Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

AL JINAN PROJECT

CONTRACTOR’S DAILY REPORT


Project No: C010 Work Package No: MC01

CONTRACTOR: TGCC REPORT NO: 015-C010-MC01-TG-DR-0286

PROJECT: AL JINAN DATE: 15/04/2023

PROJECT MANAGER/AGENT: ZOUHAIR BELHADI RESIDENT ENGINEERS: ELOUED ZAKARIA

SUBCONTRACTORS: LONGOMETAL – SOMARETREC

M T W T F S
S : Sunny C : Cloudy R : Rainy
WEATHER S S S S S S
H : High M : Medium L : Low
HUMIDITY M M M M M M

TEMPERATURE Max 22 23 21 22 23 22

TEMPERATURE min 10 10 14 9 11 9

CONTRACTOR’S MANPOWER EQUIPMENT


Staff M T W T F S Direct M T W T F S TYPE Qt
Labor
Project Director 1 1 1 1 1 1 Carpenter 139 137 137 135 135 134 Backhoe excavator 1
Project Manager 1 1 1 1 1 1 Steel fixer 9 9 9 9 9 9 Soil Compactor Roller 1
Site Manager 2 2 2 1 2 2 Mason 23 23 23 22 22 25 Trucks 2
Site Engineers 2 2 2 2 2 2 Driver 8 8 8 8 8 8 Mobile Crane 0
Foreman 16 16 16 16 16 16 Operator 7 7 7 7 7 7 Rock Breaker 0
Admin / Secretary 2 2 2 2 2 2 Welder 2 2 2 2 2 2 Crane/Mobile Crane 6
Quality Manager 1 1 1 1 1 1 Rigger 6 6 6 6 6 6 Mini loader 1
Maid 1 1 1 1 1 1 Electrician 2 2 2 2 2 2 Drilling machine 0
Security guard 9 9 9 9 9 9 Plumber 1 1 1 1 1 1 TOTAL 11
Topographer 1 1 1 1 1 1 Worker 154 155 157 154 154 153
Site supervisor 2 2 2 2 2 2 Flagman 4 4 4 4 4 4 WORKFORCE DISTRIBUTION
Security Animator 1 1 1 1 1 1
HOTEL MALL : 344
TOTAL 39 39 39 38 39 39 TOTAL 355 354 356 353 353 358
A B C
76 72 151 121

Staff LONGOMETAL SOMARETREC TOTAL

Site Engineer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Site Manager 2 2 2 2 2 2 1 1 1 1 1 1 3 3 3 3 3 3

Foreman 2 2 2 2 2 2 0 0 0 0 0 0 2 2 2 2 2 2
Worker 56 56 56 56 56 56 6 6 6 6 6 6 62 62 62 62 62 62

CONSTRUCTION ACTIVITIES
See attached separate Daily Work Program sheets
For the Contractor:
ELOUED
ZAKARIA
Page 1 of 1 Document No: 015-C010-MC01-TG-DR-0286
AL JINAN PROJECT

CONTRACTOR’S DAILY WORKS PROGRAM (CDWP) FOR (15/04/2023)

REF DISCIPLINE ACTIVITY LOCATION TEST TYPE OF TEST FORECAST EXECUTED Comments

01 Casting Pouring concrete in the columns R2 Hotel/ U.S.G FLOOR /Z3/ axe y’ YES Slump + sampling 2 m3 2 m3 -

02 Formwork Form work of the stairs N°3 Hotel / G.F to 1st floor NO - - - -

03 Formwork Formwork of the beams Hotel/U.S.1ST FLOOR/Z1 NO - - - -


N80/N79/BN/N37/N22A/N54
04 Reinforcement Reinforcement of the beams Hotel/U.S.1ST FLOOR/Z1 NO - - - -

05 Casting Pouring concrete in the columns P1/P2 MALL / 2nd floor/A YES Slump + sampling 4 m3 4 m3 -

06 Casting Pouring concrete in the stairs wall N°2 MALL / 2nd floor/A YES Slump + sampling 8 m3 8 m3 -

-
07 Formwork Formwork for the pre-stressed beams MALL / U.S.2nd floor/A/[F.H] NO - - -

08 Reinforcement Reinforcement of the slab MALL / U.S G.floor/A/[b.d][6.9] NO - - - -

09 Formwork Formwork for the pre-stressed beams MALL / G Floor/B/ [F.H] [6’.9] NO - - - -

10 Formwork Formwork of the slab MALL / U.S.G Floor/B/[F.D] [6’.9] NO - - - -


11 Formwork Formwork of the slab MALL / U.S.1ST BASEMENT/B/[J.K][L.L””] NO - - - -
NO -
Reinforcement Reinforcement of the columns 4 P2 MALL / G.FLOOR /C/ - - -
12
Masonry Installation of the first low of masonry MALL / 2nd basement - -
13 NO - -

