: RT ote
Und QM instructions QA 12 IB-A01
le |
Plant commissioning cman Le
1of4
Contents
Page
1 Cover page:
Title, code, contents, checking and approval of first edition and revision sos 1
User instructions:
1 Scope.
‘Aimipurpose
3 Definitions...
4 Responsibilities.
5 Procedure
5.1 General
5.2 Pre-commissioning.
5.3 Transfer of responsibilities to the commissioning manager
54 Commissioning management.
5.5 Commissioning,
5.6 — QM/HES supervision ....
5.7 Documentation to be produced during the commissioning phase.
5.7.1 As-built documents
5.7.2. Minutes, protocol sheets.
5.8 Feedback report...
5.9 Hand-over of the piant to the customer
5.10 Operational feedback report
Notes and remarks
Documentation
Updating procedure
Document distribution
Bebbbb b&w bbw KwENNNNNN
Reference documents:
‘Annex AO1: Typical commissioning organisational chart
talid Jr dajis Way ver bel
arpaed lyyprunnn WHS Or
Arte ¢
age vOut
OHA Rev 0 ;
Document foun RL
preparation t IC. Kreumann
_brionas ddoce (Neumann 04, 26601, pexonen |
Date; Prepared Daler Checked Dale: Anproved
comme 2005 Unio cmon [ OM lement Section ee
eae Commissioning Commissioning °GHD code
QA 12 IB-A01
TAN (ar GMAT Page:
20f4
QM instructions
Plant commissiot
1 Scope
These QM instructions (QAW) apply to all Unde divisions and departments involved in plant
commissioning and shal take effect on the date of approval
2 Aim/purpose
These QM instructions define the standardised procedures for al plant commissioning activities in
compliance with the requirements, beginning withthe preparations in the engineering office, the
preparations on the site, the actual commissioning and ending with the plant hand-over tothe customer.
“They also define the tasks of the commissioning manager and his team
3 Definitions
ABL Head of department
BSL Site manager
1BL_ Commissioning manager
IBN Commissioning
MC_— Mechanical completion
RFC Ready for commissioning
Sifa Safety engineer
FMS Fehler, Mangel, Schaden (non-conformities, deficiencies, damages)
VT Process engineering department
Pre-commissioning After the functional and leak tests, neutral media, such as water, air
and nitrogen, are filed in to check and document the plant reliability
performance.
Commissioning The plant is operated using the specified feedstock and supplies the specified
product. The operating data must be documented
Performance testrun The performance test run is carried out by Unde (in the presence of the
customer) under the contractual conditions to prove the piant’s functionality
and to deliver the specified product.
Transfer of hazards and responsibilities in accordance with the Berufsgenossenschatt (‘Employer's
Liability Insurance Association) regulations.
4 Responsibilities
The responsibiities and tasks of the commissioning manager are described in section 5.1.2.4 of
{echnical instructions 08 AR-AOS “Tasks of the project team. The commissioning manager, preferably
the process lead engineer (LE-VT), is normally appointed by the technical division responsible
he division transfers the tasks to the commissioning manager who represents the company on the site
and is responsible for the contractual commissioning and performance test run of the plant to ensure
plant hand-over to the customer. The commissioning manager is assisted by the safety engineer, the
QMIHES representative and staff members responsible for various plant units, offsites, rotating and
static equipment and staff members of the various technical disciplines, such as electrical and
instrumentation engineering as well as fitters and laboratory personnel, if required. He may also be
assisted by staff groups, such as a commercial administration manager, a progress control and cost
engineer, a claims manager, a manager for dealing with non-conformities, deficiencies and damage
(FMS manager) and a secretary. In the case of large-scale plants, commissioning managers
responsible for specific plant sections are named. atyplemt commissioning organisational chart is,
shown in Annex AO1 Whe Currant Safco
5 Procedure
5A General
Plant commissioning is the last stage in plant construction and is preceded by mechanical completion
which is documented by an MC acceptance certificate. Thus the verification is achieved, a confirmation
providing objective evidence in the form of @ checklist that the results of the individual components.
meet the specified requirements
Ohi clemer =o T
[commissioning [commissioning |52
53
54
55
56
57
jez
8.72
- - GNA code
QM instructions QA 12 IB-A01
Plant commissioning LSet on
o
ocessful plant commissioning the plant is handed over to the customer depending on the
contractual provisions.
Pre-commissioning
Pre-commissioning includes all activities which can be carried out using auxiliaries but no feedstock. As
the construction site has already been set up as part of the construction activities, the corresponding
provisions - including amendments if required — also apply to the pre-commissioning and
commissioning procedure.
Transfer of responsibilities to the commissioning manager
‘The transitional phase from plant construction to commissioning is characterised by the fact that the
construction activities drawing to a close, the pre-commissioning activities and the commissioning itself
can be implemented simultaneously, Some technical instructions have been drawn up which cover the
responsibilities and methods during the transitional phase from plant construction to commissioning,
‘These responsibilities must be assumed and the methods applied for properly transferring the
entrepreneurial duties from the site manager to the commissioning manager, especially paying attention,
to the transfer of responsibilities in accordance with the Berufsgenossenschaft ("Employer's Liability
Insurance Association) regulations. Any commissioning activities in an existing plant are subject to plant
‘operator's approval.
