -Jt3 27-May-24 17:00 27-May-24 21:00 4h IRT & Fil ...
A5170 Lowering 5th Pipe -TL-17 28-May-24 06:30 28-May-24 08:30 2h Lowering 5...

Actual Work Critical Remaining Work Page 6 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A5180 Habitat preparation 28-May-24 08:30 28-May-24 10:30 2h Habitat pr...
A5190 Fit up of 4th Joint in pit & Inspection 28-May-24 10:30 28-May-24 12:30 2h Fit up of ...
A5200 Fill Up & Cap-Jt3 28-May-24 12:30 29-May-24 09:30 7h Fill Up & ...
A5210 AUT-Jt3 29-May-24 09:30 29-May-24 10:30 1h AUT-Jt3
A5230 Root & Hot Pass Joint No 4 28-May-24 12:30 28-May-24 16:00 4h Root & Hot...
A5240 IVT-Jt4 28-May-24 16:00 28-May-24 16:30 1h IVT-Jt4
A5250 IRT& Film processing-Jt4 28-May-24 17:00 28-May-24 21:00 4h IRT& Film...
A5260 Fill Up & Cap-Jt4 29-May-24 06:30 29-May-24 13:30 7h Fill Up & ...
A5270 AUT-Jt4 29-May-24 13:30 29-May-24 14:30 1h AUT-Jt4
A5280 FBE coating-Jt-3&4 29-May-24 14:30 29-May-24 16:30 2h FBE coatin...
A5290 Installation of Zinc Rbbon (8nos) 30-May-24 06:30 30-May-24 08:30 2h Installati...
A5300 Pulling of 4th pipe & 5th pipe 30-May-24 08:30 30-May-24 12:30 4h Pulling of...
Pipe 6,7 (Jt 5&6) 30-May-24 13:30 03-Jun-24 12:30 39h 03-Jun-24 ...
A5310 Lowering 6th Pipe -TL-17 30-May-24 13:30 30-May-24 15:30 2h Lowering 6...
A5320 Habitat preparation 30-May-24 15:30 31-May-24 07:30 2h Habitat pr...
A5330 Fit up of 5th Joint in pit & Inspection 31-May-24 07:30 31-May-24 09:30 2h Fit up of ...
A5340 Root & Hot Pass Joint No 5 31-May-24 09:30 31-May-24 13:00 4h Root & Hot...
A5350 IVT -Jt-5 31-May-24 13:00 31-May-24 13:30 1h IVT -Jt-5
A5360 IRT & Film processing -Jt5 31-May-24 17:00 31-May-24 21:00 4h IRT & Fil ...
A5370 Lowering 7th Pipe -TL-17 01-Jun-24 06:30 01-Jun-24 08:30 2h Lowering 7...
A5380 Habitat preparation 01-Jun-24 08:30 01-Jun-24 10:30 2h Habitat pr...
A5390 Fit up of 6th Joint in pit & Inspection 01-Jun-24 10:30 01-Jun-24 12:30 2h Fit up of ...
A5400 Fill Up & Cap-Jt5 01-Jun-24 12:30 02-Jun-24 09:30 7h Fill Up & ...
A5410 AUT-Jt5 02-Jun-24 09:30 02-Jun-24 10:30 1h AUT-Jt5
A5430 Root & Hot Pass Joint No 6 01-Jun-24 12:30 01-Jun-24 16:00 4h Root & Hot...
A5440 IVT-Jt6 01-Jun-24 16:00 01-Jun-24 16:30 1h IVT-Jt6
A5450 IRT& Film processing-Jt6 01-Jun-24 17:00 01-Jun-24 21:00 4h IRT& Film...
A5460 Fill Up & Cap-Jt6 02-Jun-24 06:30 02-Jun-24 13:30 7h Fill Up & ...
A5470 AUT-Jt6 02-Jun-24 13:30 02-Jun-24 14:30 1h AUT-Jt6
A5480 FBE coating-Jt-5&6 02-Jun-24 14:30 02-Jun-24 16:30 2h FBE coatin...
A5490 Installation of Zinc Rbbon (8nos) 03-Jun-24 06:30 03-Jun-24 08:30 2h Installati...
