Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

2.

5% Retation Payment certficate

Project :Sojato River Bridge Project Amount ( Birr)


Span Length: 14m 1. Main Contract
Location: W/ Arsi Zone, Kore Woreda 2. Contigency
Type of Project: New 3. Suppl. Contract
Budget Source: Oromiya Regional Government 4. Variation Order No
Client/Employer : West Arsi Zone Road and Logistic office 5. Others
Contractor : H.B.F Road construction Plc 6. 15% VAT
Consultant : West Arsi Zone Road and Logistic office Total Sum
Client Supervisor/inspector from Aanaa/zone Road Office :
637,589.03
637,589.03

Previous consecutive payments to the Contractor With outVAT


IPC NO. Date Amount(Birr)
ACP 2,989,266.00
ICP NO-1 7,343,434.53
ICP NO-2 5,275,289.21
ICP NO-3 3,837,340.43
ICP NO-4 (Final Peyment) 4,783,052.93
ICP NO-5
ICP NO-6
ICP NO-7
ICP NO-8
ICP NO-9
ICP NO-10
ICP NO-11
ICP NO-12
Total 21,239,117.10

Amount of advance taken (20%) due to Cash Received for


Amount of advancere-paid previuos(20%) due to cash
Received
Amount of advance re-paid this month
Amount of advance remaining out of ( 20%) due to Cash
Received
Amount of advance re-paid to date( 20%) due to Cash

We, the Supervising Engineers or his/her representatives certify


that the Contractor is now entitled to the net sum of 637,589.03
(Six Hundred Thrity Seven Thousands Five Hundred Eighty Nine
Birr and cents 03/100 only including 15% VAT) on this paymnet
certificate

Measured & submitted By _______________


Approved By_______________
Certified By _______________
General Manager of the Contractor
Zone Supervising Engineer
Regulatory Body