Contractor'S Daily Report: Project No
Contractor'S Daily Report: Project No
M T W T F S
S : Sunny C : Cloudy R : Rainy
WEATHER S S S S S S
H : High M : Medium L : Low
HUMIDITY M M M M M M
TEMPERATURE Max 22 23 21 22 23 22
TEMPERATURE min 10 10 14 9 11 9
Site Engineer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Site Manager 2 2 2 2 2 2 1 1 1 1 1 1 3 3 3 3 3 3
Foreman 2 2 2 2 2 2 0 0 0 0 0 0 2 2 2 2 2 2
Worker 56 56 56 56 56 56 6 6 6 6 6 6 62 62 62 62 62 62
CONSTRUCTION ACTIVITIES
See attached separate Daily Work Program sheets
For the Contractor:
ELOUED
ZAKARIA
Page 1 of 1 Document No: 015-C010-MC01-TG-DR-0286
AL JINAN PROJECT
REF DISCIPLINE ACTIVITY LOCATION TEST TYPE OF TEST FORECAST EXECUTED Comments
01 Casting Pouring concrete in the columns R2 Hotel/ U.S.G FLOOR /Z3/ axe y’ YES Slump + sampling 2 m3 2 m3 -
02 Formwork Form work of the stairs N°3 Hotel / G.F to 1st floor NO - - - -
05 Casting Pouring concrete in the columns P1/P2 MALL / 2nd floor/A YES Slump + sampling 4 m3 4 m3 -
06 Casting Pouring concrete in the stairs wall N°2 MALL / 2nd floor/A YES Slump + sampling 8 m3 8 m3 -
-
07 Formwork Formwork for the pre-stressed beams MALL / U.S.2nd floor/A/[F.H] NO - - -
09 Formwork Formwork for the pre-stressed beams MALL / G Floor/B/ [F.H] [6’.9] NO - - - -
01 Reinforcement Reinforcement of the columns P21 P8 Hotel/ F FLOOR /Z3/ axe (R//S) -
02 Casting Pouring concrete in the beams N57A N72A N71 N42A Hotel / F Floor /Z2 AXE (2->3//I->L) 8m 3
03 Reinforcement Reinforcement of the beams N56 N30 N37 N70 Hotel/U.S.1ST FLOOR/Z2 -
05 Casting Pouring concrete in the core walls Hotel/U.S.1ST FLOOR/Z3/AXE (R->S//2->3) 10m 3
06 Casting Pouring concrete in the Beams A66 A36 A73 A32 A3 MALL / 2nd floor/A 10 m3
Hotel/ F floor
Page 3 of 15 Document No: 015-C010-MC01-TG-DR-0286
AL JINAN PROJECT
Cleanliness of the
construction site and public access arrangements
road
Wearing of personal
protective equipment (TGCC request to the subcontractor for the PPE
and subcontractors) obligation
Presence of HSE signs on
the site
Availability of drinking
water
Delimitation, identification
and layout of storage areas
Development of
passageways and traffic Passage cleaning
lanes
Signs and posters for the
respect of the 10km/h
speed limit inside the
construction site