A5500 Pulling of 6th pipe & 7th pipe 03-Jun-24 08:30 03-Jun-24 12:30 4h Pulling of...
Pipe 8,9 (Jt 7&8) 03-Jun-24 13:30 07-Jun-24 12:30 39h 07-Jun-24 ...
A5510 Lowering 8th Pipe -TL-17 03-Jun-24 13:30 03-Jun-24 15:30 2h Lowering 8...
A5520 Habitat preparation 03-Jun-24 15:30 04-Jun-24 07:30 2h Habitat pr...
A5530 Fit up of 7th Joint in pit & Inspection 04-Jun-24 07:30 04-Jun-24 09:30 2h Fit up of ...
A5540 Root & Hot Pass Joint No 7 04-Jun-24 09:30 04-Jun-24 13:00 4h Root & Hot...
A5550 IVT -Jt-7 04-Jun-24 13:00 04-Jun-24 13:30 1h IVT -Jt-7
A5560 IRT & Film processing -Jt7 04-Jun-24 17:00 04-Jun-24 21:00 4h IRT & Fil ...
A5570 Lowering 9th Pipe -TL-17 05-Jun-24 06:30 05-Jun-24 08:30 2h Lowering 9...
A5580 Habitat preparation 05-Jun-24 08:30 05-Jun-24 10:30 2h Habitat pr...
A5590 Fit up of 8th Joint in pit & Inspection 05-Jun-24 10:30 05-Jun-24 12:30 2h Fit up of ...
A5600 Fill Up & Cap-Jt7 05-Jun-24 12:30 06-Jun-24 09:30 7h Fill Up & ...
A5610 AUT-Jt7 06-Jun-24 09:30 06-Jun-24 10:30 1h AUT-Jt7
A5630 Root & Hot Pass Joint No 8 05-Jun-24 08:30 05-Jun-24 12:00 4h Root & Hot...
A5640 IVT-Jt8 05-Jun-24 12:00 05-Jun-24 12:30 1h IVT-Jt8
A5650 IRT& Film processing-Jt8 05-Jun-24 17:00 05-Jun-24 21:00 4h IRT& Film...
A5660 Fill Up & Cap-Jt8 06-Jun-24 06:30 06-Jun-24 13:30 7h Fill Up & ...
A5670 AUT-Jt8 06-Jun-24 13:30 06-Jun-24 14:30 1h AUT-Jt8
A5680 FBE coating-Jt-7&8 06-Jun-24 14:30 06-Jun-24 16:30 2h FBE coatin...
A5690 Installation of Zinc Rbbon (8nos) 07-Jun-24 06:30 07-Jun-24 08:30 2h Installati...

Actual Work Critical Remaining Work Page 7 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A5700 Pulling of 8th pipe & 9th pipe 07-Jun-24 08:30 07-Jun-24 12:30 4h Pulling of...
Pipe 10,11 (Jt 9&10) 07-Jun-24 13:30 11-Jun-24 12:30 39h 11-Jun-24 ...
A5710 Lowering 10th Pipe -TL-17 07-Jun-24 13:30 07-Jun-24 15:30 2h Lowering 1...
A5720 Habitat preparation 07-Jun-24 15:30 08-Jun-24 07:30 2h Habitat pr...
A5730 Fit up of 9th Joint in pit & Inspection 08-Jun-24 07:30 08-Jun-24 09:30 2h Fit up of ...
A5740 Root & Hot Pass Joint No 9 08-Jun-24 09:30 08-Jun-24 13:00 4h Root & Hot...
A5750 IVT -Jt-9 08-Jun-24 13:00 08-Jun-24 13:30 1h IVT -Jt-9
A5760 IRT & Film processing -Jt9 08-Jun-24 17:00 08-Jun-24 21:00 4h IRT & Fil ...
A5770 Lowering 11th Pipe -TL-17 09-Jun-24 06:30 09-Jun-24 08:30 2h Lowering 1...
A5780 Habitat preparation 09-Jun-24 08:30 09-Jun-24 10:30 2h Habitat pr...
A5790 Fit up of 10th Joint in pit & Inspection 09-Jun-24 10:30 09-Jun-24 12:30 2h Fit up of ...
A5800 Fill Up & Cap-Jt9 09-Jun-24 12:30 10-Jun-24 09:30 7h Fill Up & ...
