GREEN BUILDING EDUCATION AND RESEARCH ACADEMY

Provided by/ Karim Elnabawy


USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
LEED AP BD+C Course | GBERA

Table of Contents Energy and Atmosphere (EA)

• EA Overview | Introduction
• 1) EA Prerequisite | Fundamental Commissioning and Verification
• 2) EA Prerequisite | Minimum Energy Performance
• 3) EA Prerequisite | Building-Level Energy Metering
• 4) EA Prerequisite | Fundamental Refrigerant Management
• 5) EA Credit | Enhanced Commissioning
• 6) EA Credit | Optimize Energy Performance
• 7) EA Credit | Advanced Energy Metering
• 8) EA Credit | Demand Response
• 9) EA Credit | Renewable Energy Production
• 10) EA Credit | Enhanced Refrigerant Management
• 11) EA Credit | Green Power and Carbon Offsets
• EA Quiz
• EA | Illustrative Quiz Q&A

Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning


USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
and Verification
LEED AP BD+C Course | GBERA

1
7/7/2021

Energy and Atmosphere (EA)

EA Prerequisite | Fundamental Commissioning


and Verification
LEED AP BD+C

Provided by/ Karim Elnabawy


USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
LEED AP BD+C Course | GBERA

POINTS
No This Prerequisite Applies to Number of Points
01 New Construction -

02 Core and Shell -

03 Schools -

04 Retail -

05 Data Centers -

06 Warehouses and Distribution Centers -

07 Hospitality -

08 Healthcare -

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

2
7/7/2021

INTENT

To support the design, construction, and eventual operation of a


project that meets the owner’s project requirements for energy,
water, indoor environmental quality, and durability.

REQUIREMENTS
COMMISSIONING PROCESS SCOPE
Complete the following commissioning (Cx) process activities for mechanical, electrical, plumbing, and
renewable energy systems and assemblies, in accordance with ASHRAE Guideline 0-2005 and ASHRAE
Guideline 1.1–2007 for HVAC&R Systems, as they relate to energy, water, indoor environmental quality,
and durability.
Requirements for exterior enclosures are limited to inclusion in the owner’s project requirements (OPR)
and basis of design (BOD), as well as the review of the OPR, BOD and project design. NIBS Guideline 3
2012 for Exterior Enclosures provides additional guidance.
• Develop the OPR.
• Develop a BOD.

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

3
7/7/2021

THE COMMISSIONING AUTHORITY (CXA) MUST DO THE FOLLOWING:


• Review the OPR, BOD, and project design.
• Develop and implement a Cx plan.
• Confirm incorporation of Cx requirements into the construction documents.
• Develop construction checklists.
• Develop a system test procedure.
• Verify system test execution.
• Maintain an issues and benefits log throughout the Cx process.
• Prepare a final Cx process report.
• Document all findings and recommendations and report directly to the owner throughout the process.
The review of the exterior enclosure design may be performed by a qualified member of the design or
construction team (or an employee of that firm) who is not directly responsible for design of the
building envelope.

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

By the end of the design development phase, engage a commissioning authority with the following
qualifications.
• The CxA must have documented commissioning process experience on at least two building projects
with a similar scope of work. The experience must extend from early design phase through at least
10 months of occupancy;
• The CxA may be a qualified employee of the owner, an independent consultant, or an employee of
the design or construction firm who is not part of the project’ design or construction team, or a
disinterested subcontractor of the design or construction team.
• For projects smaller than 20,000 square feet (1 860 square meters), the CxA may be a qualified member of
the design or construction team. In all cases, the CxA must report his or her findings directly to the owner.
Project teams that intend to pursue EA Credit Enhanced Commissioning should note a difference in the
CxA qualifications: for the credit, the CxA may not be an employee of the design or construction firm
nor a subcontractor to the construction firm.

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

4
7/7/2021

CURRENT FACILITIES REQUIREMENTS AND OPERATIONS AND MAINTENANCE PLAN


Prepare and maintain a current facilities requirements and operations and maintenance plan that contains the
information necessary to operate the building efficiently. The plan must include the following:
• A sequence of operations for the building;
• The building occupancy schedule;
• Equipment run-time schedules;
• Setpoints for all HVAC equipment;
• Set lighting levels throughout the building;
• Minimum outside air requirements;
• Any changes in schedules or setpoints for different seasons, days of the week, and times of day;
• A systems narrative describing the mechanical and electrical systems and equipment;
• A preventive maintenance plan for building equipment described in the systems narrative; and
• A commissioning program that includes periodic commissioning requirements, ongoing commissioning tasks,
and continuous tasks for critical facilities.

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

Data Centers Only


For small projects with computer room peak cooling loads less than 2,000,000 Btu/h (600 kW) or a total
computer room peak cooling load less than 600,000 Btu/h (175 kW), the CxA may be a qualified
employee of the design or construction team.

