Professional Documents
Culture Documents
10+CO LEED AP1 CH6-EA-02+Fundamental+Commissioning
10+CO LEED AP1 CH6-EA-02+Fundamental+Commissioning
10+CO LEED AP1 CH6-EA-02+Fundamental+Commissioning
• EA Overview | Introduction
• 1) EA Prerequisite | Fundamental Commissioning and Verification
• 2) EA Prerequisite | Minimum Energy Performance
• 3) EA Prerequisite | Building-Level Energy Metering
• 4) EA Prerequisite | Fundamental Refrigerant Management
• 5) EA Credit | Enhanced Commissioning
• 6) EA Credit | Optimize Energy Performance
• 7) EA Credit | Advanced Energy Metering
• 8) EA Credit | Demand Response
• 9) EA Credit | Renewable Energy Production
• 10) EA Credit | Enhanced Refrigerant Management
• 11) EA Credit | Green Power and Carbon Offsets
• EA Quiz
• EA | Illustrative Quiz Q&A
1
7/7/2021
POINTS
No This Prerequisite Applies to Number of Points
01 New Construction -
03 Schools -
04 Retail -
05 Data Centers -
07 Hospitality -
08 Healthcare -
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
2
7/7/2021
INTENT
REQUIREMENTS
COMMISSIONING PROCESS SCOPE
Complete the following commissioning (Cx) process activities for mechanical, electrical, plumbing, and
renewable energy systems and assemblies, in accordance with ASHRAE Guideline 0-2005 and ASHRAE
Guideline 1.1–2007 for HVAC&R Systems, as they relate to energy, water, indoor environmental quality,
and durability.
Requirements for exterior enclosures are limited to inclusion in the owner’s project requirements (OPR)
and basis of design (BOD), as well as the review of the OPR, BOD and project design. NIBS Guideline 3
2012 for Exterior Enclosures provides additional guidance.
• Develop the OPR.
• Develop a BOD.
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
3
7/7/2021
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
By the end of the design development phase, engage a commissioning authority with the following
qualifications.
• The CxA must have documented commissioning process experience on at least two building projects
with a similar scope of work. The experience must extend from early design phase through at least
10 months of occupancy;
• The CxA may be a qualified employee of the owner, an independent consultant, or an employee of
the design or construction firm who is not part of the project’ design or construction team, or a
disinterested subcontractor of the design or construction team.
• For projects smaller than 20,000 square feet (1 860 square meters), the CxA may be a qualified member of
the design or construction team. In all cases, the CxA must report his or her findings directly to the owner.
Project teams that intend to pursue EA Credit Enhanced Commissioning should note a difference in the
CxA qualifications: for the credit, the CxA may not be an employee of the design or construction firm
nor a subcontractor to the construction firm.
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
4
7/7/2021
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
10
5
7/7/2021
STEP-BY-STEP GUIDANCE
11
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
12
6
7/7/2021
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
13
14
7
7/7/2021
Overview
• Issues log, detailing open and closed issues
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
15
STEP 15. COMPILE CURRENT FACILITY REQUIREMENTS AND OPERATIONS AND MAINTENANCE
PLAN
Prepare and maintain a current facility requirements (CFR) and operations and maintenance (O&M) plan that contains
the information necessary to operate the building efficiently. This information is covered in the OPR, BOD, and functional
test scripts, but more information may be taken from specific submittals or equipment operations and maintenance
manuals. The plan must include the following:
• Sequences of operation for the building
• Building occupancy schedule
• Equipment run-time schedules
• Setpoints for all HVAC equipment
• Lighting levels throughout the building
• Minimum outside air requirements
• Changes in schedules or setpoints for different seasons, days of the week, and times of day Systems narrative
describing the mechanical and electrical systems and equipment
• Preventive maintenance plan for building equipment described in the systems narrative
Overview
• Cx program that includes periodic Cx requirements, ongoing Cx tasks, and continuous tasks for critical facilities
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
16
8
7/7/2021
FURTHER EXPLANATION
17
SYSTEMS TO BE COMMISSIONED
• Mechanical, including HVAC&R equipment and controls
• Plumbing, including domestic hot water systems, pumps, and controls
• Electrical, including service, distribution, lighting, and controls, including daylighting controls
• Renewable energy systems
The envelope must be covered in the OPR and BOD, but full envelope commissioning is not required unless
the project team pursues EA Credit Enhanced Commissioning, Option 2.
Systems that are not required to be commissioned under this prerequisite but may be added to the Cx scope at the
request of the owner include the following:
• Envelope
• Life safety systems
• Communications and data systems
• Fire protection and fire alarm systems
• Process equipment
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
18
9
7/7/2021
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
19
20
10
7/7/2021
BASIS OF DESIGN
The BOD explains how the construction and other details will execute the OPR. The intention is to document the thought
processes and assumptions behind design decisions made to meet the OPR. There is no required format; a
BOD outline might include the following:
• Systems and assemblies. Overview of the systems and assemblies and how they are intended to meet the OPR.
• Performance criteria and assumptions. The standards that the system was designed to meet and the
expectations regarding system operation and maintenance, both linked to the OPR.
• Descriptions. A description of the general building, envelope, HVAC, electrical, water, and other systems, and a
statement of operation that describes how the facility is expected to operate under various situations and modes.
• Governing codes and standards. Specific codes, standards, and guidelines considered during the design of the
facility and the designer’s response to these requirements.
• Owner directives. Assumptions regarding usage of the facility.
• Design development guidelines. Concepts, calculations, decisions, and product selections; the specific design
methods, techniques, and software used in design; information regarding ambient conditions used during design;
and specific manufacturer makes and models used as the basis of design for drawings and specifications.
• Revision history. A summary of changes made throughout the project phases.
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
21
CX PLAN
The commissioning team develops the Cx plan with input from the project team. Updates during the design and
construction process are the primary responsibility of the CxA.
The Cx plan begins with a program overview:
Goals and objectives, General project information, and Systems to be commissioned.
22
11
7/7/2021
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
23
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
24
12
7/7/2021
FURTHER EXPLANATION
Group Approach
All buildings in the group may be
documented as one.
Campus Approach
Ineligible
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
25
REFERENCED STANDARDS
ASHRAE Guideline 0–2005, The Commissioning Process: ashrae.org
ASHRAE Guideline 1.1–2007, HVAC&R Technical Requirements for the Commissioning Process:
ashrae.org
NIBS Guideline 3–2012, Exterior Enclosure Technical Requirements for the Commissioning Process:
wbdg.org/ccb/NIBS/nibs_gl3.pdf
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
26
13
7/7/2021
REQUIRED DOCUMENTATION
27
Cx plan X
Cx report X
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
28
14
7/7/2021
THINK ABOUT IT
• What is the difference between downstream equipment and upstream equipment? How both are relevant to
commissioning process? And what is DES?
• What is included in O&M plan?
• How renewable energy production credit is linked with Commissioning?
• How metering will benefit the commissioning process?
Overview
Points
Intent and Requirements
Behind the Intent
Step by Step Guidance
Further Explanation
Referenced Standards Provided by/ Karim Elnabawy EA Prerequisite Fundamental Commissioning
Exemplary Performance USGBC Faculty, B.Sc. Archi., LEED AP (BD+C, O+M, ID+C), M.Sc. UK, PMP, WELL AP, Estidama PQP-PbRS, EDGE EXPERT
Required Documentation and Verification
Questions LEED AP BD+C Course | GBERA
29
30
15