A5810 AUT-Jt9 10-Jun-24 09:30 10-Jun-24 10:30 1h AUT-Jt9
A5830 Root & Hot Pass Joint No 10 09-Jun-24 12:30 09-Jun-24 16:00 4h Root & Hot...
A5840 IVT-Jt10 09-Jun-24 16:00 09-Jun-24 16:30 1h IVT-Jt10
A5850 IRT& Film processing-Jt10 09-Jun-24 17:00 09-Jun-24 21:00 4h IRT& Film...
A5860 Fill Up & Cap-Jt10 10-Jun-24 06:30 10-Jun-24 13:30 7h Fill Up & ...
A5870 AUT-Jt10 10-Jun-24 13:30 10-Jun-24 14:30 1h AUT-Jt10
A5880 FBE coating-Jt-9&10 10-Jun-24 14:30 10-Jun-24 16:30 2h FBE coatin...
A5890 Installation of Zinc Rbbon (8nos) 11-Jun-24 06:30 11-Jun-24 08:30 2h Installati...
A5900 Pulling of 10th pipe & 11th pipe 11-Jun-24 08:30 11-Jun-24 12:30 4h Pulling of...
Pipe 12,13 (Jt 11&12) 11-Jun-24 13:30 15-Jun-24 12:30 39h 15-Jun-24 ...
A5910 Lowering 12th Pipe -TL-17 11-Jun-24 13:30 11-Jun-24 15:30 2h Lowering 1...
A5920 Habitat preparation 11-Jun-24 15:30 12-Jun-24 07:30 2h Habitat pr...
A5930 Fit up of 11th Joint in pit & Inspection 12-Jun-24 07:30 12-Jun-24 09:30 2h Fit up of ...
A5940 Root & Hot Pass Joint No 11 12-Jun-24 09:30 12-Jun-24 13:00 4h Root & Hot...
A5950 IVT -Jt-11 12-Jun-24 13:00 12-Jun-24 13:30 1h IVT -Jt-11
A5960 IRT & Film processing -Jt11 12-Jun-24 17:00 12-Jun-24 21:00 4h IRT & Fil ...
A5970 Lowering 13th Pipe -TL-17 13-Jun-24 06:30 13-Jun-24 08:30 2h Lowering 1...
A5980 Habitat preparation 13-Jun-24 08:30 13-Jun-24 10:30 2h Habitat pr...
A5990 Fit up of 12th Joint in pit & Inspection 13-Jun-24 10:30 13-Jun-24 12:30 2h Fit up of ...
A6000 Fill Up & Cap-Jt11 13-Jun-24 12:30 14-Jun-24 09:30 7h Fill Up & ...
A6010 AUT-Jt11 14-Jun-24 09:30 14-Jun-24 10:30 1h AUT-Jt11
A6030 Root & Hot Pass Joint No 12 13-Jun-24 12:30 13-Jun-24 16:00 4h Root & Hot...
A6040 IVT-Jt12 13-Jun-24 16:00 13-Jun-24 16:30 1h IVT-Jt12
A6050 IRT& Film processing-Jt12 13-Jun-24 17:00 13-Jun-24 21:00 4h IRT& Film . .
A6060 Fill Up & Cap-Jt12 14-Jun-24 06:30 14-Jun-24 13:30 7h Fill Up & ...
A6070 AUT-Jt12 14-Jun-24 13:30 14-Jun-24 14:30 1h AUT-Jt12
A6080 FBE coating-Jt-11&12 14-Jun-24 14:30 14-Jun-24 16:30 2h FBE coatin...
A6090 Installation of Zinc Rbbon (8nos) 15-Jun-24 06:30 15-Jun-24 08:30 2h Installati...
A6100 Pulling of 12th pipe & 13th pipe 15-Jun-24 08:30 15-Jun-24 12:30 4h Pulling of...
TL-19 26-Jun-24 12:30 26-Jul-24 12:30 300h 26-Jul-24 ...
Pipe 1,2,3( Jt 1 &2) 26-Jun-24 12:30 06-Jul-24 12:30 100h 06-Jul-24 ...
A3625 Removal of Pulling Head from TL-21 & Installtion on TL-19 26-Jun-24 12:30 30-Jun-24 12:30 40h Removal of...
