Professional Documents
Culture Documents
Buhaly 1995
Buhaly 1995
Downloaded by UNIVERSITY OF NEW SOUTH WALES on July 30, 2015 | http://arc.aiaa.org | DOI: 10.2514/6.1995-2454
David A. Buhaly
Thiokoi Corporation
Brigham City, UT
3Ist A I M A S ME/SAE/ASEE
Joint Propulsion Conference and Exhibit
July
- 10-12,1995/San Diego, CA -
For permissionto copy or republish, contact Thiokol Corporation, Defense and Launch Vehicle Division,
P.O. Box 689, Brlgham Clty, UT 843024689.
AIM-95-2454
David A. Buhaly
Thiokol Corporation
Brigham City, Utah
development program began in 1988 with the designed to a factor of safety of 1.4 (versus a typical
realization that a small satellite launch vehicle market 1.25 factor) while maintaining a high mass fraction of
was emerging. Internal analyses and numerous 0.93. The internal insulation uses silica-filled ethylene
interviews with key customers revealed that a new propylene diene monomer (EPDM) rubber. The aft
rocket motor would be needed to meet the requirements dome also incorporates Kevlar@ in the EPDM. The
of this market. A subscale demonstration motor was internal insulation was initially designed to a 1.5 factor
tested in 1990. After analyzing the results of this test, a of safety in the aft end and 1.25 in the forward end of
full-scale motor demonstration test was performed in the motor. After gathering full-scale static test results
1992. A third qualification test was successfully showing lower than predicted erosion, it was decided
performed in 1993. Finally, the first flight motor, for that the inert weight of future motors could be reduced
the Lockheed Launch Vehicle, was completed and by over 200 pounds while maintaining a common
delivered in January, 1995. Along the way, full-scale thermal factor of safety of 1.4. Typical factors of safety
motor case structural and burst tests were performed. for ballistic missiles are in the range of 1.15. This
This development program was conservative and costly, change will be incorporated in all motors fabricated
but much less so than a typical defense rocket motor after 1 October 1995.
development program. Key lessons can be gained from
analyzing the decisions made during this program that The nozzle is very similar to that used in the
d should be incorporated into future programs such as the Peacekeeper motor. It uses a 3-D carbon-carbon throat
Evolved Expendable Launch Vehicle. from a billet fabricated by Textron Industries, a carbon
cloth phenolic liner, and a PAN-based medium density
Castor 120 Motor Description phenolic structural overwrap. This nozzle is designed
to thermal and structural factors of safety (1.5) that are
The Castor 120 motor is the same diameter much higher than typical programs.
(92-inches) as the Peacekeeper first stage motor and
about 20 inches longer (351 inches) (Figure 1). It Thrust vector control is provided by an
contains about 10,000 pounds more propellant. These AlliedSignal cold gas blowdown system. It is a low
key similarities allowed u s to make maximum use of cost, highly reliable system similar to that used on the
existing facilities and tooling for propellant casting, Castor IVB and on Orbital Science's Taurus launch
case fabrication, nozzle fabrication, stage assembly, and vehicle. The system includes an electronic loop closure
transportation. unit which conditions both commands and performance
data for telemetry downlink. The design requirements
The motor propellant, a typical Class 1.3 hydroxyl- were developed with AlliedSignal concurrently with the
terminated polybutadiene (HTPB) formulation, differs motor design, which contributed to the low cost of the
from the Peacekeeper propellant in two key areas. The system.
burn rate is lower, allowing the Castor 120 to burn
50 percent longer than the Peacekeeper, reducing the The systems tunnel was developed and installed on
acceleration forces on the payload. The second the second static test motor. This experience proved
difference is that the Castor 120 propellant burn rate is invaluable as we worked with Lockheed to integrate
adjusted by using an iron oxide burn rate catalyst vehicle cabling and ordnance lines. The envelope and
instead of changing the proportions of the ground attach points for all cables were defined well before the
ammonium perchlorate sizes. This allows the Castor vehicle cabling was fabricated.
u
' Castor 120 is a registered trademark of Thiokol Corporation.
