Professional Documents
Culture Documents
HIAEP Alternative Proposal Technical Proposal
HIAEP Alternative Proposal Technical Proposal
HIAEP Alternative Proposal Technical Proposal
ALTERNATIVE TENDER
Technical
Proposal
June 2018
1 Alternate Tender
Submission
Section 1 - Introduction
Our ‘Alternative’ reflects an optimised de-risking approach which mitigates those critical
challenges which potentially threaten the security of your programme objectives.
You need the assurance that your PM/CM team not only understands the challenges and identified risks of your
Programme, but also has the knowledge and ability to meet the challenges and mitigate the risks. Our team
brings direct experience and lessons learned from some of the world’s largest and most complex aviation and
major infrastructure projects. We will focus on solutions that incorporate an integrated view of challenge
resolution and risk mitigation.
Our experience in the design, project and construction management of major international aviation programmes consistently
demonstrates that an appropriate execution strategy is critical to the successful outcome of mega projects. Our Alternative Approach is
heavily influenced by our relevant global aviation and large project delivery experience, combined with proven ‘know how’ of executing
complex major projects. In developing this alternative approach, we assembled key management and delivery personnel with relevant
experience from successful major projects to participate in an interactive planning workshop designed to challenge the current approach
and identify realistic alternatives which would positively impact project delivery certainty. This workshop was set up to create a
collaborative pre-contract project environment, in which the team would effectively engage in their management and technical lead
activities, consistent with their nominated positions on the project delivery team. This process facilitated the opportunity for:
• a disciplined deep dive into HIAEP programme scope and project understanding;
• assessing delivery of Facilities to support growing demand;
• an interrogation of the RFP’s schedules and potential acceleration of proposal timelines; and
• an understanding of the programme interfaces, impact and importance to the HIAEP.
1
Alternate Tender Submission
We noted that as the demand grows to a 53 MAP, there will be a shortage of capacity to accommodate that demand until the new
improvements are transitioned.
Exhibit 1-1 illustrates the correlation between demand and capacity development per the HIA’s baseline programme.
Exhibit 1-2 illustrates the potential capacity increase by accelerating the delivery of the WTAP (Alternative Strategy Sub-element #3).
Exhibit 1-1. HIA Forecast on Annual Passenger Growth Exhibit 1-2. Potential Capacity Increase
Discussion Focus
A summary of key discussion points can be expressed as follows:
• The challenge of this programme is the number of concurrent projects delivered within an incredibly aggressive schedule, in a
highly complex operating environment (The projected annual work in place is approx. QAR 2.5 to 3 billion).
• On recent programmes Jacobs found that 60% of design changes and time impacts were due to stakeholder and interface issues.
• Development of Alternative Approach which benefits the HIAEP by:
–– Reducing interface risks;
–– Reducing logistical complexity;
–– Reducing PM/CM manpower required to deliver the required scope; and
–– Improving integration quality.
All of the above have the potential to significantly impact cost and schedule security.
To achieve the aforementioned Alternative Approach recommendations the team focused on the followings:
1. Packaging / Concurrent Works: a package strategy that supports the accelerated timelines, maintains manageability, optimise the
de-risking of critical inter-dependencies.
2. Project Management / Groupings: evaluation of the various work packages to determine the optimal clustering of projects to
ensure effective management, restructure PM/CM team to an area management approach.
3. Programme Execution Timeline: examining opportunities to shorten listed durations, examining means and methods to achieve.
4. Contracting Strategy: assess procurement activities which overlapped with predecessor/successor activities, discussed strategies
to mitigate risk to proposed delivery methodology.
5. Constructability / Logistics: ensure the design and construction packaging approach aligns with safe and appropriate
construction best practices and site logistic requirements.
6. Technical Interface/System Integration: Identifying the required stakeholders, documenting the requested items for incorporation
into projects, ensuring inclusion and proper coordination, communication. Identify the airport systems (IT, VDGS, CUTE, FIDS,
BHS, etc.) to be integrated into the project for the operation of the airport.
7. Regulatory Requirements: considering package envelopes which support on efficient and logical ‘regulatory compliance’ journey.