A3630 Lowering 1st Pipe with pulling head -TL-19(12 mrs) 30-Jun-24 12:30 30-Jun-24 14:30 2h Lowering 1...
A3640 Installation of Zinc Rbbon (4 nos) 30-Jun-24 14:30 30-Jun-24 16:30 2h Installati...
A3650 Pulling of 1st pipe( 12 mtr) 01-Jul-24 06:30 01-Jul-24 08:30 2h Pulling of...
A3660 Lowering 2nd Pipe -TL-19 01-Jul-24 08:30 01-Jul-24 10:30 2h Lowering 2...
A3670 Habitat preparation 01-Jul-24 10:30 01-Jul-24 12:30 2h Habitat pr...
A3680 Fit up of 1st Joint in pit & Inspection 01-Jul-24 12:30 01-Jul-24 14:30 2h Fit up of ...
A3690 Root & Hot Pass Joint No 1 01-Jul-24 14:30 02-Jul-24 08:30 4h Root & Hot...

Actual Work Critical Remaining Work Page 8 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A3700 IVT -Jt-1 02-Jul-24 08:30 02-Jul-24 09:30 1h IVT -Jt-1
A3710 IRT& Film Processing-Jt1 02-Jul-24 17:00 02-Jul-24 21:00 4h IRT& Film . .
A3720 Lowering 3rd Pipe -TL-19 03-Jul-24 06:30 03-Jul-24 08:30 2h Lowering 3...
A3740 Habitat preparation 03-Jul-24 08:30 03-Jul-24 10:30 2h Habitat pr...
A3750 Fit up of 2nd Joint in pit & Inspection 03-Jul-24 10:30 03-Jul-24 12:30 2h Fit up of ...
A3760 Root & Hot Pass Joint No 2 03-Jul-24 12:30 03-Jul-24 16:30 4h Root & Hot...
A3770 Fill Up & Cap-Jt1 03-Jul-24 12:30 04-Jul-24 09:30 7h Fill Up & ...
A3780 AUT-Jt1 04-Jul-24 09:30 04-Jul-24 10:30 1h AUT-Jt1
A3790 FBE coating -Jt1 04-Jul-24 10:30 04-Jul-24 12:30 2h FBE coatin...
A3800 IVT-Jt2 04-Jul-24 06:30 04-Jul-24 07:30 1h IVT-Jt2
A3810 IRT& Film processing-Jt2 04-Jul-24 17:00 04-Jul-24 21:00 4h IRT& Film...
A3820 Fill Up & Cap-Jt2 05-Jul-24 06:30 05-Jul-24 13:30 7h Fill Up & ...
A3830 AUT-Jt2 05-Jul-24 13:30 05-Jul-24 14:30 1h AUT-Jt2
A3840 FBE coating-Jt-1& 2 05-Jul-24 14:30 05-Jul-24 16:30 2h FBE coatin...
A3850 Installation of Zinc Rbbon (8 nos) both Pipes 2&3 06-Jul-24 06:30 06-Jul-24 08:30 2h Installati...
A3860 Pulling of 2nd pipe & 3rd Pipe 06-Jul-24 08:30 06-Jul-24 12:30 4h Pulling of...
Pipe 4,5 (Jt 3&4) 06-Jul-24 13:30 10-Jul-24 12:30 39h 10-Jul-24 ...
A3870 Lowering 4th Pipe -TL-19 06-Jul-24 13:30 06-Jul-24 15:30 2h Lowering 4...
A3880 Habitat preparation 06-Jul-24 15:30 07-Jul-24 07:30 2h Habitat pr...
A3890 Fit up of 3rd Joint in pit & Inspection 07-Jul-24 07:30 07-Jul-24 09:30 2h Fit up of ...
A3900 Root & Hot Pass Joint No 3 07-Jul-24 09:30 07-Jul-24 13:00 4h Root & Hot...
A3910 IVT -Jt-3 07-Jul-24 13:00 07-Jul-24 13:30 1h IVT -Jt-3
A3920 IRT & Film processing -Jt3 07-Jul-24 17:00 07-Jul-24 21:00 4h IRT & Fil...
