RA-Excavation & Backfilling
RA-Excavation & Backfilling
Consequence
Likelihood
Insignificant(1) Minor(2) Moderate(3) Major(4) Catastrophic(5)
Rare(1) 1 2 3 4 5
Possible(2) 2 4 6 8 10
Likely(3) 3 6 9 12 15
Often(4) 4 8 12 16 20
Frequent(5) 5 10 15 20 25
Risk Rating
15-25 Extreme Risk Activity should not proceed in current form
8-12 High Risk Activity should be modified to include planning and action and be subject to HSE detailed assessment
4-6 Moderate Risk Activity can operate subject to modification and/ or management
1-3 Low Risk No immediate action required unless escalation of risk is possible
S.NO Hazard(s)/Aspect Possible Person(s) at risk Existing Control Measures with mechanism from Current Additional Control Measure(s) required with mechanism from hierarchy of control for Residual risk
Consequences hierarchy of Control for each identified hazard Risk (With each identified hazard (after
/ Effects Controls ) additional
controls)
R
C
C
L
L
Damage to Electrocution, Contractor & Sub- Work shall start with proper NOC from all 2 3 6 All workmen must be given proper training on excavation safety. 2 1 2
1 Existing fire & explosion. contractor personnel existing services. Area should be barricaded and provide the caution sign board.
service Damage to Before doing excavation, "L" shape or "T" Only authorized person should be allow working area.
existing service. shape trial pit should be made for Working area should be barricaded well.
identifying the underground utilities. . Work will start only with the permits from authorities.
Approved route drawing & tracing of Work will carry out as per approved method statement and drawings.
existing services to be done thoroughly.
Use Cable Detector to find out existing
cable.
Where existing line there is should make
manual excavation.
Page 1 of 5
RISK ASSESSMENT FOR EXCAVATION AND BACKFILLING WORKS
Project No. N-17727
Project Title New 132/22 kV Substation at Hudayriat Island and Associated works
Client TRANSCO
Consultant WSP
Main Contractor ELMEC
Sub-Contractor Site Technology Ltd.co
Internal Document No. STL -N-17727-MS-CIV-001
Rev. 00
3 Hit by vehicle Personnel Contractor & Sub- Follow site safety rules. 2 3 6 Workmen should give proper training, work procedure. 2 1 2
injury, fatal, contractor personnel Observe and obey site caution boards. Wherever required flash light and revolving light provided.
property Wear safety shoes, helmet, visible vest, Close supervision/Monitoring by supervisor/Forman
damage. Goggles if needed. Watch your steps while walking in sites.
Housekeeping shall be conducted before STL shall Follow the ELMECS Excavation safety
start of work.
Deployment of banksman.
Follow site Traffic management plan
Page 2 of 5
RISK ASSESSMENT FOR EXCAVATION AND BACKFILLING WORKS
Project No. N-17727
Project Title New 132/22 kV Substation at Hudayriat Island and Associated works
Client TRANSCO
Consultant WSP
Main Contractor ELMEC
Sub-Contractor Site Technology Ltd.co
Internal Document No. STL -N-17727-MS-CIV-001
Rev. 00
4 Fall of Personnel Contractor & Sub- The excavated trench shall be sloped, 2 4 8 Monitoring need to be done for the provision made for access (walkways), 2 1 2
Person/ injury, fatal, contractor personnel stepped or shored as stated in the method hard barriers if the trench is kept open for a longer period.
Material/ property statement. No lone working shall be allowed.
Machinery damage Ladder at regular intervals or temporary Workmen shall not be allowed to sit near the edge of the excavation.
stairs by means of scaffold shall be PTW system should be followed.
provided for access and egress for
workmen.
The excavated trench shall be barricaded
by hard barrier , flash lights displayed and
revolving lights
The spoil removed from the trench shall
be kept 1M away from the trench.
Signage (Danger Deep Excavation, Men at
work, Services exposed etc.) shall be
displayed at regular intervals.
Operator of the machinery shall be
competent to do the job.
The placement of the machine shall be
checked for its stability.
Speed limit of the vehicle shall be
maintained to 20Km / Hr. at site.
5 Underground Trench collapse Contractor & Sub- Continuous dewatering is required. 3 2 6 Dedicated person is required to monitor the dewatering activity. 3 1 3
Water contractor personnel
Seepage
6 Electricity Electrocution Contractor & Sub- All temporary Electrical Supply shall be 3 3 9 All temporary Electrical supply shall be routed through ELCB/RCCB trip in 3 1 3
contractor personnel made by Competent Electrician. 30MA.
Proper Earthling of electrical parts shall Tool Box Talk Shall be conducted about Electrical Safety.
be ensured
All cables shall be treated as live unless
otherwise it is confirmed.
7 Inclement Heat Stress Contractor & Sub- Work should not be carried out in adverse 2 3 6 Provide tents/shelter for workmen. 2 1 2
Weather contractor personnel weather. Providing adequate information, Instruction, supervision and awareness on
Page 3 of 5
RISK ASSESSMENT FOR EXCAVATION AND BACKFILLING WORKS
Project No. N-17727
Project Title New 132/22 kV Substation at Hudayriat Island and Associated works
Client TRANSCO
Consultant WSP
Main Contractor ELMEC
Sub-Contractor Site Technology Ltd.co
Internal Document No. STL -N-17727-MS-CIV-001
Rev. 00
11 Access /Egress Personal injury Contractor & Sub Safe access by ladders to be ensured. 2 4 8 Full training and instruction provided in both induction and on- going safety 2 1 2
Property contractor personnel’s Access ladder should be secured by training.
damage bottom and above. PTW system should be followed
Access to the site must be controlled to Access to the site must be controlled to ensure the safety of site employees
Page 4 of 5
RISK ASSESSMENT FOR EXCAVATION AND BACKFILLING WORKS
Project No. N-17727
Project Title New 132/22 kV Substation at Hudayriat Island and Associated works
Client TRANSCO
Consultant WSP
Main Contractor ELMEC
Sub-Contractor Site Technology Ltd.co
Internal Document No. STL -N-17727-MS-CIV-001
Rev. 00
12 Manual Ligament Contractor & Sub Mechanical aids used wherever possible. 2 2 4 Full training and instruction provided in both induction and on- going safety 2 1 2
Handling strains. Muscle contractor personnel’s Assess the load training.
strains. Weights marked on all loads. Mechanical aids used wherever possible.
Fatigue. Mandatory PPE worn
Abdominal
hernias.
Prolapsed/her
niated discs.
13 Vehicle Personnel Contractor & Sub Driver/ Operators must be competent and 3 3 9 Do not drive under pressure. 3 1 3
accidents injury/death contractor personnel’s having valid UAE driving license/ 3rd party Always keep an eye on the other vehicles during driving.
during the Property certificates. Proper sign boards and warning boards to be provided.
activity damage/produ Proper maintenance of vehicles at regular Always follow road traffic rules and regulations
ction loss intervals. Only construction vehicles allowed to entering into site areas.
Access/ egress must be clear and safe to Competent banks man/ signal man should be available with equipment during
use. operation.
Do not drive in poor weather.
14 Slip/Trip Personnel Injury Contractor & Sub Proper housekeeping and material 2 3 6 TBT should be given to all the workforce. 2 1 2
Property contractor stacking should be done. Emergency procedures should be explain to all the workforce.
damage personnel’s Proper and clear access& egress must be Standard fencing should be provided around the site to avoid unauthorized
provided for safe movement of the work entry.
force. Use proper PPE.
Stockpile area to be barricaded and
adequate signage should be provided.
Page 5 of 5