Daily Monitoring Pile Slab 14+274 - 240222

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROYEK PEMBANGUNAN TOL SEKSI 3

Ruas Tebing Tinggi - Dolok Merawan (STA 0+000 s.d. STA 30+000) Termasuk Simpang Susun Serbelawan (Lanjutan)
Owner : PT. Hutama Marga Waskita
Consultant : PT. Multi Phi Beta - PT. Bina Karya KSO
Contractor : PT. Hutama Karya

ID Task Name Start Finish Duration % February 2024 March 2024 April 2024 May 2024
Complete 11 16 21 26 31 05 10 15 20 25 01 06 11 16 21 26 31 05 10 15 20 25 30
2 PILE SLAB 14+274 - 14+381 (107m) 16/01/24 29/04/24 90 days 45% 16/01 29/04
3 Approval Desain JBH 18/01/24 18/01/24 0 days 100% 18/01
4 Pembongkaran Area Existing 16/01/24 08/03/24 52 days 54% 16/01 08/03
8 Foundation 24/01/24 19/02/24 27 days 99% 24/01 19/02
39 Cut Off Pile 06/02/24 18/02/24 13 days 98% 06/02 18/02
40 Isian Tiang Pancang 09/02/24 24/02/24 16 days 93% 09/02 24/02
43 Upper Structure 09/02/24 24/03/24 45 days 12% 09/02 24/03
44 Pile Head (16 row) 17/02/24 15/03/24 28 days 14% 17/02 15/03
253 Half Slab (27 pcs) 09/02/24 13/03/24 34 days 67% 09/02 13/03
254 Penyiapan Lahan 09/02/24 09/02/24 1 day 100% 09/02 09/02
255 Pembesian 11/02/24 11/02/24 0 days 100% 11/02
256 Pengecoran 12/02/24 20/02/24 9 days 100% 12/02 20/02
257 Instalasi Half Slab 09/03/24 13/03/24 5 days 0% 09/03 13/03
258 Deck Slab 23/02/24 24/03/24 31 days 0% 23/02 24/03
259 Pembesian 23/02/24 22/03/24 29 days 0% 23/02 22/03
275 Pengecoran 23/03/24 24/03/24 2 days 0% 23/03 24/03
278 Finishing Structure 24/03/24 29/04/24 22 days 0% 24/03 29/04
279 Lining Beton 18/04/24 28/04/24 11 days 0% 18/04 28/04
285 Parapet 24/03/24 01/04/24 9 days 0% 24/03 01/04
312 Aspal 28/03/24 31/03/24 4 days 0% 28/03 31/03
313 Expansion Joint 01/04/24 29/04/24 14 days 0% 01/04 29/04
314 Open Traffic Lebaran 03/04/24 03/04/24 0 days 0% 03/04

PILE SLAB 14+274 - 14+381 Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split Slippage
23/02/24 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress

Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress