Professional Documents
Culture Documents
OEE and Limit Analysis
OEE and Limit Analysis
Training
Objectives
1
Agenda
• Limit analysis
2
OEE is a measure of productiveness
The higher the OEE measure the more good product per shift
a machine or line produces – which results in lower costs per unit
produced and helps operations to be more competitive
3
OEE at a glance
100 %
Total Time not Breaks PM* out- Total PM* in Break- Setup / Idling / Speed Startup Scrap / OEE
time scheduled (Lunch, side pro- available production downs Adjust- Minor losses losses Rework
for pro- etc.) duction time time ments stops
duction time
* Preventive Maintenance 4
OEE takes into account machine availability, performance and quality
How much time per How well did the How many products
shift was the machine machine perform were good the first
actually running? (compared to the time?
rated speed) when it
was actually running?
5
There are seven big losses of machine time
1 Planned maintenance
Downtime
Availability rate 2 Breakdowns
losses
3 Changeovers
6
OEE can also be calculated directly from production output
8
Application case
9
What is the OEE of my machine? TO BE FILLED DURING THE SESSION
10
Application case - Solution
11
Agenda
• Limit analysis
12
Availability rate is defined as running time divided
with total available time A
P
Q
100%
13
Availability losses - examples
A
P
Q
Examples
Planned maintenance • Periodic checks need to be done to ensure
The line is idle because teams proper machine operating conditions
are doing periodical • Worn parts need to be replaced to avoid major
maintenance breakdowns going forward
Examples
Breakdowns/Stops • Transfer of product is not possible due to broken
The line stops for more than 5 conveyor or faulty automation
minutes because something is • Machine is shut down because of machine
broken or needs to be fixed failures
• Equipment stopped because operator is missing
Examples
Changeovers • Fixtures and/or material types need to be changed
The line stops because material because of different product (product change)
or tools need to be changed • Equipment fixtures/tools need to be changed
(tool change)
14
Performance rate is defined as standard operating
time over running time A
P
15
Performance losses - examples
A
P
Examples
Idling and minor stoppages • Equipment is idle because product supply
The line has either no products from previous process is insufficient
to process or it stops for short • Operators pause to “tweak” equipment (e.g.,
periods of time, often less than adjustment of tool interrupting normal flow of
a minute
parts to the workstation)
Examples:
Reduced speed • A stamping press is slow down to avoid
The actual line speed is slower overheating of a motor
than the rated speed • A temporary fix of a conveyor breakdown limit the
transfer speed of material
16
Quality rate is defined as net operating time over
operating time A
P
17
Quality losses - examples
A
P
18
Application case
(3 person groups)
19
What is the availability rate of my machine?
TO BE FILLED DURING THE SESSION
• 2 breakdowns of 35 minutes
each occurred during shift 1
• Another breakdown of 35
minutes occurred during shift
2
22
Availability rate - Solution
• 2 breakdowns of 35 minutes Total available time = 50 400 sec (previous application case)
each occurred during shift 1
Planned stops for maintenance = 0 sec
• An other breakdown of 35
minutes occurred during shift Breakdowns time = 3 x 35 x 60 = 6300 sec
2
Changeover time = 2 x 5 x 282 = 2820 sec
23
Performance rate - Solution
Losses distribution:
29 110
Quality rate = = 87,9%
33 120
OEE is the combination of the availibility, performance and quality rates
26
Priorities for improvement become visible
1. Minor stops
Percent
0,0 2. Breakdowns
12,5
5,6
3. Scrap
100,0 16,2
27
Agenda
• Limit analysis
28
OEE improvement targets are set through a
limit analysis
Performance Performance
Limit
What will What if it all
satisfy goes right?
everyone? Target
Target Gap
Current Current Gain
Gain
29
What is a technical limit?
• Unavoidable losses,
e.g.,
– Required PMs
– Losses from local • Avoidable losses or
conditions (e.g. • Targeted gap to
waste e.g.,
weather) close
– Excessive
– Safety/logistical downtime – Typically set at
constraints ~50% of gap to
– Speed losses
– Idle time technical limit
100
OEE 10 90
75
30
15
60
Utopian limit or
perfection, interesting
but not achievable
Technical limits
Theoretical/
Observations/ What if it all
Limit design limits
trials
goes right?
of
Gap equipment
Current
31