Release B:
"Copyright 0 1995 by Thiokol Corporation. Published by the American Institute of Aeronautics and Astronautics,
Inc. with permission."
I
92.9"
t
59.8"
Downloaded by UNIVERSITY OF NEW SOUTH WALES on July 30, 2015 | http://arc.aiaa.org | DOI: 10.2514/6.1995-2454
Vectorable
Internal Insulation Nozzle
- 302.3"
350.9"
Firmre 1. Castor 120 Motor
Develooment Proeram
Desien AnDroaCh
goo
~
r ~~
2
American Institute of Aeronautics and Astronautics
Demonstration Static Tests Motor Case CaRabilitv Tests
We began our test program with a subscale Beyond proving ballistic performance, it is critical
demonstration motor. This motor (46-inch diameter, that the motor case’s capability be proven through full-
25,000 pounds) was tested in March 1990. This scale testing. This testing consisted of a full-scale
successful test proved many of the key, low cost skirt/case structural test and a full-scale case hydroburst
materials and processes that were eventually used in the test. The structural testing was completed in October
full-scale Castor 120 motor. Some new processes were 1993. Both compressive and tensile tests were
considered too risky and were abandoned before performed. The test article failed in a compressive test
committing to full-scale fabrication. During early mode at a load of 10,414 pounds per circumferential
development of the full-scale motor, we experienced a inch at the skidcase attach point. This test proved
case failure during initial bydroproof testing. This acceptable capability for all first and second stage
failure was due to the usage of rigid adhesive in-line vehicle configurations and provides confidence
attachment of the skirts to the pressure vessel. for the strap-on applications.
Downloaded by UNIVERSITY OF NEW SOUTH WALES on July 30, 2015 | http://arc.aiaa.org | DOI: 10.2514/6.1995-2454
3
American Institute of Aeronautics and Astronautics
is required to certify each hazardous shipment, they
need full details on the cargo and shipping
configuration. The process can take up to nine months,
so it is never too early to get started. In our case, we
L,
were able to break some new ground for the
commercial launch vehicle market. Before this motor
shipment, no commercial solid rocket motor had been
shipped with the linear shape charge (classified as 1.1
ordnance) installed. This ordnance had to he installed
at the launch site, greatly increasing processing time,
complexity, and facility requirements. We argued that a
shipment with linear shape charges installed constituted
no greater risk than the shipment of the motor itself
This rationale was accepted by the DOT.
Downloaded by UNIVERSITY OF NEW SOUTH WALES on July 30, 2015 | http://arc.aiaa.org | DOI: 10.2514/6.1995-2454
4
American Institute of Aeronautics and Astronautics
requirements to push to the edge of the performance Lockheed Launch Vehicle. It has heen a long series of
envelope. Weight must he reduced to the greatest small steps to get to this point, each a critical
extent and total impulse must be increased to get the accomplishment. The small commercial market is
2 vehicle out of the silo fast and get to the target with the gaining momentum rapidly and the Castor 120 will he a
greatest amount of firepower. I n a commercial major player on a variety of launch vehicles. When this
program, performance is important, hut it must he paper is presented in July, I fully expect to he able to
balanced at least equally with reliability and low cost. share successful flight results in addition to the data
It is especially true for the small launch vehicle market pmvided within the current version. The only tasks that
that low cost is the name of the game. Therefore, the need to be completed to fully take advantage of the
Castor 120, built for the commercial market increases potential of this motor is development and test of
safety factors to reduce the cost and reliability impact of strap-on hardware and a casting core consistent with a
manufacturing variability. Our target is to build and long ballistic tailoff to reduce thrust imbalance.
deliver a low cost rocket motor to the launch site that
will work each and every time. Future development efforts should take into
Downloaded by UNIVERSITY OF NEW SOUTH WALES on July 30, 2015 | http://arc.aiaa.org | DOI: 10.2514/6.1995-2454
5
American Institute of Aeronautics and Astronautics