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

10

5
7/7/2021

STEP-BY-STEP GUIDANCE

11

STEP 1. DEVELOP OWNER’S PROJECT REQUIREMENTS

STEP 2. DEVELOP BASIS OF DESIGN

STEP 3. ENGAGE COMMISSIONING AUTHORITY

STEP 4. DEVELOP PRELIMINARY COMMISSIONING PLAN

STEP 5. REVIEW OPR, BOD, AND DESIGN DOCUMENTS


• The review should be conducted on middesign documents so that the project team has time to make any
necessary changes.
• Earlier and additional reviews at other project milestones are advisable and often beneficial to project
performance but are not required

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

12

6
7/7/2021

STEP 6. DEVELOP CX REQUIREMENTS AND INCORPORATE INTO CONSTRUCTION DOCUMENTS


Before construction begins, develop commissioning requirements based on the systems included in the design and
incorporate them into the construction documents.

STEP 7. UPDATE OPR, BOD, AND CX PLAN

STEP 8. CONDUCT CX KICKOFF MEETING

STEP 9. DEVELOP CONSTRUCTION CHECKLISTS


• Checklists provide confirmation to the CxA that the systems have been installed, started up, programmed, tested, and
balanced, and that the team is ready to proceed with functional testing.
• In general, contractors are responsible for filling out the checklists and returning them to the CxA.
• Construction checklists must be completed for all equipment, assemblies, and systems included in Cx scope. Sampling
strategies are not permitted.

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

13

STEP 10. CONDUCT PREFUNCTIONAL INSPECTIONS


Communicate with the contractors to determine the exact schedule for prefunctional inspections to verify proper
installation and handling of systems to be commissioned. Several activities that can be considered prefunctional inspections
include site visits, field observations, and review of start-up forms, construction checklists, and complete test-and-balance
reports.
STEP 11. DEVELOP FUNCTIONAL TEST SCRIPTS
Functional testing scripts typically follow the sequence of operations developed by the engineer. If a controls contractor
created the sequence of operations, the design engineer must approve the controls submittal to ensure it adheres to the
BOD.
STEP 12. EXECUTE FUNCTIONAL TESTING
Perform functional performance testing once all system components are installed, energized, programmed, balanced, and
otherwise ready for operation under part- and full-load conditions.
• The CxA generally oversees the testing; the contractors execute the testing.
• Sampling strategies may be implemented for functional testing. An acceptable sampling rate is “10 or 10%,” meaning
that for multiple units of the same type with the same components and sequences (e.g., fan coil units or variable air
Overview volume systems), the commissioning team may test only 10 units or 10% of the units, whichever is greater.
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

14

7
7/7/2021

STEP 13. DOCUMENT FINDINGS


Use the issues log to track any deficiencies discovered and any benefits identified through functional testing.
STEP 14. PREPARE CX REPORT
The CxA should write the Cx report after installation inspections and functional performance test verification. The report
covers all components of the commissioning process, including the following:
• Executive summary of commissioning process and results, system deficiencies identified and resolution, and
outstanding issues
• Project directory
• Cx process overview
• Owner’s project requirements and Basis of design
• Submittals
• Design review log
• Cx specifications
• List of systems commissioned and Installation verification checklists
• Functional performance tests

Overview
• Issues log, detailing open and closed issues
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

15

STEP 15. COMPILE CURRENT FACILITY REQUIREMENTS AND OPERATIONS AND MAINTENANCE
PLAN
Prepare and maintain a current facility requirements (CFR) and operations and maintenance (O&M) plan that contains
the information necessary to operate the building efficiently. This information is covered in the OPR, BOD, and functional
test scripts, but more information may be taken from specific submittals or equipment operations and maintenance
manuals. The plan must include the following:
• Sequences of operation for the building
• Building occupancy schedule
• Equipment run-time schedules
• Setpoints for all HVAC equipment
• Lighting levels throughout the building
• Minimum outside air requirements
• Changes in schedules or setpoints for different seasons, days of the week, and times of day Systems narrative
describing the mechanical and electrical systems and equipment
• Preventive maintenance plan for building equipment described in the systems narrative

Overview
• Cx program that includes periodic Cx requirements, ongoing Cx tasks, and continuous tasks for critical facilities
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

16

8
7/7/2021

FURTHER EXPLANATION

17

SYSTEMS TO BE COMMISSIONED
• Mechanical, including HVAC&R equipment and controls
• Plumbing, including domestic hot water systems, pumps, and controls
• Electrical, including service, distribution, lighting, and controls, including daylighting controls
• Renewable energy systems

The envelope must be covered in the OPR and BOD, but full envelope commissioning is not required unless
the project team pursues EA Credit Enhanced Commissioning, Option 2.
Systems that are not required to be commissioned under this prerequisite but may be added to the Cx scope at the
request of the owner include the following:
• Envelope
• Life safety systems
• Communications and data systems
• Fire protection and fire alarm systems
• Process equipment

