REKAPITULASI SLIPFORM JL ROW 14 MVS

No Item Pekerjaan BAHAN UPAH


1 Pekerjaan perapihan,kupas & pemadatan basecourse Rp 8,762,000.00 Rp 2,822,880.00

2 Pekerjaan Cor Slipform Kanstin Rp 24,080,000.00 Rp 21,531,400.00

TOTAL : Rp 32,842,000.00 Rp 24,354,280.00


SUBTOTAL : Rp 57,196,280.00
HARGA PER M1 Rp 58,441.07

RAB SLIPFORM JL ROW 14 MVS


No Item Pekerjaan sat vol harga satuan jumlah
1
Pekerjaan perapihan,kupas & pemadatan basecourse
Upah
Upah pekerjaan Kupas,gelar basecourse,pemadatan m2 293.61 Rp 8,000.00 Rp 2,348,880.00
Upah gali & psg pipa 3 in outlet titik 79 Rp 6,000.00 Rp 474,000.00
Rp 2,822,880.00
Bahan
Pipa 4 in btg 30 Rp 90,000.00 Rp 2,700,000.00
Knee Pipa 4 in bh 79 Rp 18,000.00 Rp 1,422,000.00
mata Gergaji besi sanflex bh 2 Rp 25,000.00 Rp 50,000.00
sapu lidi bh 3 Rp 8,000.00 Rp 24,000.00
Basecourse rit 1 Rp 2,500,000.00 Rp 2,500,000.00
stemper hari 7 Rp 250,000.00 Rp 1,750,000.00
mobilisasi stemper ls 1 Rp 100,000.00 Rp 100,000.00
Bensin stemper hari 9 Rp 24,000.00 Rp 216,000.00
Rp 8,762,000.00
2 Pekerjaan Cor Slipform Kanstin
Upah
Upah cor m1 978.7 Rp 22,000.00 Rp 21,531,400.00
Rp 21,531,400.00
Bahan
Beton m3 27 Rp 850,000.00 Rp 22,950,000.00
Benang pack 1 Rp 50,000.00 Rp 50,000.00
semen zak 2 Rp 50,000.00 Rp 100,000.00
Plastik Cor m1 20 Rp 4,000.00 Rp 80,000.00
koordinasi beton rit 4 Rp 100,000.00 Rp 400,000.00
cetakan slipform bh 1 Rp 500,000.00 Rp 500,000.00
Rp 24,080,000.00