Event Summary
Event Type Workover Event Start Date 5/23/2024 Days on Location 9.00
Objective Workover - Replace Completion Original Spud Date
Est. Days 0.00 Contractor Dasco
Work Unit Dasco 27 Days To Release
Rig Phone/FAX No. 3135
Well Status
Supervisor Mohamed Abdel Bar Measured Depth(m)
Operating Rates
HSE Summary
Last Incident Date Days Last Incident Date Days KPI's
Safety Comments:
LTI: 578 days
Safety Observation system (Stop cards):
- Total Number Daily/Monthly: 8 /10.
- Stop card participation: Bapetco=02, Dasco= 08, Service hand= 0
• Safe acts/condition: Good arranged &housekeeping in dog house and Rig floor.
• Unsafe acts: Observed one person talking with forklift operator during working operation (Stopped him).
• Unsafe conditions: There was the wire of air horse not arranged in its spool (F.M Arranged it).
** Barriers **
• Primary: 8.5 PPG.
• Secondary: BOP & FBSV.
**Current Activity/Phase**.
• POOH W/ 6”Bit assy on 3.5” D.P STG, by using Rig tong & L/D Same.
MOC’s/Deviations in place:
• Some well control equipment: (1- MOC for Annular BOP Rubber element 2- MOC for stand pipe and valves of manifold 3- MOC for
crown block sheaves.)
HSE Activities Today:
• Performed safety meeting with crew members before job.
• Preformed Discuss about confined space Session with crew member.
• Prepared the work permits before jobs.
• Weekly inspection for crane.
PTW register:
Total PTW: (Cold/Hot/Confined space: 2/0/0)
Open PTW: 1
Closed PTW: 1
HSE Drills
Drills/Tests Date Days Since Last
HSE Inspections
Government Inspection
Company Inspection 3/22/2024
Operations Summary
24 Hour Summary
Clean out the HUD to 3172 mbdf.
POOH 170 m , Waited 1 hr for settling time.
RIH and dry tagged HUD at depth 3169 mbdf ( bottom perf at 3133 m )
POOH with 6" Bit and L/D 3.5" D/P till depth 1248 m
Update Since Report Time
Cont POOH with 6" Bit and L/D 3.5" D/P till depth 410 m
24 Hour Forecast
Cont POOH with 6" Bit and L/D 3.5" D/P to surface.
RIH W/ 4.5" CSG Gun on 2 7/8" V.T tubing.
Time Summary
10:00 1.00 0 O RIH and dry tagged HUD at depth 3169 mbdf.
11:00 13.00 0 O POOH with 6" Bit and L/D 3.5" D/P till depth 1248 m
Total 24.00
06.00 Update
Start Hours PH OPN Detail Drilled NPT Description
Depth (m) level
0:00 6.00 0 Cont POOH with 6" Bit and L/D 3.5" D/P till depth 410 m
Fluid Details
Mud type KCl Brine Oil/Water (%) pH/Pm (cc)
MD (m) TS/HGS/LGS (%) Pf/Mf (cc)
Mud Density (ppg) 8.50 Sand (%) Ca+ (ppm)
Vis (s/qt) Cl- (ppm)
PV/YP (cp/lbf/100ft²) MBT (lbm/bbl)
Gels 10 s/m (lbf/100ft²) LCM (lbm/bbl)
API/HTHP WL (cc/30min) ECD (ppg) R600/300 (°)
FC/HTHP FC (32nd") H2S (%) R200/100 (°)
KCl (%) R6/3 (°)
FL temp. (°F) Ditch Magnet in Last 24hrs/Cum. (gm)
Bulks Summary
Product Quantity Onboard Units Daily Usage
Toolstring Components
Item description # Jts Length OD Max OD ID Connection Weight Grade Serial no.
(m) (in) (in) (in) Name (ppf)
6" Milled Teeth Bit 1 0.190 6.000
Toolstring Details
Date/Time in Date/Time out BHA no. BHA Length (m) Min. ID (in) Purpose
6/1/2024 11:59PM 0.90
Personnel
Company Service No. of people Base Complement Reason for Deviation
BapetCo DSV 2
Dasco Catering 9
Dasco Crew 34
Halliburton Logging/Elec 1
Wirelinei
Sapesco Tubular Handling 4
Total 50