SR.

DURATI ON Man Power START END START END UPDATE 7 ON


TA SK DESCRIPTION
NO. In Days DATE DATE ACTUAL DATE DECEMBER PROGRES
S
A UNIT-2 FOR MILL NO.B 150

1 Dismantling of existing Mill no.2 for Unit-2 15 2-


GANGS 16-9-19 30-9-19
100%

G DRAG CHAIN FEEDER ASSEMBLY ELECTRICAL & 12


INSTRUMENTATION WORKS 4-11-19 15-11-19

Ensure completion of civil work such as


1 foundation/fixing as per requirement/drawing. 1 4-11-19 4-11-19

100%

Installation of the electrical panel and alignment


2 of all 03 chain 1 5-11-19 5-11-19
conveyors
50%

3 Laying of cables as per cable schedule and cable 3


glanding at both ends for all 03 chain conveyor 6-11-19 8-11-19
1- GANG

4 Cable Termination at both panel end and field 3


side for all 03 chain conveyors 9-11-19 11-11-19

5 Continuity checking of the cables for all 03 chain 2


conveyors 12-11-19 13-11-19

Installation of the ZSS sensor, flow sensor and


6 cable termination of the same for all 03 chain 1 14-11-19 14-11-19
conveyors.

Charging of the panel and feedback checkings


7 for all 03 chain 1 15-11-19 15-11-19
conveyors.

I All Electrical & Instrumentation activities 45 10-12-19 23-1-20

1 Preliminary Activities 3 10-12-19 12-12-19 100%


2 Cable Tray Installation 14 13-12-19 26-12-19 80%
3 Cable Pulling & Laying Cable 10 21-12-19 30-12-19 80%
4 Installation of Control Pannels 6 13-12-19 18-12-19 33%

Cable Termination at both panel end and field 2- GANGS


5 side for Panel 14 31-12-19 13-1-20
Airblaster, Panel PLC & Panel Power.
40%
6 Continuity Test 5 9-1-20 13-1-20

7 Download Program PLC 1 14-1-20 14-1-20

8 IO Test Mill A 1 15-1-20 15-1-20

9 Test Integration to DCS 2 16-1-20 17-1-20


SR. DURATI Man START START END UPDATE 7 ON
NO. TA SK DESCRIPTION ON In Power DATE END DATE ACTUAL DATE DECEMBER PROGRESS
Days
Dismantling of existing Mill 2-
1
no.2 for Unit-2
15
GANGS 16-9-19 30-9-19 100%

Removing of Existing Civil


2-
2 foundation and macking of new 45
GANGS 1-10-19 14-11-19 100%
foundation as per drawing.

ERECTION & COMMISSIONING


B COAL GRINDING SYSTEM FOR 135 1-10-19 12-2-20
MILL NO.1

C AIR BLASTERS 30 10-11-19 9-12-19


Ground assembly of air blasters
1 as per drawing 4 10-11-19 13-11-19 100%
Installation of Air blasters
2 Nozzles at Hopper 14 1- GANG 14-11-19 27-11-19 100%
Pipe line connections of Air
3 blasters 9 28-11-19 6-12-19 100%

4 Installation of Control Pannels 3 7-12-19 9-12-19 100%


D ROD GATE ASSEMBLY 3 1-10-19 3-10-19
Installation of Rod gate 1- GANG
1 assembly as per drawing 3 1-10-19 3-10-19 100%
MANUAL PNEUMATIC GATE
E ASSEMBLY 4 4-10-19 7-10-19

Installation of Manual 1- GANG


1 Pneumatic Gate Assembly as 4 4-10-19 7-10-19 100%
per drawing
DRAG CHAIN FEEDER
F ASSEMBLY 30 8-10-19 6-11-19

Ensure completion of civil work


such as foundation, footings &
1 insert plate fixing as per 1 8-10-19 8-10-19 80%
requirement/drawing.

Checking and marking of


foundation center lines and
2 elevation 1 9-10-19 9-10-19 100%
levels by piono wires as per GA
drawing

Fixing of rod gate, slide gate,


expansion bellow and inlet
3 chute to the silo as drawing and 5 10-10-19 14-10-19 100%
alignment.
Erection of the casing below
inlet and other casings along
casing supports with respective
match marks in side of the
casings. Apply silicon sealents
at the casing joints and ensure
4 for use of correct fasteners as 8 15-10-19 22-10-19 20%
per drawing

1- GANG
1- GANG
Alignment of the casings i.e.
Straightness, water level, Input
&
5 Output matching with feeding 2 23-10-19 24-10-19
equipments. Add shim plates
wherever necessary.

Installation of the conveying


6 chain 2 25-10-19 26-10-19

Installation of the drive


assembly, transmission chain
7 and 4
alignment of the same. 26-10-19 30-10-19
Electrical connection of the
drive.

Installtion of the Zero speed


8 and flow sensor and 1 31-10-19 31-10-19
connections

Pre-commissioning activity -
9 Final inspection, Greasing of all 2
bearing points, Lubricants 1-11-19 2-11-19
filling, baffle plate setting, etc.