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

18

9
7/7/2021

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

19

OWNER’S PROJECT REQUIREMENTS


The OPR details the functional requirements as well as the expectations of the building’s use and operation. The
intention is to document the owner’s requirements and objectives for the project to verify that those goals are carried
through the life of the project.
There is no required format; an OPR outline might include the following:
• Key project requirements. Items that the Cx process will focus on, and that the owner has deemed critical to the
project.
• Occupant requirements. Functions, number of occupants, and schedules for the building.
• Budget considerations and limitations. The expected cost restrictions and considerations for the project’s design,
construction, and commissioning process.
• Target goals. The owner’s overall goals, such as energy efficiency and sustainability.
• Performance criteria. The standards by which the project will be evaluated by the Cx team. Each criterion should
be measurable and verifiable. Potential topics include general, economic, user requirements, construction process,
operations, systems, and assemblies.
• Operations and maintenance requirements. Established criteria for ongoing operations and maintenance, as well
as training requirements for personnel.
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

20

10
7/7/2021

BASIS OF DESIGN
The BOD explains how the construction and other details will execute the OPR. The intention is to document the thought
processes and assumptions behind design decisions made to meet the OPR. There is no required format; a
BOD outline might include the following:
• Systems and assemblies. Overview of the systems and assemblies and how they are intended to meet the OPR.
• Performance criteria and assumptions. The standards that the system was designed to meet and the
expectations regarding system operation and maintenance, both linked to the OPR.
• Descriptions. A description of the general building, envelope, HVAC, electrical, water, and other systems, and a
statement of operation that describes how the facility is expected to operate under various situations and modes.
• Governing codes and standards. Specific codes, standards, and guidelines considered during the design of the
facility and the designer’s response to these requirements.
• Owner directives. Assumptions regarding usage of the facility.
• Design development guidelines. Concepts, calculations, decisions, and product selections; the specific design
methods, techniques, and software used in design; information regarding ambient conditions used during design;
and specific manufacturer makes and models used as the basis of design for drawings and specifications.
• Revision history. A summary of changes made throughout the project phases.
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

21

CX PLAN
The commissioning team develops the Cx plan with input from the project team. Updates during the design and
construction process are the primary responsibility of the CxA.
The Cx plan begins with a program overview:
Goals and objectives, General project information, and Systems to be commissioned.

It describes the Cx team:


Team members, roles, and responsibilities, Communication protocol, coordination, meetings, and management.

Finally, it summarizes the Cx process activities:


• Reviewing the OPR
• Reviewing the BOD
• Developing systems functional test procedures
• Verifying system performance
• Reporting deficiencies and the resolution process
• Accepting the building systems
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

22

11
7/7/2021

ISSUES LOG FOR THE DESIGN REVIEW


It is useful to include the following information in the design review issues log:
• Date of the review
• Drawing number or page where the issue was found
• Comments
• Party responsible for addressing the issue
• Response
• Date the issue was closed

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

23

PROJECT TYPE VARIATIONS


Data Centers
The OPR should address the overall energy efficiency goals of the project, including the partial- and full-load power
usage effectiveness (PUE). Information on how the data center will be operated and by whom will help ensure quality
operation of complex systems. Clear and concise documentation of the BOD—including the cooling systems’ level of
power, redundancy, reliability, and ability to support data center operations and energy efficiency during preventive or
unscheduled maintenance—will help the CxA evaluate performance.

District Energy Systems


All downstream equipment is included in the scope of this prerequisite. Such equipment includes heat exchangers,
steam pressure reduction stations, pumps, valves, pipes, building electrical services, and controls. All upstream
equipment is excluded from the scope of this prerequisite.

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

24

12
7/7/2021

FURTHER EXPLANATION
Group Approach
All buildings in the group may be
documented as one.

Campus Approach
Ineligible

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

25

REFERENCED STANDARDS
ASHRAE Guideline 0–2005, The Commissioning Process: ashrae.org

ASHRAE Guideline 1.1–2007, HVAC&R Technical Requirements for the Commissioning Process:
ashrae.org

NIBS Guideline 3–2012, Exterior Enclosure Technical Requirements for the Commissioning Process:
wbdg.org/ccb/NIBS/nibs_gl3.pdf

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

26

13
7/7/2021

REQUIRED DOCUMENTATION

27

Documentation All Projects

CxA previous experience X

Confirmation of OPR and BOD contents X

List of systems to be commissioned X

Verification of CxA activities and reviews X

Cx plan X

Documentation of testing and verification X

CFR, O&M plan X

Cx report X

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

28

14
7/7/2021

THINK ABOUT IT
• What is the difference between downstream equipment and upstream equipment? How both are relevant to
commissioning process? And what is DES?
• What is included in O&M plan?
• How renewable energy production credit is linked with Commissioning?
• How metering will benefit the commissioning process?

Share any thoughts by any of the following


Email: Karimelnabawy@gmail.com
Website Discussion Board
Private Messages
Facebook Group discussion board
Whatsapp: 002 01226041726

Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA

29

GREEN BUILDING EDUCATION AND RESEARCH ACADEMY

Provided by/ Karim Elnabawy


USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
LEED AP BD+C Course | GBERA

30