Professional Documents
Culture Documents
Cy2024 Rmse
Cy2024 Rmse
Subject : AGUS 1,2,4,5,6, 7 & Pulangi 4 Hydro Power Plant Survey & Risk
Assessment
Sir:
In preparation for our upcoming risk survey on captioned subject (various Agus & Pulangi
4 hydro power plants). The survey will result in two (2) deliverables; 1. Survey Report (for
insurance/re-insurance purposes), 2. Loss Control Recommendation (addressed to Guy
Carpenter and the insured).
Both reports will be based on the verbal information, documentation review and the
physical walk through of the entire facility with the intention of providing an overview of
risk in relation to plant operations, current conditions and issues that may impact overall
business objectives of above captioned hydro power plant’s management.
The survey and assessment will be conducted by ERM team. Each property survey starts
with a discussion/presentation about each unique plant system, controls and procedures
in place followed by a tour around each facility and concludes with an exit meeting to
discuss findings and propose risk reduction recommendations, if there are any.
Should you approve, below is the proposed survey schedule with designated surveyor
assigned for each hydro power plant. The entire duration of the survey is estimated to be
at least 3 days per hydro power plant including close out meeting provided all information
requested is available. The proposed schedule will be updated once we receive the pre
audit documents and we can fine tune the logistics, as well as the duration per segment of
the audit/risk survey. f
(May 6, 2024/Mon) - 3 teams leave from Cebu to Cagayan de Oro enroute to Iligan
City
1200-1300 Lunch
1200-1300 Lunch
0900-1200 Close out meeting with plant admin, O & M, safety and
security team/ handing out findings & recommendations
(May 13, 2024/Mon) - 3 teams leave from Cebu to Cagayan de Oro enroute to Iligan
City
Day 5 (May 14, 2024/Tue) - simultaneous in 3 different plants (Agus HPP 5, 6 & 7)
1200-1300 Lunch
1200-1300 Lunch
0900-1200 Close out meeting with plant admin, O & M, safety and
security team/ handing out findings & recommendations
(May 20, 2024/Mon) - 1 team leave from Cebu to Cagayan de Oro enroute to
Bukidnon
1200-1300 Lunch
1200-1300 Lunch
0900-1200 Close out meeting with plant admin, O & M, safety and
security team/ handing out findings & recommendations
The inspection agenda includes an initial discussion with the respective plant personnel to
be followed by a plant tour and an exit meeting at the end of the visit to discuss survey
findings and risk mitigation recommendations if there are any. We appreciate that the
requested documents (if there’s any) will be prepared prior to the visit as time is critical
during insurance placement.
Below is the list of discussion points. Please note that these are sent in advance to the
representatives of the insured (PSALM) for the latter to prepare/compile to save time
during the site visit. PPT Presentations from each plant team would be appreciated.
1. Company profile/plant history/ milestone
2. On-going projects/short term plan
3. Major Equipment Particulars: Suppliers name, rating, brand and country of
origin (turbine, generator, transformers, etc)
4. Plant staffing/organization
5. Plant general maintenance/ spare parts inventory control
6. Plant auxiliaries and other utilities
7. Available fire protection system
8. Calibration on protection system sensors & relays
9. Plant Key Performance Indicators
10. Infrastructure seismic and wind design parameters
11. Slope protection and drainage (protection against slides, rock fall, etc)
12. Flood mitigation
13. Quality system/certifications
14. OHSS/environmental, security, contingency plan
15. Social responsibility
16. Fire Layout Separation (Control Room/turbine
hall/switchgear/Transformers)
17. Previous 5-year loss history, causes and mitigation
18. Regulatory clearances/permits
Miscellaneous Information:
Documents Needed per plant (should be sent to ERM a week prior survey date for
advance review)