Commissioning management
The commissioning management is made up of the commissioning managers responsible for specific
plant sections #Fea¥} and the staff groups mentioned in section 4
Commissioning
Plant commissioning starts with the filing of feedstock into the process equipment and the functional
test using the specified product. Plant commissioning serves 10 prove that the individual contractual
performances have been audited and that an operable and reliable plant has been built which supplies
the specified final and intermediate products. Thus the validation is achieved, a confirmation providing
objective evidence that the requirements for a specified application or a specific intended use are
fulfilled. The plant supplies a saleable product.
For the most part, the plant is commissioned with the assistance of the future operating personnel
assigned by the customer, the operating personnel undergoing efficent training. In exceptional cases
Unde's commissioning team (or some team members only) remain on the site for a defined period of
time to ensure continuous plant management
QMIHES supervision
The QM/HES supervision ensures the Implementation of the integrated quality managementhealth,
environment and safety system in the commissioning activities. In this way Unde can meet the
requirements of DIN EN ISO 9001:2000 and of SCC (safety certificate for contractors)
‘The efficient implementation of the QM/HES system is ensured by site audits in accordance with the
audit plan. However. during the commissioning phase economic considerations must not take
precedence over the requirements to be met for health, environment and safety.
Documentation to be produced during the commissioning phase
As-built documents
(On the basis of the requirements specified in the QMHA the documents that are already in the as-bu lt
slatus after commissioning are to be integrated into the P&l diagram series, operating andior analys s.
manuals, Beginning with the construction phase, master copies are to be kept which are available in the
site emeemenissicaing manager's office. Said master copies are reviewed, making clear entries in red
dated and inttialled by the person responsible). Normally the R&l master copies are handed over by the
site manager to the commissioning manager as part of the transfer of responsibilities,
After commissioning the master copies are handed over to the technical divisions responsible which
nust ensure that the documents are integrated into the final documentation as stipulated in the
contract.
Minutes, protocol sheets
During the commissioning phase the commissioning manager is responsible for drawing up and filirg
ne specific records. After hand-over of the plant to the customer al least one copy of the said records
2005 soe Gt
3 serent
Commissioning
Commissioning58
5.9
5.10
‘OND cade
QA 12 IB-A01
TAN Ter OMFIAT Page!
40f4
QM instructions
Plant commissioning
‘must be integrated into the final documentation. The applicable Product Liability Act must especially be
taken ino account in the case of the operating manual.
Feedback report
‘The feedback report is drawn up as an independent report and integrated into the final contract report
It furnishes data about the customer, the plant location and the practices with local authorities. It should
be systematically evaluated by the process engineering depariment to prevent repeated errors when
{ulfiling similar tasks and to ensure continuous quality improvement of the contractual plant. The head
cf the process engineering department must ensure adequate communication with the employees.
Hand-over of the plant to the customer
After the successful performance test run the plant will be handed over to the customer, which is
cocumented by jointly signed minutes. At the same time, the plant hazards and responsibilities are
transferred to the customer and the guarantee period commences,
Operational feedback report
The feedback of information must be integrated/documented by reviewing and updating the operating
‘and analysis manuals and the feedback report
Notes and remarks
The following instructions shall also apply:
QAW QA 09 VT-F38. Handling hazardous substances
AAW 0B AR-A0S Tasks of the project team.
AAW 09 VT-AO1 $43 Standard engineering procedures “Process engineerin
workflow step: Planning of commissioning
FAW 09VT-F38 Operating manual
All instructions of QM element 11 "Construction" and of QM element 12 “Commissioning”
FAW 12 1B-FO5 Transfer of responsibiliies from site to commissioning manager
FAW 13LB-FO8 Commissioning support
Documentation
(QM instructions shall be documented. This shall include in particular the persons responsible for
compiling, checking and approving the documents. These QM instructions shall become an integral
part of the QMHU. Any obsolete version or revision shall be stored electronically by CC-QM. Any
differences between document versions can thus be identified and shown accordingly
Updating procedure
Should these instructions require amendment, he proposed changes shall be submitted to the
Corporate GM manager via the divisional QM representatives. Instructions QA 01 ZZ-A02 shall apply
Document distribution
‘These instructions shall be made available on the Intranet by CC-OM,
‘ht eioment
Commissio
Seaton rs ac
Commissioning o|
on
<=
ay
&
is]
J
ES
Fs
eB
n=]
| enue 0} 304 ‘ueesasoy :ouery 0123)
ques ‘N
yeys fr |
sysjeioadg s0puen, Ble, XZ sosyy “A
ou "H" 2e1S xb wineg ‘q
weqa ‘nN wiesepung *y uuewualyors "3
Bulpasey} g ayerzueld “HIG se6upley °C
awnyag “s Aydiow *p Jepeiyosnz ‘d)
a eee asa “1 oeneg “J uewiiog *5
| uopejuewinsu 9sseo | JOulag “| JOy190N IG !
leoujoa| | neo seBeuew eory ean seBeuey ray €HN JaBeuew eay
we)shs-OW
d0/vO cu
JONSON 10 /8uI29 "1 :Andag
uuewddr ‘Gig
seBeuew Buluolssiwiwos Twn
Ipluseu-iv ‘H
seBeuew Buluoisspmiu0g oss
uonesiuebic Buluoissiwwog - TWN