Commissioning activity - No-


10 load trial and load trial. 1 3-11-19 3-11-19
HP 743 BOWL MILL
H COMPONENTS 95 10-11-19 12-2-20

Checking and marking of


foundation center lines and
1 elevation 2 10-11-19 11-11-19 100%
levels by piano wires fixing
arrangement
Preparation of packing shims
2 for Gear box base plate 3 10-11-19 12-11-19 100%

Erection and initial alignment


3 of Gear box Sole plate 2 13-11-19 14-11-19 100%

Pocket Grouting and curing of


4 foundation bolts of Gearbox ba 4 15-11-19 18-11-19 100%

Fianl alignment of Gearbox Sole


5 plate 2 19-11-19 20-11-19 100%

Installation and Alignment of


Existing Mounting Plate with
6 respective Main Gear box Sole 1 21-11-19 21-11-19 100%
plate.
Installation and alignment of
7 Main Gearbox 1 22-11-19 22-11-19 100%
Installation and alignment of
8 Mill side assembly with 2 23-11-19 24-11-19 100%
respective Main Gearbox
Confirmation of the seal gaps
9 to Mill side to gear box 1 25-11-19 25-11-19

Installation and initial


alignment of main motor Sole
10
Plate
1 26-11-19 26-11-19 100%
with respective Main Gearbox

Installation & Initial Alignemnt


11 of Main Motor with respective 1 27-11-19 27-11-19 100%
Main Gearbox
Pocket Grouting of Motor Sole
12 Plate. 4 28-11-19 1-12-19 100%

Final alignment of Main Motor


13 with respective Main Gearbox 2 2-12-19 3-12-19 100%

Full grouting of Mill side


14 Mounting plates, Gear Box Base 4 4-12-19 7-12-19 30%
plate and and motor base
frame.

Blue Matching of Bowl hub


15 Assembly with respective Main 3 11-11-19 13-11-19 100%
Gear box out put flange

Ground assembly of Vane


16 wheel assembly. 1 10-11-19 10-11-19 100%
Installation and alignment of
17 Bowl hub assembly 2 8-12-19 9-12-19 30%
Installation and alignment of
18 Bull ring segments and 3 10-12-19 12-12-19 50%
clamping Ring assembly
Alignment of vane wheel
19 assembly 1 13-12-19 13-12-19

20 Installation of scraper assembly 2 14-12-19 15-12-19 100%


Alignment of Scrapper
21 Assembly. 2 16-12-19 17-12-19
Installation of Bowl hub Air
22 seals assembly. 2 10-12-19 11-12-19
Alignment of Bowl hub Air Seal
23 Assembly 1 12-12-19 12-12-19
Installation of Stuffing Rope or 2-
24 Gland Packing. 1 GANGS 13-12-19 13-12-19
Installation of the bowl hub
25 Insulation. 4 14-12-19 17-12-19 100%
Installation of the Separator
26 body Assembly. 2 13-12-19 14-12-19 50%
Alignment of Separator body
27 assembly 1 15-12-19 15-12-19
Installation of Air restriction
28 Ring 2 16-12-19 17-12-19
Installation of Intermediate
29 Plate 4 18-12-19 21-12-19

Installation of Inner Cone


30 assembly with linning and it's 2 22-12-19 23-12-19
support
Installation and Alignment of
31 Feed Chute. 4 24-12-19 27-12-19
Installation of Sepearator Top
32 assembly. 1 27-12-19 27-12-19

33 Installation of Journal Heads 3


and it' Trunnion shafts. 28-12-19 30-12-19

Installation of Journal shaft


34 assembly with Grinding Rolls. 3 31-12-19 2-1-20

Installation of Journal Head


35 Linners. 3 3-1-20 5-1-20
Tilt-in the Grinding Journal
36 Assembly. 3 6-1-20 8-1-20

Installation of Stop bolts and O


37 rings to Journal Opening 6 9-1-20 14-1-20
Covers.
Installation of Journal Spring
38 Assembly. 6 15-1-20 20-1-20
Installation of Entire cover
39 assembly to the Mill. 2 21-1-20 22-1-20
Installation of Mill Out let
40 connections 7 27-12-19 2-1-20

41 Installation of Knife Gate Valves 4 27-12-19 30-12-19


Installation of Knife Gate Valves
42 Piping work 7 31-12-19 6-1-20
Installation of Aspirating fitting
43 assembly 2 31-12-19 1-1-20

44 Installation of Seal Air Piping 10 27-12-19 5-1-20


Installation of Gearbox
45 lubrication system and it's 3 13-12-19 15-12-19
accessories.
Flushing of Gearbox lubrication
46 system Pipings. 2 16-12-19 17-12-19
Installation of Pyrites box
47 assembly. 3 16-12-19 18-12-19

Installation of Knife Gate Valves


48 for Pyrite box assembly. 2 19-12-19 20-12-19

Installation of Mill
49 Instrumentation and it's 30 11-12-19 9-1-20
Controls.
Insulate the Mill Side Hot Air
50 Entry Portion. 30 17-12-19 15-1-20
51 Installation of Mill Platform 15 17-12-19 31-12-19 20%
Installation of N2 Air Line
52 connection Piping 7 23-12-19 29-12-19

Check all equipment, box-up


53 the pulveriser and make ready 2 23-1-20 24-1-20
for operation.

54 All Miscallaneous Jobs. 15 31-12-19 14-1-20


No Load Trail Runs of All
55 Equepments 3 25-1-20 27-1-20