DPWH UPMO - FCMC Flood Control Projects under KEXIM Bank

As of December 2023

Project Name Cost Loan/Grant Project Description Status Remarks


Integrated Disaster Risk Reduction and Climate 7.571 Billion PhP Loan The project focuses on conducting the following flood damage 97.03% No Major Issues
Change Adaptation Measures in the Low-Lying mitigation measures namely (1) dredging/excavation of river (Civil Works)
Areas of Pampanga Bay channels in the Third River (Mainstream), the Caduang Tete
River, and the Sapang Maragul River (tributaries), (2)
improvement and replacement of sluice gates located in the
right side of the Pampanga River, in order to maximize the
drainage efficiency and minimize flood damages, (3) dike
embankment with sodding and concrete slope protection, and
(4) construction of bridges and fishpond gates.

Integrated Disaster Risk Reduction and Climate 199.8 Million GOP It aims to mitigate the flooding in the low-lying areas of 88.4% Request for Supplemental FS was submitted to NEDA
Change Adaptation Measures in the Low-Lying Pampanga Bay, particularly in the Municipalities of Minalin, (FS and DED on November 16, 2023 as required by the KEXIMBank
Areas of Pampanga Bay, Stage II Macabebe, and Sto. Tomas. under GOP) to facilitate the EDCF approval process for Civil Works.
DPWH UPMO - FCMC Flood Control Projects under KEXIM Bank
As of December 2023

Project Name Cost Loan/Grant Project Description Status Remarks


1,338.847 Million Loan The proposed conduct of the updating of master plan, 76.91% No Major Issues
Updating of Master Plan, Feasibility Study and Php feasibility study and detailed engineering design for the
Detailed Engineering Design of Flood Control priority four (4) major river basins, namely, Bicol River,
for Bicol River, Agusan River, Panay River, and Agusan River, Panay River and Pampanga River (BAPP Rivers)
Pampanga River Basins - Philippines-Korea shall be handled by the foreign consulting firm (Consultants)
Project Preparation Facility Output 2 under the direction of the DPWH through its Unified Project
Management Office – Flood Control Management Cluster
(DPWH-UPMO-FCMC). The updating of master plan and the
feasibility study are expected to determine the required flood
control infrastructures in the river basins including the priority
flood control projects based on economic, environmental and
social impacts, together with the development of suitable and
optimal investment programs. Identified priority projects will
then be subjected to detailed engineering design.
DPWH UPMO - FCMC Flood Control Projects under KEXIM Bank
As of December 2023

Project Name Cost Loan/Grant Project Description Status Remarks


Feasibility Study of Integrated Water - Grant This feasibility study focuses on the review of "The Study on Final FS submitted to Planning Services on October 18,
Engineering Project in Laoag River Basin, Sabo and Flood Control in the Laoag River Basin, 1997," with 2023
Philippines the primary goal of establishing crucial infrastructure to
reduce flood damage in the vulnerable Laoag River basin. To be proposed under Loan:
The project Detailed Engineering Design and Construction of
ultimately aims to enhance the region's resilience to floods, Integrated Water Engineering Project in Laoag River
safeguard lives and property, and contribute to sustainable Basin Engineering Project in Laoag River Basin
economic growth. 39,117.95 Million Php (Tentative)
- Two (2) Additional Sabo Dams (Labuganon and
Solsona)
- Papa River Embankment Reinforcement
- Daorao Creek Improvement

Feasibility Study for the Integrated Flood Risk - Grant To formulate an appropriate Feasibility Study with short-term, - To be proposed as Technical Assistance under GOK
Management of Bulacan Province medium term and long-term solutions for the province of
Bulacan while considering the effects of on-going government
projects and climate change that can adversely affect flood.