A3930 Lowering 5th Pipe -TL-19 08-Jul-24 06:30 08-Jul-24 08:30 2h Lowering 5...
A3940 Habitat preparation 08-Jul-24 08:30 08-Jul-24 10:30 2h Habitat pr...
A3950 Fit up of 4th Joint in pit & Inspection 08-Jul-24 10:30 08-Jul-24 12:30 2h Fit up of ...
A3960 Fill Up & Cap-Jt3 08-Jul-24 12:30 09-Jul-24 09:30 7h Fill Up & ...
A3970 AUT-Jt3 09-Jul-24 09:30 09-Jul-24 10:30 1h AUT-Jt3
A3990 Root & Hot Pass Joint No 4 08-Jul-24 12:30 08-Jul-24 16:00 4h Root & Hot...
A4000 IVT-Jt4 08-Jul-24 16:00 08-Jul-24 16:30 1h IVT-Jt4
A4010 IRT& Film processing-Jt4 08-Jul-24 17:00 08-Jul-24 21:00 4h IRT& Film...
A4020 Fill Up & Cap-Jt4 09-Jul-24 06:30 09-Jul-24 13:30 7h Fill Up & ...
A4030 AUT-Jt4 09-Jul-24 13:30 09-Jul-24 14:30 1h AUT-Jt4
A4040 FBE coating-Jt-3&4 09-Jul-24 14:30 09-Jul-24 16:30 2h FBE coatin...
A4050 Installation of Zinc Rbbon (8nos) 10-Jul-24 06:30 10-Jul-24 08:30 2h Installati...
A4060 Pulling of 4th pipe & 5th pipe 10-Jul-24 08:30 10-Jul-24 12:30 4h Pulling of...
Pipe 6,7 (Jt 5&6) 10-Jul-24 13:30 14-Jul-24 12:30 39h 14-Jul-24 ...
A4070 Lowering 6th Pipe -TL-19 10-Jul-24 13:30 10-Jul-24 15:30 2h Lowering 6...
A4080 Habitat preparation 10-Jul-24 15:30 11-Jul-24 07:30 2h Habitat pr...
A4090 Fit up of 5th Joint in pit & Inspection 11-Jul-24 07:30 11-Jul-24 09:30 2h Fit up of ...
A4100 Root & Hot Pass Joint No 5 11-Jul-24 09:30 11-Jul-24 13:00 4h Root & Hot...
A4110 IVT -Jt-5 11-Jul-24 13:00 11-Jul-24 13:30 1h IVT -Jt-5
A4120 IRT & Film processing -Jt5 11-Jul-24 17:00 11-Jul-24 21:00 4h IRT & Fil ...
A4130 Lowering 7th Pipe -TL-19 12-Jul-24 06:30 12-Jul-24 08:30 2h Lowering 7...
A4140 Habitat preparation 12-Jul-24 08:30 12-Jul-24 10:30 2h Habitat pr...
A4150 Fit up of 6th Joint in pit & Inspection 12-Jul-24 10:30 12-Jul-24 12:30 2h Fit up of ...
A4160 Fill Up & Cap-Jt5 12-Jul-24 12:30 13-Jul-24 09:30 7h Fill Up & ...
A4170 AUT-Jt5 13-Jul-24 09:30 13-Jul-24 10:30 1h AUT-Jt5
A4190 Root & Hot Pass Joint No 6 12-Jul-24 12:30 12-Jul-24 16:00 4h Root & Hot...
A4200 IVT-Jt5 12-Jul-24 16:00 12-Jul-24 16:30 1h IVT-Jt5
A4210 IRT& Film processing-Jt5 12-Jul-24 17:00 12-Jul-24 21:00 4h IRT& Film...

Actual Work Critical Remaining Work Page 9 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A4220 Fill Up & Cap-Jt5 13-Jul-24 06:30 13-Jul-24 13:30 7h Fill Up & ...
A4230 AUT-Jt5 13-Jul-24 13:30 13-Jul-24 14:30 1h AUT-Jt5
A4240 FBE coating-Jt-5&6 13-Jul-24 14:30 13-Jul-24 16:30 2h FBE coatin...
A4250 Installation of Zinc Rbbon (8nos) 14-Jul-24 06:30 14-Jul-24 08:30 2h Installati...