Page 1 of 15 Document No: 015-C010-MC01-TG-DR-0286


AL JINAN PROJECT

Program of the 17/04/2023


REF DISCIPLINE ACTIVITY LOCATION QUANTITY

01 Reinforcement Reinforcement of the columns P21 P8 Hotel/ F FLOOR /Z3/ axe (R//S) -

02 Casting Pouring concrete in the beams N57A N72A N71 N42A Hotel / F Floor /Z2 AXE (2->3//I->L) 8m 3

03 Reinforcement Reinforcement of the beams N56 N30 N37 N70 Hotel/U.S.1ST FLOOR/Z2 -

04 Reinforcement Reinforcement of the beams Hotel/U.S.1ST FLOOR/Z1 -

05 Casting Pouring concrete in the core walls Hotel/U.S.1ST FLOOR/Z3/AXE (R->S//2->3) 10m 3

06 Casting Pouring concrete in the Beams A66 A36 A73 A32 A3 MALL / 2nd floor/A 10 m3

07 Reinforcement Reinforcement of the Columns MALL / G floor/C -

08 Casting Pouring concrete in the columns 2P2 P1 MALL / G floor/C AXE(D//F) 5m 3

09 Masonry Installation of the first low of masonry MALL / 2nd basement -

Page 2 of 15 Document No: 015-C010-MC01-TG-DR-0286


AL JINAN PROJECT

Hotel/ F floor
Page 3 of 15 Document No: 015-C010-MC01-TG-DR-0286
AL JINAN PROJECT

Mall / Bloc A / B3 to 2nd Floor


Page 4 of 15 Document No: 015-C010-MC01-TG-DR-0286
AL JINAN PROJECT

Mall / Bloc B /B3 to B1

Page 5 of 15 Document No: 015-C010-MC01-TG-DR-0286


AL JINAN PROJECT

Mall // bloc b//G floor

Page 6 of 15 Document No: 015-C010-MC01-TG-DR-0286


AL JINAN PROJECT

Project :AL JENAN Date : 15/04/2023

Point to check C N.C Team or Area Correction actions

Cleanliness of the 
construction site and public access arrangements
road
Wearing of personal
protective equipment (TGCC  request to the subcontractor for the PPE
and subcontractors) obligation
Presence of HSE signs on 
the site
Availability of drinking 
water
Delimitation, identification 
and layout of storage areas
Development of
passageways and traffic  Passage cleaning
lanes
Signs and posters for the
respect of the 10km/h
speed limit inside the 
construction site

Sufficient lighting  Job site lighting reinforcement


Delimitation of work areas  Work zone
Presence of compliant
guardrails (rail, under rail  Work zone the skirting boards are being
and baseboard) installed
Protections and enclosures
for rotating machines  Mechanic
Compliant electrical Building site
installation  and offices
Compliant electrical box
with differential circuit 
breaker
Presence of grounding 

Presence of markings in Work zone


areas at risk  marking of areas
Page 7 of 15 Document No: 015-C010-MC01-TG-DR-0286
AL JINAN PROJECT

Clean and tidy


scaffolding  Tagging the scafolding
Strict prohibition Team
of work on  Leaders awareness-raising for team leaders
ladders and
stepladders
Condition of the 
blade towers Work zone
Wear safety
harnesses with  Work zone awareness-raising for team leaders
lifeline in ereas
without
guardrails
Presence of
specific
equipment for  Welders
individual
protection of
welders (apron,
leather gloves,
welding helmet...)
Limitation of the Welders
welding area 
Presence of fire Offices,
extinguishers in  Cranes, (fill in the checklists)
sufficient number store
Storage of
chemical
products in  Store
compliance
(separation,
ventilation of the
room, MSDS,
posting)
Presence of a
compliant,  (fill in the checklists)
watertight
hazardous waste
collection area

Page 8 of 15 Document No: 015-C010-MC01-TG-DR-0286


Sorting Store zone (fill in the checklists)
hazardous waste 
Daily watering of  Site access
the site
Daily follow-up of  (fill in the checklists) In process
the machines
Separation of
liquid and solid 
waste
No burning or
burying of waste  Job site
on the site

Daily awareness  Meeting Theme : Respect for railings / effectif : 07


of the teams point

Page 9 of 15 Document No: 015-C010-MC01-TG-DR-0286


AL JINAN PROJECT

installation of the lifeline installation of railing

Page 10 of 15 Document No: 015-C010-MC01-TG-DR-0286


AL JINAN PROJECT

installation of the lifeline access to the emergency exit

Name & First Name Function signature

Entered by Hicham BELGHOLAM Supervisor EHS

Page 11 of 15 Document No: 015-C010-MC01-TG-DR-0286

You might also like