1 Pekerjaan perapihan,kupas & pemadatan basecourse Rp 8,762,000.00 Rp 2,822,880.00
2 Pekerjaan Cor Slipform Kanstin Rp 24,080,000.00 Rp 21,531,400.00
TOTAL : Rp 32,842,000.00 Rp 24,354,280.00
SUBTOTAL : Rp 57,196,280.00 HARGA PER M1 Rp 58,441.07
RAB SLIPFORM JL ROW 14 MVS
No Item Pekerjaan sat vol harga satuan jumlah 1 Pekerjaan perapihan,kupas & pemadatan basecourse Upah Upah pekerjaan Kupas,gelar basecourse,pemadatan m2 293.61 Rp 8,000.00 Rp 2,348,880.00 Upah gali & psg pipa 3 in outlet titik 79 Rp 6,000.00 Rp 474,000.00 Rp 2,822,880.00 Bahan Pipa 4 in btg 30 Rp 90,000.00 Rp 2,700,000.00 Knee Pipa 4 in bh 79 Rp 18,000.00 Rp 1,422,000.00 mata Gergaji besi sanflex bh 2 Rp 25,000.00 Rp 50,000.00 sapu lidi bh 3 Rp 8,000.00 Rp 24,000.00 Basecourse rit 1 Rp 2,500,000.00 Rp 2,500,000.00 stemper hari 7 Rp 250,000.00 Rp 1,750,000.00 mobilisasi stemper ls 1 Rp 100,000.00 Rp 100,000.00 Bensin stemper hari 9 Rp 24,000.00 Rp 216,000.00 Rp 8,762,000.00 2 Pekerjaan Cor Slipform Kanstin Upah Upah cor m1 978.7 Rp 22,000.00 Rp 21,531,400.00 Rp 21,531,400.00 Bahan Beton m3 27 Rp 850,000.00 Rp 22,950,000.00 Benang pack 1 Rp 50,000.00 Rp 50,000.00 semen zak 2 Rp 50,000.00 Rp 100,000.00 Plastik Cor m1 20 Rp 4,000.00 Rp 80,000.00 koordinasi beton rit 4 Rp 100,000.00 Rp 400,000.00 cetakan slipform bh 1 Rp 500,000.00 Rp 500,000.00 Rp 24,080,000.00