Q1. When there is a single data movement of the 4 types the functional size is?
Ans: 8

Q2. A project size of 200 KLOC is to be developed. Software development team has
average experience on similar type of projects. The project schedule is not very tight.
Calculate the Effort, development time, average staff size, and productivity of the project.

Solution: The semidetached mode is the most appropriate mode, keeping in view the size,
schedule and experience of development time.

Hence E=3.0(200)1.12=1133.12PM
D=2.5(1133.12)0.35=29.3PM

P = 176 LOC/PM

Q3. For the given activities determine:


1. Critical path using PERT.
2. Calculate variance and standard deviation for each activity.
3. Calculate the probability of completing the project in 26 days.
∴ The critical path = 1-2-4-6 with time duration (tcp) of 24 days.

Q4.
Q5.

Q6.
Q7

Q8.
Q 9. Say that you can either receive $3,200 today and invest it at a rate of 4% or take a lump sum
of $3,500 in a year. Calculating the PV of $3,500 can help you make a choice.

Q10. Calculate the Return on Investment