–– Interfaces identified;
–– Permitting Process; and
–– Internal or External Reviews.
8. Decision Marking: to aid and facilitate HIAEP to make the appropriate decisions
2
Alternate Tender Submission
Presented below is our team’s assessment of key challenges, risks, approaches to mitigation and benefits to the programme. Also,
using our project planning and technical analysis experience, we developed this alternative strategy which comprises of three
sub-elements.
Strategy sub-element which positively
impacts the respective challenge Disciplined application if PM/CM best
Critical Challenges
practices to compliant delivery strategy
#1 #2 #3
Challenge 1 - Packaging/Concurrent Work Packages
Challenge 2 - Programme Execution Timeline
Challenge 3 - Construction Logistics
Challenge 4 - Technical Interfaces
Challenge 5 - Regulatory Requirements
Challenge 6 - Decision Marking
Challenge 7 - Monitoring and Managing Progress
These three sub-elements combine to accumulatively maximise the mitigation of the identified key challenges. The integration of these
considerations into the overall delivery strategy will provide optimal de-risking to the programme with positive benefits for schedule,
cost and operational security.
The relevance of those three alternative approach strategies to the critical challenges is shown on the table above which highlights a
beneficial impact on the subject challenge.
3
Alternate Tender Submission
B15
Z1
Z1
A1
C2
Z1
B18
A2
HIA Terminal
Building
Expansion to C3 A1 B11 B17
53 MAP
(Phase 1) Baggage System Upgrade
Z1 B18
A1
Temp Baggage Facility
A1
Z1
4
Alternate Tender Submission
5
Alternate Tender Submission
Project Director
PACKAGE B
Project Manager
Secondary Works
CCTV System Enhancement as per MOI Foreign Objects Debris Detection Access Control System
B1 SSD Law 9 Compliance B5 System for Runway B9
Completion of MOI Wireless Network for Updated Airport Master Plan - Design
B3 B8 Airside Panoramic Surveillance B16 Consultancy Services
Emergency Services Communications
CONTROLS
- Project Controls
CONTROLS TECHNICAL CONSTRUCTION
Manager Programmer (1) Design Manager (1) Site Inspector: Civil (1)
- Contracts Manager
- Cost Manager
Contracts Manager (1) Mechanical Engineer (1) Site Inspector: Mechanical (1)
- Document Control Project Controls/Contracts Assistant (1) Electrical Engineer (1) Site Inspector: Electrical (2)
Manager
Special Systems/Security Engineer (3) Site Inspector: Security/Special Sys (3)
TECHNICAL
- Lead Design
Manager
- Contracts Manager
- Aviation Security
Specialist
CONSTRUCTION
- Lead Construction
Manager
- HS & E Manager
7
Alternate Tender Submission
PACKAGE D
Project Manager
Secondary Works
Major Incident Response Interim Baggage Handling QACC Building Expansion ATM and CNS Systems at the D2 General Consultancy Services
D6 Facility D1 Facility D3 D9 QATCC
Qatar Museums Artwork Multi-Level Midfield Car Park
D4 Programme 2 Years Maintenance of D16
Modifications at Main Bag Chute - Supply and
D7 D8 D10 the ATM and CNS Systems Ras Abu Abboud Road
Security Checkpoint No. 1 Installation at each PLB D17 Embankments
Allocated Space for General installed at the QATCC
D5 Authority of Customs in
Interim Cargo Handling Cargo Terminal Upgrade of the existing ATM Ras Abu Abboud Road Street
D15 Facility - Phase 2 D11 and CNS systems at DIA D18 Lighting - Fix and Installation
at DIA area
D20 PCA Upgrade to existing QM Artwork Program -
D13 Electric Fountain, ‘Relief
Upgrade of the existing ATM
D12 and CNS systems at HIA
PLB’s D19 Miscellaneous Works
2009’ and ‘Under the Volcano’
QM Artwork Program -
D14 Fabrication and Installation of
Paper Plane
CONTROLS
- Project Controls
Manager Procurement Only
- Contracts Manager Project Controls/Contracts Manager (1)
- Cost Manager
- Document Control Project Controls/Contracts Assistant (2)
Manager
TECHNICAL
- Lead Design
Manager
- Contracts Manager
- Aviation Security
Specialist
CONSTRUCTION
- Lead Construction
Manager
- HS & E Manager
8
Alternate Tender Submission
Exhibit 1-10. Example of Logistic Planning for Atlanta Airport Terminal Programme
9
Alternate Tender Submission
10
Alternate Tender Submission
11
Alternate Tender Submission
External Factors:
• Never underestimate the importance of third party deliverables.
