Professional Documents
Culture Documents
Exercisses Module 2
Exercisses Module 2
MANAGEMENT
OF CLAIMS AND
RESOLUTION OF
DISPUTES
EXERCISES
6/22/2016
Session 1 – Contract
Exercises
6/22/2016
EXERCISE 1
WHAT IS A CONTRACT?
WHAT ARE THE ELEMENTS OF A
CONTRACT?
EXERCISE 2:
WHAT IS PROJECT CONTRACTING
STRATEGY?
BASED ON WHAT IS DEVELOPED?
6
6/22/2016
Exercise 3
Exercise 4
Exercise 5
• RISK ALLOCATION IN FIDIC 1999 CONTRACTS
13
Sub-
Description
clause
1.9
Delayed instruction and drawings
[Red]
1.9
Errors in Employer’s requirements
[Yell.]
E= Employer C=Contractor 14
6/22/2016
Sub-
Description
clause
4.24 Vestige
E= Employer C=Contractor 15
Sub-
Description
clause
E= Employer C=Contractor 16
6/22/2016
Sub-
Description
clause
E= Employer C=Contractor 17
Sub-
Description
clause
14 Payment
17.1 Indemnities
E= Employer C=Contractor 18
6/22/2016
Sub-
Description
clause
E= Employer C=Contractor 19
6/22/2016
Exercise 6
21
22
6/22/2016
Exercise 7
• What are the Contractor’s entitlements under
FIDIC 1999 Red and Yellow Book
23
Sub-clause Entitlement
7.4 Testing
Sub-clause Entitlement
Entitlement
Sub-clause
4.24 Fossils
Entitlement
Sub-clause
Entitlement
Sub-clause
Entitlement
Sub-clause
29
Exercise 8
30
6/22/2016
Exercise 9
• Employer’s entitlements under FIDIC 1999
Conditions of Contract
32
6/22/2016
EMPLOYER’S CLAIMS
Entitlement
Sub-clause
7.5 Rejection
33
EMPLOYER’S CLAIMS
Entitlement
Sub-clause
34
6/22/2016
EMPLOYER’S CLAIMS
Entitlement
Sub-clause
17.1 Indemnities
35
6/22/2016
Exercise 10
• Extreme climatic conditions
37
`
I am a contract manager for a contractor on an African project for
which we are using un-amended FIDIC Red Book 1999 form. We’ve
recently been plagued by weather which I and my colleagues think is
completely out of the ordinary and which has delayed our work on
site to a degree. In the last couple of project meetings I mentioned
that the rain is causing us some problems and that was recorded in
the minutes. I notified a claim in accordance with sub-clause 8.4 and
20.1 in 28 days from the last rainy day in order not to lose my
entitlement. I also made sure that in our last progress report I put in
a reference to the weather under the “Causes of Delay” section. In
our last project meeting the engineer on the project told me that
rain like this at this time of year isn’t exceptional – we strongly
disagreed on the point.
We’re thinking of putting together the details of the claim in any
event for extension of time, as we have liquidated damages on the
project for late completion.
Have you got any tips about what we should be keeping in mind to
give us the best chance of success?
38
6/22/2016
Exercise 11
39
We are working under FIDIC 99 Red Book. To calculate Price Adjustment using Pn
formula Contractor has to use statistical data provided by State Agency for
Statistics.
Recently Client have forwarded a letter from State Agency for statistics, where it
says that all previously data has to be changed since they were not correctly
calculated.
Now Client wants to recalculate all previously certified IPCs.
State Agency for Statistics explains situations as follows: “the Agency calculated
indices based on the Data provided by companies which are involved in Project and
companies manipulated situation to their advantage. Having understood this lately
the Agency now decided to recalculate indices using data provided by neutral
companies not involved the Project.”
Now Contractor put a Claim against Client for changing indices, specially Base
Indices in Contract.
1) Can Contractor put a Claim against Client in such a situation?
2) Is Sub clause 19.1 of FIDIC ( Force Majeure ) applicable in such situation?
3) Client insisting that overpaid Price Adjustment must be recovered from the
Contractor. Employer is saying that Engineer has to calculate PA himself and then
include to IPC & recover. Is this ok ?
40
6/22/2016
Exercise 12
41
Concurrent delays
• A Contractor Risk Event will result in five weeks
Delay to Completion, delaying the contract
completion date from 21 January to 25 February.
Independently and a few weeks later, a variation
is instructed on behalf of the Employer which, in
the absence of the preceding Contractor Risk
Event, would result in Delay to Completion from 6
February to 20 February.
• What EOT is due to the Contractor?
42
6/22/2016
Exercise 13
43
• The Employer and the Contractor signed a FIDIC 99 Red Book Contract for the
execution of a railway. The completion date is 1 April 2016.
• The Contractor did not finish on time due to the fact that he did not mobilize
on time, there were no requests for an Extension of Time for Completion.
• The Employer claimed delay damages and the Engineer issued a
determination on this aspect giving a determination in the favor of the
Employer.
• We are on 1 June 2016 and the Contractor find an archeological vestige on
Site. On 1 June 2016 the works are not completed (only 70% of the works are
done) and there is no Taking Over Certificate.
• The Contractor is claiming Extension of Time for Completion and Costs.
• The Employer stated that he is outside of the Completion date and the
Contractor has no entitlement for an Extension of Time for Completion
• Is the Contractor entitled to an Extension of Time for Completion?
44
6/22/2016
Exercise 14
45
46
6/22/2016
Exercise 15
47
A construction Contract started in 2010 and suspended in July 2012 because of the
change of the government and lack of funds.
An addendum to the Contract has been signed in which the Contractor agreed to
continue the works without payment during 2012, and for the works executed in
2012 the payment shall be done in February 2013.
After resuming the works in September 2012, the contractor took a credit from the
bank for 180 day periods, however IPC submitted in December 2012 was not paid in
accordance with the addendum exceeding the bank 180 day period of
reimbursement.
The government decided not to allocate funds for this project in 2013 and asked the
Contractor to sign the same amendment, meaning to continue the works and for
2013 the payment shall be done in 2014. The Contractor was willing to agree to the
addendum and went with it to his Bank.
The bank is now concerned about continued financing because of lack of guarantee
and ask for a Bank Guarantee from the Employer in order to continue financing the
Contractor. The Employer cannot give guarantee as state enterprise because it
depends on government funding.
The Contractor requested additional credit from the Bank but it was refused.
Because the Contractor did not reimburse the credit on time the Bank asked the
Contractor’s insolvency
What best action the contract affords to the contractor? 48
6/22/2016
51
52
6/22/2016
53
Exercise
On a FIDIC Red Book Contract the Contractor has to build a motorway. During the
excavation process the Contractor becomes aware that the soil is much harder
than foreseen. For the execution of the works the Contractor need drilling and
blasting equipment. In the BOQ there were no items for this kind of works.
During the Monthly Progress Meting the contractor raised this issue but there was
not recorded in the minute.
The Contractor stopped the work, and mobilized the additional equipment
required.
He gave notice of a claim under 20.1 but the Engineer rejected because the notice
was too late (more than 28 days) from the event.
Exercise 18 - Virus
55
Exercise
On an isolated site a virus hit the Contractor’s and the Engineer’s camp. The effect
of the virus was for 15 days. The Contractor made a claim under Sub-clause 20.1
and 8.4(d) and requested 15 days Extension of Time. The Engineer’s representative
on site, who was also affected, gave an Extension of Time of 15 days in accordance
with the sub-clause 3.5 and 8.4.
57
DAB Workshop
59