Professional Documents
Culture Documents
QHSE Documents-Temporary Works Standard Safety Procedure
QHSE Documents-Temporary Works Standard Safety Procedure
QHSE Documents-Temporary Works Standard Safety Procedure
PROCEDURE
Revision
Company Doc. No. Contractor Ref. No. Date
0
REVISION ISSUE
DESCRIPTION REVIEW / STATUS
HISTORY DATE
Table of Contents
Purpose.................................................................................................................................................4
Definitions and Abbreviations...............................................................................................................4
Responsibilities......................................................................................................................................4
Hazard Identification and Risk Assessment...........................................................................................4
Risk Checklist for Temporary Works..................................................................................................4
Control Measures for Hazards in Temporary Works..........................................................................5
Control of Temporary Works.................................................................................................................5
Duties and Responsibilities of Staff for Temporary Works....................................................................5
Contractor’s Responsibilities.............................................................................................................5
The Main Items of Responsibility..........................................................................................................5
Formal Appointment of Persons to Carry Out Individual Duties........................................................6
Temporary Works Register....................................................................................................................6
Classification of Temporary Works........................................................................................................6
Class “A” Temporary Work................................................................................................................6
Class “B” Temporary Works...............................................................................................................7
The Concept and Design Brief for Temporary Works............................................................................7
Temporary Work Concept.................................................................................................................7
Design Brief for Temporary Work..........................................................................................................8
Design Brief Checklist............................................................................................................................8
Who is suitable?................................................................................................................................9
Responsibility to carry out.................................................................................................................9
Duties to ensure that.........................................................................................................................9
The Temporary Works Designer........................................................................................................9
Who is suitable?............................................................................................................................9
Responsibilities to produce...............................................................................................................9
Duties..............................................................................................................................................10
The Temporary Works Design Checker................................................................................................10
Temporary Works Supervisor TWS......................................................................................................10
Who is suitable?..........................................................................................................................10
Responsibilities................................................................................................................................10
Duties & Authorities of TWS............................................................................................................10
Inspection / Checking of Temporary Works.........................................................................................11
Temporary Works – Safety Checklist...............................................................................................11
Temporary Works Erection..............................................................................................................11
Use of Temporary Works.................................................................................................................12
Dismantling of Temporary Works....................................................................................................12
Related Records...............................................................................................................................12
Purpose
The purpose of this procedure is to provide safe work instructions for the safe erection, dismantling,
and structure design of temporary works.
Responsibilities
The following person has responsibilities for the implementation of this standard safety procedure:
– Project Director
– Project Manager
– Temporary Works Coordinator
for each transient paintings agreement, or separate elements of a Contract depending on the
character and extent of the Temporary Works:
A. Temporary Works Coordinator (TWC)
B. Temporary Works Designer (TWD)
C. Temporary Works Design Checker (TWDC)
D. Temporary Works Supervisor (TWS)
It will normally be the case on large projects in which the TWC and TWS are based on-website
online. However, on medium-sized and small initiatives the individuals can be appointed on a
traveling foundation. In such instances, the unique requirements for Temporary Works will be
assessed with the Project Manager before making the perfect appointments.
Temporary Works Register
The TWC will keep an up-to-date register of all the objects of Temporary Works on the site with
every object categorized as defined at the Temporary Works Register. The reason of the sign in is to
make certain that each item of Temporary Works whether or not originating inside the essential
contractor or from a Sub-contractor, is formally diagnosed, designed, and checked following
assignment and company requirements. The brief works register ought to be hooked up through
Contracts Management at each Contract handover meeting and updated as essential by way of the
TWC during the Contract.
8. Open-cut excavations greater than 6 meters deep, but dependent on the nature of the
ground and site conditions
9. Formwork for concrete pours higher than 3 meters
10. Falsework higher than 3 meters
11. Façade retention schemes
12. Marine works
13. All tower crane bases
ground conditions, adjacent overhead or underground services, and any other relevant information,
should form a complete statement of the working performance required of the Temporary Works
and the circumstances affecting it. The Design brief should also include a controller program that will
define who provides what and when. Emphasis should also be placed on the fact that all
communication must be channeled through the Temporary Works Coordinator, who is authorized to
apply and progress the requirements of the brief and the program.
At all stages, from the design brief to the dismantling of the Temporary Works, it is necessary to
check that the information being used is correct and that the work is carried out as specified.
Changes in the requirements of the design brief should be recorded therein as well as incorporated
into the design and drawings. As specialist equipment suppliers accept virtually no responsibility for
to use of equipment on sites, particular attention should be given to the physical and functional
interfaces between these suppliers and any Temporary Works. The health and safety aspects of
design need to be communicated to, and where necessary discussed with, the Planning Supervisor
to:
1. Avoid or reduce risks arising from any interaction with the work of others involved in design
and planning.
2. Enable the information to be incorporated into the Health and Safety Plan.
3. The person responsible for communicating this information will be the Temporary Works
Coordinator.
Who is suitable?
A Line Manager
Sufficiently experienced to recognize the need for Temporary Work (TW)
Acknowledged experience and knowledge of the construction methods to be used
Who recognizes limits to their technical abilities and when to request assistance?
Who is a competent communicator and administrator?
Duties
1. To conform to codes of practice and design standards appropriate to the temporary works
2. To produce a safe, economic design within the timescale of the program
3. To liaise fully with the TWC to resolve any queries
4. To consult recognized specialists when required to expedite the design, as agreed with the
TWC
2. In cases where the engineering manager is appointed as TWD and TWDC, the Temporary
Works Co-coordinator must confirm the appointment in writing and ensure that the correct
independent checking regime is followed.
3. In the case of Class “B” Temporary Works, the TWDC role may be undertaken by any
competent person appointed by the Line Management.
4. The qualifications, duties, and authority of the TWDC are similar to that of the TWD. The
responsibility of the TWDC is to verify the design and confirm that with the TWC.
Responsibilities
1. Safety at all times – especially during erection, use, and dismantling of temporary work.
2. To contribute to the design brief – method, skills, plant, and materials. Access, etc.
3. To ensure the standard of workmanship is good – careful attention to detail
4. To supervise erection, loading, and removal in the correct sequence
5. To activate the checking procedures called for by the design and the Contract
6. To organize the Works – to meet the program
The adequacy of access ways and working platforms and their edge protection measures
must be paramount considerations.
5. Statutory requirements must be met at all stages of the process.
6. All Temporary Works designed or erected by Subcontractors must be checked by the TWC
for the site using the same regime of checks that would be employed if they were designed
and erected by the contractor.
7. The Engineering Manager and HSE Department will be consulted to ensure that all schemes
comply with all the Temporary requirements in this section of the procedure.
Related Records