Schedule Pekerjaan 5 January

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

SR.

TA SK DESCRIPTION DURATI ON Man Power START END START END UPDATE 7 ON


NO. In Days DATE DATE ACTUAL DATE DECEMBER PROGRESS

A UNIT-2 FOR MILL NO.B 150

1 Dismantling of existing Mill no.2 for Unit-2 15 2-


GANGS 16-9-19 30-9-19
100%

DRAG CHAIN FEEDER ASSEMBLY ELECTRICAL &


G INSTRUMENTATION WORKS 12 4-11-19 15-11-19

Ensure completion of civil work such as


1 foundation/fixing as per requirement/drawing. 1 4-11-19 4-11-19

100%

Installation of the electrical panel and alignment


2 of all 03 chain 1 5-11-19 5-11-19
conveyors
60%
Laying of cables as per cable schedule and cable
3 glanding at both ends for all 03 chain conveyor 3 1- GANG 6-11-19 8-11-19
40%
Cable Termination at both panel end and field
4 side for all 03 chain conveyors 3 9-11-19 11-11-19

Continuity checking of the cables for all 03 chain


5 conveyors 2 12-11-19 13-11-19

Installation of the ZSS sensor, flow sensor and


6 cable termination of the same for all 03 chain 1 14-11-19 14-11-19
conveyors.

Charging of the panel and feedback checkings


7 for all 03 chain 1 15-11-19 15-11-19
conveyors.
70%
I All Electrical & Instrumentation activities 45 10-12-19 23-1-20
1 Preliminary Activities 3 10-12-19 12-12-19 100%
2 Cable Tray Installation 14 13-12-19 26-12-19 80%
3 Cable Pulling & Laying Cable 10 21-12-19 30-12-19 80%
4 Installation of Control Pannels 6 13-12-19 18-12-19 40%

Cable Termination at both panel end and field 2- GANGS


5 side for Panel 14 31-12-19 13-1-20
Airblaster, Panel PLC & Panel Power.
40%
6 Continuity Test 5 9-1-20 13-1-20

7 Download Program PLC 1 14-1-20 14-1-20

8 IO Test Mill A 1 15-1-20 15-1-20

9 Test Integration to DCS 2 16-1-20 17-1-20


DURATI
SR. TA SK DESCRIPTION ON In Man START END START END UPDATE 7 ON
NO. Days Power DATE DATE ACTUAL DATE DECEMBER PROGRESS

Dismantling of existing Mill no.2 for 2-


1
Unit-2
15
GANGS 16-9-19 30-9-19 100%

Removing of Existing Civil foundation 2-


2 and macking of new 45 GANGS 1-10-19 14-11-19 100%
foundation as per drawing.

ERECTION & COMMISSIONING COAL


B GRINDING SYSTEM FOR 135 1-10-19 12-2-20
MILL NO.1
C AIR BLASTERS 30 10-11-19 9-12-19
Ground assembly of air blasters as per
1 drawing 4 10-11-19 13-11-19 100%
Installation of Air blasters Nozzles at 1- GANG
2 Hopper 14 14-11-19 27-11-19 100%
3 Pipe line connections of Air blasters 9 28-11-19 6-12-19 100%
4 Installation of Control Pannels 3 7-12-19 9-12-19 100%
D ROD GATE ASSEMBLY 3 1-10-19 3-10-19
Installation of Rod gate assembly as 1- GANG
1 per drawing 3 1-10-19 3-10-19 100%
E MANUAL PNEUMATIC GATE ASSEMBLY 4 4-10-19 7-10-19
Installation of Manual Pneumatic Gate 1- GANG
1 Assembly as per drawing 4 4-10-19 7-10-19 100%

F DRAG CHAIN FEEDER ASSEMBLY 30 8-10-19 6-11-19

Ensure completion of civil work such as


1 foundation, footings & insert plate 1 8-10-19 8-10-19 100%
fixing as per requirement/drawing.

Checking and marking of foundation


center lines and elevation
2
levels by piono wires as per GA
1 9-10-19 9-10-19 100%
drawing

Fixing of rod gate, slide gate, expansion


3 bellow and inlet chute to the silo as 5 10-10-19 14-10-19 100%
drawing and alignment.

Erection of the casing below inlet and


other casings along casing supports
with respective match marks in side of
the casings. Apply silicon sealents at
4 the casing joints and ensure for use of 8 15-10-19 22-10-19 100%
correct fasteners as per drawing
1- GANG

Alignment of the casings i.e.


Straightness, water level, Input &
5 Output matching with feeding 2 23-10-19 24-10-19 100%
equipments. Add shim plates wherever
necessary.