A4260 Pulling of 6th pipe & 7th pipe 14-Jul-24 08:30 14-Jul-24 12:30 4h Pulling of...
Pipe 8,9 (Jt 7&8) 14-Jul-24 13:30 18-Jul-24 12:30 39h 18-Jul-24 ...
A4270 Lowering 8th Pipe -TL-19 14-Jul-24 13:30 14-Jul-24 15:30 2h Lowering 8...
A4280 Habitat preparation 14-Jul-24 15:30 15-Jul-24 07:30 2h Habitat pr...
A4290 Fit up of 7th Joint in pit & Inspection 15-Jul-24 07:30 15-Jul-24 09:30 2h Fit up of ...
A4300 Root & Hot Pass Joint No 7 15-Jul-24 09:30 15-Jul-24 13:00 4h Root & Hot...
A4310 IVT -Jt-7 15-Jul-24 13:00 15-Jul-24 13:30 1h IVT -Jt-7
A4320 IRT & Film processing -Jt7 15-Jul-24 17:00 15-Jul-24 21:00 4h IRT & Fil ...
A4330 Lowering 9th Pipe -TL-19 16-Jul-24 06:30 16-Jul-24 08:30 2h Lowering 9...
A4340 Habitat preparation 16-Jul-24 08:30 16-Jul-24 10:30 2h Habitat pr...
A4350 Fit up of 8th Joint in pit & Inspection 16-Jul-24 10:30 16-Jul-24 12:30 2h Fit up of ...
A4360 Fill Up & Cap-Jt7 16-Jul-24 12:30 17-Jul-24 09:30 7h Fill Up & ...
A4370 AUT-Jt8 17-Jul-24 09:30 17-Jul-24 10:30 1h AUT-Jt8
A4390 Root & Hot Pass Joint No 8 16-Jul-24 12:30 16-Jul-24 16:00 4h Root & Hot...
A4400 IVT-Jt8 16-Jul-24 16:00 16-Jul-24 16:30 1h IVT-Jt8
A4410 IRT& Film processing-Jt8 16-Jul-24 17:00 16-Jul-24 21:00 4h IRT& Film...
A4420 Fill Up & Cap-Jt8 17-Jul-24 06:30 17-Jul-24 13:30 7h Fill Up & ...
A4430 AUT-Jt8 17-Jul-24 13:30 17-Jul-24 14:30 1h AUT-Jt8
A4440 FBE coating-Jt-7&8 17-Jul-24 14:30 17-Jul-24 16:30 2h FBE coatin...
A4450 Installation of Zinc Rbbon (8nos) 18-Jul-24 06:30 18-Jul-24 08:30 2h Installati...
A4460 Pulling of 8th pipe & 9th pipe 18-Jul-24 08:30 18-Jul-24 12:30 4h Pulling of...
Pipe 10,11 (Jt 9&10) 18-Jul-24 13:30 22-Jul-24 12:30 39h 22-Jul-24 ...
A4470 Lowering 10th Pipe -TL-19 18-Jul-24 13:30 18-Jul-24 15:30 2h Lowering 1...
A4480 Habitat preparation 18-Jul-24 15:30 19-Jul-24 07:30 2h Habitat pr...
A4490 Fit up of 9th Joint in pit & Inspection 19-Jul-24 07:30 19-Jul-24 09:30 2h Fit up of ...
A4500 Root & Hot Pass Joint No 9 19-Jul-24 09:30 19-Jul-24 13:00 4h Root & Hot...
A4510 IVT -Jt-9 19-Jul-24 13:00 19-Jul-24 13:30 1h IVT -Jt-9
A4520 IRT & Film processing -Jt9 19-Jul-24 17:00 19-Jul-24 21:00 4h IRT & Fil ...
A4530 Lowering 11th Pipe -TL-17 20-Jul-24 06:30 20-Jul-24 08:30 2h Lowering 1...
A4540 Habitat preparation 20-Jul-24 08:30 20-Jul-24 10:30 2h Habitat pr...
A4550 Fit up of 10th Joint in pit & Inspection 20-Jul-24 10:30 20-Jul-24 12:30 2h Fit up of ...
A4560 Fill Up & Cap-Jt9 20-Jul-24 12:30 21-Jul-24 09:30 7h Fill Up & ...
