TA SK DESCRIPTION DURATI ON Man Power START END START END UPDATE 7 ON
NO. In Days DATE DATE ACTUAL DATE DECEMBER PROGRESS
A UNIT-2 FOR MILL NO.B 150
1 Dismantling of existing Mill no.2 for Unit-2 15 2-
GANGS 16-9-19 30-9-19 100%
DRAG CHAIN FEEDER ASSEMBLY ELECTRICAL &
G INSTRUMENTATION WORKS 12 4-11-19 15-11-19
Ensure completion of civil work such as
1 foundation/fixing as per requirement/drawing. 1 4-11-19 4-11-19
100%
Installation of the electrical panel and alignment
2 of all 03 chain 1 5-11-19 5-11-19 conveyors 100% Laying of cables as per cable schedule and cable 3 glanding at both ends for all 03 chain conveyor 3 1- GANG 6-11-19 8-11-19 100% Cable Termination at both panel end and field 4 side for all 03 chain conveyors 3 9-11-19 11-11-19 100% Continuity checking of the cables for all 03 chain 5 conveyors 2 12-11-19 13-11-19 100%
Installation of the ZSS sensor, flow sensor and
6 cable termination of the same for all 03 chain 1 14-11-19 14-11-19 conveyors. 100% Charging of the panel and feedback checkings 7 for all 03 chain 1 15-11-19 15-11-19 conveyors. 100% I All Electrical & Instrumentation activities 45 10-12-19 23-1-20 1 Preliminary Activities 3 10-12-19 12-12-19 100% 2 Cable Tray Installation 14 13-12-19 26-12-19 100% 3 Cable Pulling & Laying Cable 10 21-12-19 30-12-19 100% 4 Installation of Control Pannels 6 13-12-19 18-12-19 100%
Cable Termination at both panel end and field 2- GANGS
5 side for Panel 14 31-12-19 13-1-20 Airblaster, Panel PLC & Panel Power. 100% 6 Continuity Test 5 9-1-20 13-1-20 100% 7 Download Program PLC 1 14-1-20 14-1-20 100% 8 IO Test Mill A 1 15-1-20 15-1-20 100% 9 Test Integration to DCS 2 16-1-20 17-1-20 DURATI SR. TA SK DESCRIPTION ON In Man START END START END UPDATE 7 ON NO. Days Power DATE DATE ACTUAL DATE DECEMBER PROGRESS
Dismantling of existing Mill no.2 for 2-
1 Unit-2 15 GANGS 16-9-19 30-9-19 100%
Removing of Existing Civil foundation 2-
2 and macking of new 45 GANGS 1-10-19 14-11-19 100% foundation as per drawing.
ERECTION & COMMISSIONING COAL
B GRINDING SYSTEM FOR 135 1-10-19 12-2-20 MILL NO.1 C AIR BLASTERS 30 10-11-19 9-12-19 Ground assembly of air blasters as per 1 drawing 4 10-11-19 13-11-19 100% Installation of Air blasters Nozzles at 1- GANG 2 Hopper 14 14-11-19 27-11-19 100% 3 Pipe line connections of Air blasters 9 28-11-19 6-12-19 100% 4 Installation of Control Pannels 3 7-12-19 9-12-19 100% D ROD GATE ASSEMBLY 3 1-10-19 3-10-19 Installation of Rod gate assembly as 1- GANG 1 per drawing 3 1-10-19 3-10-19 100% E MANUAL PNEUMATIC GATE ASSEMBLY 4 4-10-19 7-10-19 Installation of Manual Pneumatic Gate 1- GANG 1 Assembly as per drawing 4 4-10-19 7-10-19 100%
F DRAG CHAIN FEEDER ASSEMBLY 30 8-10-19 6-11-19
Ensure completion of civil work such as
1 foundation, footings & insert plate 1 8-10-19 8-10-19 100% fixing as per requirement/drawing.
Checking and marking of foundation
center lines and elevation 2 levels by piono wires as per GA 1 9-10-19 9-10-19 100% drawing
Fixing of rod gate, slide gate, expansion
3 bellow and inlet chute to the silo as 5 10-10-19 14-10-19 100% drawing and alignment.
Erection of the casing below inlet and
other casings along casing supports with respective match marks in side of the casings. Apply silicon sealents at 4 the casing joints and ensure for use of 8 15-10-19 22-10-19 100% correct fasteners as per drawing 1- GANG
Alignment of the casings i.e.
Straightness, water level, Input & 5 Output matching with feeding 2 23-10-19 24-10-19 100% equipments. Add shim plates wherever necessary.
6 Installation of the conveying chain 2 25-10-19 26-10-19 100%
Installation of the drive assembly, transmission chain and 7 alignment of the same. Electrical 4 26-10-19 30-10-19 100% connection of the drive.
