Quan Ly Thi cong-ENG VER-R3
Quan Ly Thi cong-ENG VER-R3
Quan Ly Thi cong-ENG VER-R3
1
CONSTRUCTION Effective date: 01-03-2022
MANAGEMENT Times: 3
PROCEDURE Page : 1 per 12
Effective
Times Admendment Prepared by Approved by
date
- Update reference
3 01/03/2022 - Add-in Construction
chart
DISTRIBUTION
1 Board of Directors
4 Project manager
5 Site manager
Code: TT 7.5.1
CONSTRUCTION Effective date: 01-03-2022
MANAGEMENT Times: 3
PROCEDURE Page : 2 per 12
Contents
1. Purpose........................................................................................................................3
2. Scope of work.............................................................................................................. 3
3. Reference document....................................................................................................3
4. Content.........................................................................................................................4
4.1. General..................................................................................................................4
4.1.1. Receiving project............................................................................................ 4
4.1.2. Inspection work...............................................................................................4
4.1.3. As-built drawing.............................................................................................. 5
4.1.4. The settlement and liquidation of contract......................................................5
4.1.5. Arising works...................................................................................................6
4.1.6. Using of available document/form...................................................................6
4.1.7. Warranty and maintenance.............................................................................7
4.2. Chart of construction activities...............................................................................7
4.3. Description of construction management activities................................................8
4.3.1. Receiving project............................................................................................ 8
4.3.2. Receiving document/information.....................................................................8
4.3.3. Plan of construction........................................................................................ 8
4.3.4. Construction preparation.................................................................................9
4.3.5. Developing construction and Inspection.........................................................9
4.3.6. Project hand over..........................................................................................10
4.3.7. Project warranty............................................................................................10
4.3.8. Settlement and liquidation of contracts.........................................................10
5. Form – Sheet............................................................................................................. 12
Code: TT 7.5.1
CONSTRUCTION Effective date: 01-03-2022
MANAGEMENT Times: 3
PROCEDURE Page : 3 per 12
1. Purpose
2. Scope of work
Applied for all constructing activities in supply and installation of HVAC system
and for referene in other condition.
3. Reference document
TCVN 3890: 2009 Fire prevention and fighting means for building and
works – equipment, arrangement, inspection, maintenance, symbol.
TCVN 3985: 1999 Noise standard for the manufacturing and construction
area.
TCVN 5949: 1998 Acoustics - Noise in public places and populated areas
- Permitted maximum noise level.
4. Content
4.1. General
Inspection and site acceptance testing often consist of: incoming material
– equipment inspection, Checking and acceptance of construction parts or
construction stages, ect.
Normal inspection work consist of: The engineering inspection work and
The quantity inspection work.
In The as-built drawings must indicate the name and signature of the
drawings setter
Minutes of meeting.
All design drawing and additional quotation (if have) are confirmed by
Client or legal representative of Client
During the construction process, if the investor requests using the form
given by the Client, we will follow that.
If the Client does not request, we can use our available forms
If the available documents and forms do not meet the requirements of the
Client, it can actively modify, supplement with the approval of the Owner.
However, the amendments shall be only made under the approval of the
Head of QA-QC or the company Board of Directors
Receiving project
Receiving document/Information
Plan of construction
Construction preparation
Developing construction
Inspection work
Handing over
Site Manager should actively discuss with the Board of Directors, project
managers or Client to Built an appropriate plan to meet the requirements
of the project
Construction schedule.
Safety manual;
Shopdrawing
Developing construction
Design drawing
shopdrawing;
The warranty will take effect from the date of signing the minutes of
acceptance for operation the completion project
Contract liquidation