EP WELLS DAILY OPERATIONS REPORT Report 9 6/1/2024


Company EPM_BAPETCO
Well Type Appraisal
Well BAHGA-9
Wellbore BAHGA-9
WBS No/API No

Event Summary
Event Type Workover Event Start Date 5/23/2024 Days on Location 9.00
Objective Workover - Replace Completion Original Spud Date
Est. Days 0.00 Contractor Dasco
Work Unit Dasco 27 Days To Release
Rig Phone/FAX No. 3135

Well Status
Supervisor Mohamed Abdel Bar Measured Depth(m)

Engineer Ahmed Ros TVD(m)


Other Supervisor STP: A. Azim / NTP: M. Oun HSE. 24 Hr Progress(m)
A.G
Depth Ref/Grd Elev/Water Depth(m) DFE: 57.76 / 48.61 Hole size(in)
THF Datum
Daily NPT(hr/%) 0/0 Last Casing MD
Days Ahd(-) Bhnd(+)(50/50) 8.00 Next Casing MD
Actual cost to date/AFE 83,539/613 Current MW / BH EMW(ppg) 8.50/8.50

Actual divided by AFE 136.28 LOT/FIT EMW(ppg)


Daily Cost 11,183 Lithology
Formation/MD Top

Operating Rates

Rig Operating Rate(hr) 18.00 Auxiliary/Secondary Work(hr) 0.00


Rig Standby Rate(hr) 6.00 NX Auxiliary Floor Not Available(hr) 0.00
Rig Repair Rate(hr) 0.00 Rig Modified Rate(hr) 0.00
Rig Reduced Rate(hr) 0.00 Rig Lumpsum Rate(hr) 0.00
Rig Special Rate(hr) 0.00 Rig Lumpsum Operational Rate(hr) 0.00
Rig Zero Rate(hr) 0.00 Rig Force Majeur Rate(hr) 0.00
Rig BOP Activity Rate(hr) 0.00 Rig PMS Rate(hr) 0.00
Rig Secondary BOP Activity Rate(hr) 0.00

HSE Summary
Last Incident Date Days Last Incident Date Days KPI's

LWC 10/27/2022 583 PSI 1/14/2021 1,234 TRCF


RWC 1/14/2021 1,234 NII 1/14/2021 1,234 LWCF
MTC 10/27/2022 583 HPI 1/14/2021 1,234 Safety Cards - Safe 10
FAC 8/23/2021 1,013 GOAL ZERO DAYS 10/27/2022 583 Safety Card - Unsafe 7
Last casing pressure test PS BARRIER EVENT SSE%
PS barrier bowtie review Last casing pressure(psi)

Safety Comments:
LTI: 578 days
Safety Observation system (Stop cards):
- Total Number Daily/Monthly: 8 /10.
- Stop card participation: Bapetco=02, Dasco= 08, Service hand= 0
• Safe acts/condition: Good arranged &housekeeping in dog house and Rig floor.
• Unsafe acts: Observed one person talking with forklift operator during working operation (Stopped him).
• Unsafe conditions: There was the wire of air horse not arranged in its spool (F.M Arranged it).

** Barriers **
• Primary: 8.5 PPG.
• Secondary: BOP & FBSV.

6/2/2024 6:27:48AM Report Version: 4.1.16R9 Generated from data in EDM/OpenWells/PROFILE 1


RESTRICTED
EP WELLS DAILY OPERATIONS REPORT Report 9 6/1/2024
Well BAHGA-9
Wellbore BAHGA-9

**Current Activity/Phase**.
• POOH W/ 6”Bit assy on 3.5” D.P STG, by using Rig tong & L/D Same.

MOC’s/Deviations in place:
• Some well control equipment: (1- MOC for Annular BOP Rubber element 2- MOC for stand pipe and valves of manifold 3- MOC for
crown block sheaves.)
HSE Activities Today:
• Performed safety meeting with crew members before job.
• Preformed Discuss about confined space Session with crew member.
• Prepared the work permits before jobs.
• Weekly inspection for crane.
PTW register:
Total PTW: (Cold/Hot/Confined space: 2/0/0)
Open PTW: 1
Closed PTW: 1

HSE Drills
Drills/Tests Date Days Since Last

Last Derrick Inspection 3/25/2024 68 JSA's/Toolbox Talks


Last BOP function test 5/27/2024 5 Days Since Last Drill 8
Last BOP Test 5/27/2024 5
Next BOP Test 6/10/2024