6 Installation of the conveying chain 2 25-10-19 26-10-19 100%


Installation of the drive assembly,
transmission chain and
7
alignment of the same. Electrical
4 26-10-19 30-10-19 80%
connection of the drive.
Installtion of the Zero speed and flow
8
sensor and connections
1 31-10-19 31-10-19 100%

Pre-commissioning activity - Final


9 inspection, Greasing of all bearing 2
points, Lubricants filling, baffle plate 1-11-19 2-11-19
setting, etc.
Commissioning activity - No-load trial
10 and load trial. 1 3-11-19 3-11-19
H HP 743 BOWL MILL COMPONENTS 95 10-11-19 12-2-20
Checking and marking of foundation
center lines and elevation
1 levels by piano wires fixing 2 10-11-19 11-11-19 100%
arrangement
Preparation of packing shims for Gear
2 box base plate 3 10-11-19 12-11-19 100%
Erection and initial alignment of Gear
3 box Sole plate 2 13-11-19 14-11-19 100%
Pocket Grouting and curing of
4 foundation bolts of Gearbox ba 4 15-11-19 18-11-19 100%

5 Fianl alignment of Gearbox Sole plate 2 19-11-19 20-11-19 100%

Installation and Alignment of Existing


6 Mounting Plate with 1 21-11-19 21-11-19 100%
respective Main Gear box Sole plate.
Installation and alignment of Main
7 Gearbox 1 22-11-19 22-11-19 100%
Installation and alignment of Mill side
8 assembly with 2 23-11-19 24-11-19 100%
respective Main Gearbox
Confirmation of the seal gaps to Mill
9 side to gear box 1 25-11-19 25-11-19 100%

Installation and initial alignment of


10 main motor Sole Plate 1 26-11-19 26-11-19 100%
with respective Main Gearbox

Installation & Initial Alignemnt of Main


11
Motor with respective Main Gearbox
1 27-11-19 27-11-19 100%

12 Pocket Grouting of Motor Sole Plate. 4 28-11-19 1-12-19 100%


Final alignment of Main Motor with
13
respective Main Gearbox
2 2-12-19 3-12-19 100%

Full grouting of Mill side Mounting


14 plates, Gear Box Base 4 4-12-19 7-12-19 100%
plate and and motor base frame.

Blue Matching of Bowl hub Assembly


15 with respective Main 3 11-11-19 13-11-19 100%
Gear box out put flange
Ground assembly of Vane wheel
16 assembly. 1 10-11-19 10-11-19 100%
Installation and alignment of Bowl hub
17 assembly 2 8-12-19 9-12-19 100%

Installation and alignment of Bull ring


18 segments and clamping Ring assembly 3 10-12-19 12-12-19 100%

19 Alignment of vane wheel assembly 1 13-12-19 13-12-19 100%


20 Installation of scraper assembly 2 14-12-19 15-12-19 100%
21 Alignment of Scrapper Assembly. 2 16-12-19 17-12-19 100%
Installation of Bowl hub Air seals
22 assembly. 2 10-12-19 11-12-19 100%
Alignment of Bowl hub Air Seal
23 Assembly 1 12-12-19 12-12-19

Installation of Stuffing Rope or Gland


24 Packing. 1 13-12-19 13-12-19

2-
25 Installation of the bowl hub Insulation. 4 GANGS 14-12-19 17-12-19 100%
Installation of the Separator body
26 Assembly. 2 13-12-19 14-12-19 100%

27 Alignment of Separator body assembly 1 15-12-19 15-12-19 100%


28 Installation of Air restriction Ring 2 16-12-19 17-12-19 100%
29 Installation of Intermediate Plate 4 18-12-19 21-12-19 100%
Installation of Inner Cone assembly
30
with linning and it's support
2 22-12-19 23-12-19 100%
Installation and Alignment of Feed
31 Chute. 4 24-12-19 27-12-19 100%
Installation of Sepearator Top
32 assembly. 1 27-12-19 27-12-19 100%
Installation of Journal Heads and it'
33
Trunnion shafts.
3 28-12-19 30-12-19 100%
Installation of Journal shaft assembly
34
with Grinding Rolls.
3 31-12-19 2-1-20 100%

35 Installation of Journal Head Linners. 3 3-1-20 5-1-20 100%


36 Tilt-in the Grinding Journal Assembly. 3 6-1-20 8-1-20 100%

37 Installation of Stop bolts and O rings to 6 9-1-20 14-1-20 100%


Journal Opening Covers.

38 Installation of Journal Spring Assembly. 6 15-1-20 20-1-20 100%


Installation of Entire cover assembly to
39 the Mill. 2 21-1-20 22-1-20 100%

40 Installation of Mill Out let connections 7 27-12-19 2-1-20 80%


41 Installation of Knife Gate Valves 4 27-12-19 30-12-19 100%
Installation of Knife Gate Valves Piping
42 work 7 31-12-19 6-1-20 80%
Installation of Aspirating fitting
43 assembly 2 31-12-19 1-1-20 100%
44 Installation of Seal Air Piping 10 27-12-19 5-1-20 100%
Installation of Gearbox lubrication
45 system and it's accessories. 3 13-12-19 15-12-19 100%
Flushing of Gearbox lubrication system
46 Pipings. 2 16-12-19 17-12-19

47 Installation of Pyrites box assembly. 3 16-12-19 18-12-19 100%


Installation of Knife Gate Valves for
48 Pyrite box assembly. 2 19-12-19 20-12-19 100%

49 Installation of Mill Instrumentation and 30 11-12-19 9-1-20 90%


it's Controls.
Insulate the Mill Side Hot Air Entry
50 Portion. 30 17-12-19 15-1-20 90%
51 Installation of Mill Platform 15 17-12-19 31-12-19 100%
Installation of N2 Air Line connection
52 Piping 7 23-12-19 29-12-19 50%

Check all equipment, box-up the


53 pulveriser and make ready 2 23-1-20 24-1-20
for operation.
54 All Miscallaneous Jobs. 15 31-12-19 14-1-20 80%
55 No Load Trail Runs of All Equepments 3 25-1-20 27-1-20

You might also like