Installtion of the Zero speed and flow
8 sensor and connections 1 31-10-19 31-10-19 100% Pre-commissioning activity - Final inspection, Greasing of all bearing 9 points, Lubricants filling, baffle plate 2 1-11-19 2-11-19 100% setting, etc. Commissioning activity - No-load trial 10 and load trial. 1 3-11-19 3-11-19 H HP 743 BOWL MILL COMPONENTS 95 10-11-19 12-2-20 Checking and marking of foundation center lines and elevation 1 levels by piano wires fixing 2 10-11-19 11-11-19 100% arrangement Preparation of packing shims for Gear 2 box base plate 3 10-11-19 12-11-19 100% Erection and initial alignment of Gear 3 box Sole plate 2 13-11-19 14-11-19 100% Pocket Grouting and curing of 4 foundation bolts of Gearbox ba 4 15-11-19 18-11-19 100%
5 Fianl alignment of Gearbox Sole plate 2 19-11-19 20-11-19 100%
Installation and Alignment of Existing
6 Mounting Plate with 1 21-11-19 21-11-19 100% respective Main Gear box Sole plate. Installation and alignment of Main 7 Gearbox 1 22-11-19 22-11-19 100% Installation and alignment of Mill side 8 assembly with 2 23-11-19 24-11-19 100% respective Main Gearbox Confirmation of the seal gaps to Mill 9 side to gear box 1 25-11-19 25-11-19 100%
Installation and initial alignment of
10 main motor Sole Plate 1 26-11-19 26-11-19 100% with respective Main Gearbox
Installation & Initial Alignemnt of Main
11 Motor with respective Main Gearbox 1 27-11-19 27-11-19 100%
12 Pocket Grouting of Motor Sole Plate. 4 28-11-19 1-12-19 100%
Final alignment of Main Motor with 13 respective Main Gearbox 2 2-12-19 3-12-19 100%
Full grouting of Mill side Mounting
14 plates, Gear Box Base 4 4-12-19 7-12-19 100% plate and and motor base frame.
Blue Matching of Bowl hub Assembly
15 with respective Main 3 11-11-19 13-11-19 100% Gear box out put flange Ground assembly of Vane wheel 16 assembly. 1 10-11-19 10-11-19 100% Installation and alignment of Bowl hub 17 assembly 2 8-12-19 9-12-19 100%
Installation and alignment of Bull ring
18 segments and clamping Ring assembly 3 10-12-19 12-12-19 100%
19 Alignment of vane wheel assembly 1 13-12-19 13-12-19 100%
20 Installation of scraper assembly 2 14-12-19 15-12-19 100% 21 Alignment of Scrapper Assembly. 2 16-12-19 17-12-19 100% Installation of Bowl hub Air seals 22 assembly. 2 10-12-19 11-12-19 100% Alignment of Bowl hub Air Seal 23 Assembly 1 12-12-19 12-12-19 100% Installation of Stuffing Rope or Gland 24 Packing. 1 13-12-19 13-12-19 100% 2- GANGS 2- 25 Installation of the bowl hub Insulation. 4 GANGS 14-12-19 17-12-19 100% Installation of the Separator body 26 Assembly. 2 13-12-19 14-12-19 100%
27 Alignment of Separator body assembly 1 15-12-19 15-12-19 100%
28 Installation of Air restriction Ring 2 16-12-19 17-12-19 100% 29 Installation of Intermediate Plate 4 18-12-19 21-12-19 100% Installation of Inner Cone assembly 30 with linning and it's support 2 22-12-19 23-12-19 100% Installation and Alignment of Feed 31 Chute. 4 24-12-19 27-12-19 100% Installation of Sepearator Top 32 assembly. 1 27-12-19 27-12-19 100% Installation of Journal Heads and it' 33 Trunnion shafts. 3 28-12-19 30-12-19 100% Installation of Journal shaft assembly 34 with Grinding Rolls. 3 31-12-19 2-1-20 100%
35 Installation of Journal Head Linners. 3 3-1-20 5-1-20 100%
36 Tilt-in the Grinding Journal Assembly. 3 6-1-20 8-1-20 100%
37 Installation of Stop bolts and O rings to 6 9-1-20 14-1-20 100%
Journal Opening Covers.
38 Installation of Journal Spring Assembly. 6 15-1-20 20-1-20 100%
Installation of Entire cover assembly to 39 the Mill. 2 21-1-20 22-1-20 100%
40 Installation of Mill Out let connections 7 27-12-19 2-1-20 80%
41 Installation of Knife Gate Valves 4 27-12-19 30-12-19 100% Installation of Knife Gate Valves Piping 42 work 7 31-12-19 6-1-20 80% Installation of Aspirating fitting 43 assembly 2 31-12-19 1-1-20 100% 44 Installation of Seal Air Piping 10 27-12-19 5-1-20 100% Installation of Gearbox lubrication 45 system and it's accessories. 3 13-12-19 15-12-19 100% Flushing of Gearbox lubrication system 46 Pipings. 2 16-12-19 17-12-19 100%
47 Installation of Pyrites box assembly. 3 16-12-19 18-12-19 100%
Installation of Knife Gate Valves for 48 Pyrite box assembly. 2 19-12-19 20-12-19 100%
49 Installation of Mill Instrumentation and 30 11-12-19 9-1-20 90%
it's Controls. Insulate the Mill Side Hot Air Entry 50 Portion. 30 17-12-19 15-1-20 90% 51 Installation of Mill Platform 15 17-12-19 31-12-19 100% Installation of N2 Air Line connection 52 Piping 7 23-12-19 29-12-19 100%
Check all equipment, box-up the
53 pulveriser and make ready 2 23-1-20 24-1-20 95% for operation. 54 All Miscallaneous Jobs. 15 31-12-19 14-1-20 95% 55 No Load Trail Runs of All Equepments 3 25-1-20 27-1-20 70% All DCS Controls & Programing Activities Emersion 7 17-1-20 23-1-20 Commissioning of Entire Mill Circuit.
Cold & Hot Commissioning with DCS
list to be provide 20 24-1-20 12-2-20 (Commissioning Team)