HSE Inspections
Government Inspection
Company Inspection 3/22/2024

Operations Summary
24 Hour Summary
Clean out the HUD to 3172 mbdf.
POOH 170 m , Waited 1 hr for settling time.
RIH and dry tagged HUD at depth 3169 mbdf ( bottom perf at 3133 m )
POOH with 6" Bit and L/D 3.5" D/P till depth 1248 m
Update Since Report Time
Cont POOH with 6" Bit and L/D 3.5" D/P till depth 410 m
24 Hour Forecast
Cont POOH with 6" Bit and L/D 3.5" D/P to surface.
RIH W/ 4.5" CSG Gun on 2 7/8" V.T tubing.

Time Summary

Start Hours PH OPN Detail Drilled NPT Rig Description


Depth (m) level Rate
0:00 3.50 0 O P/U and M/U kelly

Established circulation and recorded free parameters.

Clean out the HUD to 3172 mbdf.


3:30 4.00 0 Y Pumped two batches of HVP 40 bbls each and 30 bbls brine in
between.

Circulating bottom up until got HVPs out and clear brine.


7:30 1.00 0 Y L/D kelly assymbly.

8:30 0.50 0 O POOH to depth 3,100 m.

9:00 1.00 0 Y Waited 1 hr for settling time.

10:00 1.00 0 O RIH and dry tagged HUD at depth 3169 mbdf.

11:00 13.00 0 O POOH with 6" Bit and L/D 3.5" D/P till depth 1248 m

**Pumped metal displacement


**Total POOH : 198/ 321 JT.

Total 24.00

6/2/2024 6:27:48AM Report Version: 4.1.16R9 Generated from data in EDM/OpenWells/PROFILE 2


RESTRICTED
EP WELLS DAILY OPERATIONS REPORT Report 9 6/1/2024
Well BAHGA-9
Wellbore BAHGA-9

06.00 Update
Start Hours PH OPN Detail Drilled NPT Description
Depth (m) level
0:00 6.00 0 Cont POOH with 6" Bit and L/D 3.5" D/P till depth 410 m

**Pumped metal displacement


**Total POOH : 285/ 321 JT.

Fluid Details
Mud type KCl Brine Oil/Water (%) pH/Pm (cc)
MD (m) TS/HGS/LGS (%) Pf/Mf (cc)
Mud Density (ppg) 8.50 Sand (%) Ca+ (ppm)
Vis (s/qt) Cl- (ppm)
PV/YP (cp/lbf/100ft²) MBT (lbm/bbl)
Gels 10 s/m (lbf/100ft²) LCM (lbm/bbl)
API/HTHP WL (cc/30min) ECD (ppg) R600/300 (°)
FC/HTHP FC (32nd") H2S (%) R200/100 (°)
KCl (%) R6/3 (°)
FL temp. (°F) Ditch Magnet in Last 24hrs/Cum. (gm)

Gas Concentrations and Fluid Losses


Avg Connection Gas (%) Avg. trip gas (%) Losses Last 24 Hours/Cumulative...
Max. connection gas (%) Max. trip gas (%) Surface Losses (bbl) /0.00
Avg. background gas (%) Avg H2S Gas (%) Sub Surface Losses (bbl) /0.00
Max. background gas (%) Max H2S Gas (%) Total Losses 0.00/0.00
End vol. (bbl) 0.00

Bulks Summary
Product Quantity Onboard Units Daily Usage

Diesel: Rig 7,135.00 Liters 1,080.00


Diesel: Main Camp 5,382.00 Liters 480.00

Toolstring Components
Item description # Jts Length OD Max OD ID Connection Weight Grade Serial no.
(m) (in) (in) (in) Name (ppf)
6" Milled Teeth Bit 1 0.190 6.000

Bit Sub 1 0.710

6 * 4 3/4" DC 1 54.800 4.750 2.375

Toolstring Details
Date/Time in Date/Time out BHA no. BHA Length (m) Min. ID (in) Purpose
6/1/2024 11:59PM 0.90

Personnel
Company Service No. of people Base Complement Reason for Deviation

BapetCo DSV 2
Dasco Catering 9
Dasco Crew 34
Halliburton Logging/Elec 1
Wirelinei
Sapesco Tubular Handling 4

Total 50