• Unpredictable conditions: Status of historical/statistical wind speed data, climatic conditions such as sandstorms. All are important
considerations as they are beyond the control of the contractors and cause potential delays.
• Cash flow plans must be communicated well in advance with the HIAEPSC to secure timely payments to the contractors.
We will be reviewing programme requirements to assess the potential to recommend the Design/Build (D/B), Progressive Design/Build
(PD/B) or Construction Manager at Risk (CMAR) delivery methodologies. Figure A-13 illustrates the potential saving in project
execution periods that can be achieved.
12
Alternate Tender Submission
Exhibit 1-14. Example of Work Schedule (Level 1) with Indications of Key Milestones
13
Alternate Tender Submission
We have identified alternative construction packaging approaches to simplify procurement and significantly reduce coordination and
interface issues across multiple contracts.
We have identified construction logistical modifications which reduce the construction durations of critical activities related to capacity
enhancements. In so doing, we will ensure the potential increase in (early) capacity is achieved to support the growing demand. We
welcome a discussion with HIAEPSC to consolidate and assess implementation potential recommendations.
The graphics (Exhibit 1-15 and Exhibit 1-16) below show some of the anticipated construction activities during the Q1 2020 which
illustrates the complexity of coordination of construction with ongoing operations. With a peak workforce numbering in the thousands,
and massive volumes of materials being moved on and off site, the need to consider and plan construction logistics is a fundamental
part of constructability planning.
14
Alternate Tender Submission
15
Alternate Tender Submission
16
Alternate Tender Submission
• Response time vs. schedule requirements – even with parties communicating well and with genuine intent, the issue of delays in
the consultant design and construction activities or unforeseen changes in stakeholder requirements are likely to exist, thus putting
the interface milestones and budget at risk.
• Volume of interface work – with so many interfaces, interfacing parties, and conversations required to work through the interface
details, the amount of coordination required to reach agreements and resolve differences will be substantial. The challenge is how
to manage the sheer volume of work involved with the whole interface process during the project design stages. If not properly
coordinated, these interfaces will cause changes during construction.
18
Alternate Tender Submission
Our permitting strategy for respective packages will be managed by the Lead Design Manager, respective project design managers
and project designers who will work closely with the assigned HIAEPSC representative responsible for regulatory interfaces. Our Lead
Design Manager, individual project/design managers and project design team will familiarise themselves with the regulatory
requirements and prepare project permitting matrices to track progress. The project design consultants will support the permitting
process throughout the design and construction phases.
Based on our Alternative packaging analysis, we will split the Project into the following five main permitting approaches:
• PTC Early Works, PTC Main Expansion, and North Node Hotel and Lounges.
• WTAP and Fuel Farm.
• Cargo/Canine Facilities.
• Waste Water Treatment Plant Works.
• Others.
Permitting for the various secondary projects may be included with the main projects above, or done on a project basis.
Permitting requirements will be included on the project schedules. Given the magnitude of the permitting requirements, we see a need
to have early discussions with the regulatory agencies to discuss their ability to process the permits in accordance with the Project
schedule. If the agencies do not have the resources to process the permits to maintain our schedule, we will need to evaluate priorities
and/or consider the possibility of funding additional staff to conduct regulatory design reviews.
19
Alternate Tender Submission
20
Alternate Tender Submission
21
Alternate Tender Submission
22
CH2M HILL International B.V.
18th floor (West),
Al Reem Tower
West Bay
P O Box 22798
Doha, Qatar
T + 974 4 403 0555
F + 974 4 442 1898
www.ch2m.com
P O Box 207339
Burj Doha Tower
26th Floor Al Corniche Street
West Bay Doha, Qatar
www.snclavalin.com