A4570 AUT-Jt9 21-Jul-24 09:30 21-Jul-24 10:30 1h AUT-Jt9
A4590 Root & Hot Pass Joint No 10 20-Jul-24 12:30 20-Jul-24 16:00 4h Root & Hot...
A4600 IVT-Jt10 20-Jul-24 16:00 20-Jul-24 16:30 1h IVT-Jt10
A4610 IRT& Film processing-Jt10 20-Jul-24 17:00 20-Jul-24 21:00 4h IRT& Film . .
A4620 Fill Up & Cap-Jt10 21-Jul-24 06:30 21-Jul-24 13:30 7h Fill Up & ...
A4630 AUT-Jt10 21-Jul-24 13:30 21-Jul-24 14:30 1h AUT-Jt10
A4640 FBE coating-Jt-9&10 21-Jul-24 14:30 21-Jul-24 16:30 2h FBE coatin...
A4650 Installation of Zinc Rbbon (8nos) 22-Jul-24 06:30 22-Jul-24 08:30 2h Installati...
A4660 Pulling of 10th pipe & 11th pipe 22-Jul-24 08:30 22-Jul-24 12:30 4h Pulling of...
Pipe 12,13 (Jt 11&12) 22-Jul-24 13:30 26-Jul-24 12:30 39h 26-Jul-24 ...
A4670 Lowering 12th Pipe -TL-19 22-Jul-24 13:30 22-Jul-24 15:30 2h Lowering 1...
A4680 Habitat preparation 22-Jul-24 15:30 23-Jul-24 07:30 2h Habitat pr...
A4690 Fit up of 11th Joint in pit & Inspection 23-Jul-24 07:30 23-Jul-24 09:30 2h Fit up of ...
A4700 Root & Hot Pass Joint No 11 23-Jul-24 09:30 23-Jul-24 13:00 4h Root & Hot...
A4710 IVT -Jt-11 23-Jul-24 13:00 23-Jul-24 13:30 1h IVT -Jt-11

Actual Work Critical Remaining Work Page 10 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
NORTH FIELD EXPANSION PROJECT (NFXP) - EPCI OF PIPELINE MT PipeWelding Schedule 29-Apr-24 10:31
Activity ID Activity Name Start Finish Original March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
Duration02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26
A4720 IRT & Film processing -Jt11 23-Jul-24 17:00 23-Jul-24 21:00 4h IRT & Fil ...
A4730 Lowering 13th Pipe -TL-19 24-Jul-24 06:30 24-Jul-24 08:30 2h Lowering 1...
A4740 Habitat preparation 24-Jul-24 08:30 24-Jul-24 10:30 2h Habitat pr...
A4750 Fit up of 12th Joint in pit & Inspection 24-Jul-24 10:30 24-Jul-24 12:30 2h Fit up of ...
A4760 Fill Up & Cap-Jt11 24-Jul-24 12:30 25-Jul-24 09:30 7h Fill Up & ...
A4770 AUT-Jt11 25-Jul-24 09:30 25-Jul-24 10:30 1h AUT-Jt11
A4790 Root & Hot Pass Joint No 12 24-Jul-24 12:30 24-Jul-24 16:00 4h Root & Hot...
A4800 IVT-Jt12 24-Jul-24 16:00 24-Jul-24 16:30 1h IVT-Jt12
A4810 IRT& Film processing-Jt12 24-Jul-24 17:00 24-Jul-24 21:00 4h IRT& Film . .
A4820 Fill Up & Cap-Jt12 25-Jul-24 06:30 25-Jul-24 13:30 7h Fill Up & ...
A4830 AUT-Jt12 25-Jul-24 13:30 25-Jul-24 14:30 1h AUT-Jt12
A4840 FBE coating-Jt-11&12 25-Jul-24 14:30 25-Jul-24 16:30 2h FBE coatin...
A4850 Installation of Zinc Rbbon (8nos) 26-Jul-24 06:30 26-Jul-24 08:30 2h Installati...
A4860 Pulling of 12th pipe & 13th pipe 26-Jul-24 08:30 26-Jul-24 12:30 4h Pulling of...

Actual Work Critical Remaining Work Page 11 of 11 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation