Project composition

Designation Name Page


Title
Cube apartments-С Contents of the volume. 1
Cube apartments-PZ Explanatory note
1.Organization construction 2
1.1. Preparatory work
1.2. Main construction period
2.Basic organizational and technological principles 4
of construction and installation work

3.Methods performing construction, installation and 8


special construction work
4.Execution works V conditions tropical 16

climate
5.Providing quality when performing work 17
6.Security environment 19
7.General requirements for 20
productionsanitation
8. Occupational safety during construction production 22
installation
work
9.Requirements fire safety 25
10. Geodetic support for construction 27
11. Environmental impact assessment 28
12. Determination of the duration of construction of the thirty
facility
13. List of requirements for basic construction machinery, 32
mechanisms and equipment
14. Calculation of the need for energy resources 33
15. Determination of labor requirements 37
16. Need for temporary living quarters 37
17. Technical and economic indicators 38
Blueprints
Cube apartments Stroygenplan of the underground part 39
Stroygenplan. Option 1 40
Stroygenplan. Option 2 41
Stroygenplan. Option 3 42
Section to version 3 43
Explanatory note.
1. Organization of construction
Construction is expected to be carried out by contract.
The contractor will be determined during the tender.
Work at the site is expected to be carried out in two periods - preparatory and main.
Supply of construction materials and structures to the site
supposedcentralized (motor transport).
Centralized preparation of concrete and mortar, delivery to
an objectprovided by special vehicles.
Construction is expected to be carried out using the in-line method.
The construction organization project adopted one and a half shifts
executionconstruction and installation work
from 8-00 to 21-00 in compliance with the requirements of the standard
“Labor safety”, ensuring the completion of construction within the specified time frame.
When performing construction and installation works (especially at night), it is necessary to
control the noise level from construction machines and mechanisms in accordance with the
requirements of the standard
“Protection from noise” and the standard “Ensuring the sanitary and epidemic well-being of the
population”, etc.
All construction work must be carried out in accordance with the work execution project
(WPP), developed by the organizations performing these works (or, upon their order, by other
specialized enterprises that have appropriate certified specialists) on the basis of this PIC.
Agreed:

1.1 Preparatory work.


Preparatory work, including the removal of utility networks and the removal of green spaces,
can be carried out on the basis of a registered declaration of the commencement of construction
work or a permit for construction work.
Deputy inv.

On-site preparatory work includes:


- construction site fencing;
No.

- installation of gates and installation of entrances;


Signature and

- arrangement of household premises and security;

CUBE Apartments-PZ
date

Change Number of Arc. No. date StageLeafSheets


Doc.Signature
GAP
P136
Explanatory note
Inv. No. orig.

GIP
01.24 ARHI-LUDY
Developed by
NedoboyChecked
- laying and connecting to the power supply network with installation of a metering unit;
- arrangement of temporary passages;
- arrangement of a station for washing wheels (if necessary);
- arrangement of areas for storing structures;
- arrangement of a temporary lighting network;
- installation of fire protection posts;
- installation of an information board with a passport of the object (if necessary);
- removal of green spaces in accordance with the act;
- dismantling the remains of buildings and structures;
- strengthening existing fences using a spacer system of metal profiles.
Before the start of the main construction and installation work at the site, it is necessary to
carry out preparatory work in accordance with the standard for "Organization of construction
production", namely:
• arrange temporary fencing of the construction site in accordance with the regulations
“Fencing inventory construction sites and areas for construction and installation work” and
installing gates for the entry (exit) of vehicles. Signal painting of fences must be carried out in
accordance with the standard “Fire protection. Safety signs";
• construct temporary roads, driveways and storage areas from 200mm thick limestone or
PD-1 type road slabs. The width of passages is 6.0 m for two-way traffic and 3.5 m for one-way
traffic. When laying out temporary roads, the following conditions must be met:
- the distance between the road and the storage area is at least 1.5 m;
- the distance between the road and the fence enclosing the site is no more than 1 m;
- the distance between the road and the edge of the trench is 1-1.5 m.
• at the exit, install a Karcher circulation high-pressure washer for washing vehicle wheels;
• To provide the construction site with electricity, electrical cables with a voltage of 0.4 kV
are laid according to a temporary scheme. Connect the construction site according to a permanent
Deputy inv.

scheme in accordance with the technical specifications with the installation of a 0.4 kW VRP with
No.

a metering unit and distribution cabinets at the construction site. The work is carried out in
accordance with a separate temporary power supply project;
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


2
ge Doc.
• The laying of a temporary power supply network is expected to be carried out in an open
way along the fence and lighting masts;
• The construction site is provided with water for production needs from tanks installed
before the start of work. Water is supplied by vehicles in tanks;
• arrange temporary container-type sanitary facilities in accordance with the requirements of
the “Mobile Buildings (Inventory)” standard. General technical conditions";
• install temporary bathrooms (dry toilet) to provide sanitary and domestic needs;
• arrange container-type warehouses and an open area for storing materials and tools;
• arrange fire-fighting stations in accordance with the requirements of the standard
“Fire safety rules (installation location is indicated on construction plans);
• install an information stand with a passport of the object (if necessary).
The completion of off-site and on-site preparatory work to the extent that ensures the
construction of the facility must be confirmed by an act in accordance with the requirements of
the “Organization of Construction Production” standard.
Preparatory work is technologically connected with the general flow of the main construction
and installation work of the facility, provides the necessary scope of work for construction
departments, their connections in the construction flow, ensures the use of the most advanced
methods of performing work: flow, technologically possible combination of individual types of
work, comprehensive mechanization of work
1.2. Main construction period:
During the main construction period, the main construction and installation work is carried out
in the following technological sequence:
1. Construction of the underground part of the building:
- digging a pit with vertical walls alternately along the building blocks to elevation. bottom
of grillages;
- installation of reinforced concrete grillages;
Deputy inv.

- construction of underground walls;


No.

- waterproofing device (if necessary);


- backfilling of grillage cavities and underground parts.
Signature and date

2. Construction of the above-ground part of the building.


Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


3
ge Doc.
- installation of vertical and horizontal monolithic reinforced concrete elements of the
above-ground part;
- roof installation;
- installation of elements for filling door and window openings;
- finishing of building facades;
- interior finishing device;
- installation and commissioning of internal engineering systems and elevator equipment.
3. Construction of pool structures.
4. Improvement and landscaping of the territory.
5. Installation and commissioning of technological equipment.

2. Basic organizational and technological principles of construction and


installation work
2.1. Excavation
Considering that the soils are represented by rocks (limestone), soil development is expected in
several stages:
- destruction of rock masses;
- grinding large pieces of rock to the required fraction;
- loading onto vehicles.
Destruction and crushing of rock (limestone) is supposed to be done using an excavator
equipped with a hydraulic hammer or a bulldozer-ripper with specialized attachments.
After crushing the excavation soil for monolithic reinforced concrete grillages, strip
foundations, it is recommended to carry out to the bottom of the structure using Hitachi ZX250
type excavators equipped with a backhoe with a bucket with a capacity of 0.8 cubic meters. and
1.0 cubic meters (with appropriate justification in the PPR, it is permissible to use other types of
excavators, buckets of other capacities), in hard-to-reach places, compressed conditions -
Deputy inv.

manually, with loading soil onto dump trucks, the load capacity of which should be justified in the
corresponding PPR (or technical map ) and removal to a temporary dump. Refinement of the
No.

bottom of the pits to the design level should be carried out manually (5-10 cm) immediately
Signature and date

before the concrete preparation device.


The soil that is removed from the pits during excavation is supposed to be transported to a
specialized landfill outside the construction site.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


4
ge Doc.
Backfilling of the pit sinuses is carried out using JCB 3CX type backhoe loaders equipped with
bulldozer equipment and manually with thorough layer-by-layer compaction of the soil using
pneumatic or electric rammers type TR-1 or IZ-4501.
The steepness of the slopes of pits and trenches should be taken in accordance with the labor
safety standards.
Construction drainage
Due to climatic conditions, it is planned to install an external rainwater drainage system by the
beginning of the rainy season. Atmospheric water is drained by installing an open drainage
system. Open drainage is carried out by installing channels along the contour of the bottom of the
pit with a slope that ensures water drainage along the contours of the construction site or water
intake sumps, followed by the installation of pumps of the required power to pump out the water.
To carry out drainage, it is necessary to construct ditches with a slope of 0.003 towards water
collectors, draining water, mainly along the perimeter of the pit, with rainwater drainage into
receiving wells (water collectors, sumps) made of steel pipes Ø1220x10mm with a height of 1.5-
2, pumping using a pump outside construction site to places agreed upon by the customer and the
sanitary and epidemiological station.
The construction of drainage wells must precede the excavation of pit sections by at least 0.7-
1.0 m, and soil excavation must be carried out from the well with the necessary slope for water
drainage. The network of drains, sumps and catch basins must be placed so as not to create
limited conditions for the operation of earthmoving and other construction equipment and
vehicles, and not to interfere with construction.
If necessary, the pumping of surface and groundwater from pits should be divided into
technological sections in the plan. Water is pumped out using self-priming centrifugal devices of
the GNOM-10-10 type with a capacity of up to 10 m3/hour. engine power 4 kW and using electric
or motor pumps with a capacity of 80 m3/h.
The procedure and methods for performing excavation work are established by the PPR, which
Deputy inv.

addresses the issues of the most advantageous distribution of earth masses on the construction
No.

site, the appropriate sequence of excavation work in individual areas and the use of water
reduction methods.
Signature and date

2.2. Construction of structures below level 0.000


The construction of monolithic reinforced concrete foundation structures is carried out using
truck-mounted cranes of the XCMG QY25 K5 type with a 38.5 m boom or a crane on
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


5
ge Doc.
pneumatic wheels type Liebherr LTM 1045 and partially tower cranes installed according to the
construction schedule.
Direction of operation of self-propelled cranes within the designated grips with a “toward”
exit.
Simultaneously with the construction of the foundations of the building blocks, the foundations
for the tower cranes are being built.
It is advisable to install tower cranes before the start of monolithic work on the underground
part of the building.
For the access of vehicles and the movement of cranes, temporary roads, driveways and
storage areas are constructed from prefabricated reinforced concrete road slabs PD1 or filled with
limestone 20 cm thick.
Storage areas are located in the crane operating area.
The supply of concrete for foundation slabs and grillages is carried out using a Ford Trucks
3542M BST 37 type concrete pump and a crane in buckets with a volume of 0.8-1.0 m3.
The concrete mixture is compacted using deep vibrators.
After completing the work on laying the foundations and removing the formwork,
waterproofing is expected.
The procedure and methods for performing excavation work are established by the PPR, which
resolves the issues of the most advantageous distribution of earth masses at the construction site
and the appropriate sequence of excavation work in individual areas.
All excavation work must be carried out in accordance with standard requirements
“Carrying out excavation work and laying foundations and building foundations.”
2.3. Construction of structures of the above-ground part of the building
The following are accepted as the main installation mechanisms for the period of installation of
monolithic reinforced concrete structures:
Option 1.
Deputy inv.

- tower crane No. 1 type Comansa 10 LC 90, (or with similar characteristics) with a boom of
No.

40.0 m, lifting capacity of 3.0-6.0 t;


- tower crane No. 2 type Comansa 10 LC 90 (or with similar characteristics) with a boom of
Signature and date

50.0 m, lifting capacity of 1.6-6.0 tons.


Option 2.
- tower crane No. 1 type Zoomlion 7025, Comansa 11 LC 160, SYM K30/30 (or with similar
characteristics) with a boom of 55.0 m, lifting capacity of 2.5-12.0 t;
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


6
ge Doc.
- tower crane No. 2 type Potain MC 205B-2C, Potain MC 175B, Comansa 11LC160,
Comansa 16LC185 (or similar characteristics) with a boom of 65.0 m, a lifting capacity of 2.5-
10.0 tons.
Option 3.
- tower crane No. 1 Potain_GTMR 336B_1, Potain_Eurogru E42.10, Liebherr 63K (or with
similar characteristics) with a boom of 40.0 m, lifting capacity of 1.0-4.0 t;
- tower crane No. 2 type Potain_GTMR 336B_1, Potain_Eurogru E42.10, Liebherr 63K (or
with similar characteristics) with a boom of 40.0 m, a lifting capacity of 1.0-4.0 t.
Tower cranes are installed on separate monolithic reinforced concrete foundations.
The installation and operation of tower cranes is carried out based on the work execution plan
with the development of measures for their safe simultaneous operation.
The area of foundations and moving parts of tower cranes is fenced with an inventory fence so
that there is a distance of at least 1.0 m between the fence and the moving parts.
Crane areas, installation areas, areas for storing materials and structures should be fenced off
with an inventory fence 1.2 m high and safety signs should be installed.
The construction of monolithic structures of the underground and above-ground parts of the
building should be carried out in accordance with the PPR developed by a specialized
organization.
The construction of the structures of the above-ground part of the building should be carried
out sequentially by floors.
Tower cranes are provided to carry out work on installing formwork and supplying
reinforcement and materials to installation levels.
Restricted areas for tower crane operation on a construction site are indicated by red lights at
night and red flags during the day.
Ready-mixed concrete for monolithic structures is supposed to be produced at specialized
enterprises and delivered to the construction site centrally by concrete trucks directly to the
Deputy inv.

structure into which the concrete mixture will be placed either to a concrete pump or an inventory
No.

can and crane.


When constructing monolithic structures, reinforcement and other materials are supplied by
Signature and date

lifting cranes; concreting can be carried out using a concrete pump truck or tower cranes in
buckets with a volume of 0.5-1.0 m3.
The production of reinforcement spatial and flat frames should be carried out on racks in
prefabricated jigs.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


7
ge Doc.
Folding of oversized structures for installation is carried out in the crane operating area.
All construction work must be carried out in accordance with the work execution project
(WPP), or technological maps developed by organizations performing these works (or, upon their
order, by other specialized enterprises that have appropriate certified specialists) on the basis of
this PIC.
All teams, units and individual workers working at the site must receive the necessary sets of
tools and equipment to perform the relevant types of production processes. Lifting mechanisms
must be equipped with rigging equipment.
In addition to high-quality tools, construction must be provided with the necessary amount of
small-scale mechanization equipment - vibrators, mechanisms for supplying concrete mixture,
rigging devices, inventory metal and wooden scaffolding, formwork for concrete work, etc.
Work related to the construction of the designed facility must be carried out in accordance with
the requirements of the standards “Concrete and reinforced concrete structures”,
"Steel structures. Standards for design, manufacture and installation”, “Guidelines for the
performance of work during the manufacture and installation of building structures”, as well as in
accordance with the instructions given in the drawings of the design documentation.

3. Methods for performing construction, installation and special construction work.


3.1. Excavation
Excavation work must be carried out in accordance with the standard
“Carrying out excavation work and laying foundations and constructing foundations.”
The procedure and methods for performing excavation work are established by the PVR, which
resolves the issues of the most advantageous distribution of earth masses at the construction site
and the appropriate sequence of excavation work in individual areas.
Backfilling of pits and trenches is carried out in horizontal layers 0.15-0.2 m thick when
compacting the soil with pneumatic compactors and 0.6-0.8 m when compacting the soil with
Deputy inv.

heavy slabs.
No.

Backfilling of sinuses is carried out using a JCB 3CX, Hitachi ZX250 excavator (or with
similar characteristics) with bulldozer equipment and manually
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


8
ge Doc.
with layer-by-layer compaction using pneumatic or electric rammers TR-1 or IZ-4501 (or similar
characteristics).
Digging in places where live electrical cables are located is carried out in the presence of a
representative of the organization operating this cable network.
Soil development near existing utilities must be done manually.
All excavation work must be carried out in accordance with standard requirements
“Carrying out excavation work and laying foundations and building foundations.”
3.2. Construction of monolithic structures.
When performing concrete and reinforced concrete work, it is necessary to be guided by the
standard “Performance of work in the manufacture and installation of building structures” and
passports for universal formwork.
Ready-mixed concrete for monolithic structures is supposed to be produced at specialized
enterprises and delivered to the construction site centrally by concrete trucks. When justified in
the PPR, it is assumed that a mobile concrete unit of the required capacity (8-10m3/hour) will be
installed.
Laying of the concrete mixture into the formwork must be carried out uninterruptedly, in layers
500 mm high with thorough compaction using surface and deep electric vibrators of the type S -
802, S - 414, IS - 67.
To ensure solidity, breaks between laying adjacent layers of concrete should not exceed one to
one and a half hours. Concreting of a concrete floor slab must be carried out without interruption,
using grips.
Continuity of laying the concrete mixture is ensured if the next layer is laid before the cement
of the previous layer begins to set.
Leveling and smoothing the concrete surface when installing a concrete floor is assumed to be
a vibrating screed.
It is allowed to disassemble the floor formwork no earlier than the concrete reaches 75% of its
Deputy inv.

design strength.
No.

When developing a work project, determine and agree with the Chief Designer the location of
working (cold) concreting joints.
Signature and date

Working joints are made when laying the concrete mixture at the site of a technological break
in concreting during the execution of work.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


9
ge Doc.
The surface of the working joints made when laying the concrete mixture intermittently must
be perpendicular to the axis of the concrete columns and beams, the surface of the slabs and walls.
Concreting can be restored once the concrete reaches a strength of at least 1.5 MPa.
Working joints, in agreement with the design organization, may be installed during concreting:
- columns - at the level of the top of the foundation, the bottom of the purlins, beams and
crane consoles, the top of the crane beams, the bottom of the column capitals;
- flat slabs - anywhere parallel to the smaller side of the slab.
If necessary, for waterproofing cold concreting joints, the working documentation should
include the installation of waterstops.
Formwork, reinforcement and concrete work must be carried out in accordance with the
standard “Concrete and reinforced concrete structures” and passports for universal formwork, as
well as in accordance with the instructions given in the design documentation drawings.
The sequence, technology and methods of performing work must be reflected in the work
project.
3.3. Construction of enclosing structures and facades.
3.3.1. Masonry work
Work on the construction of stone structures must be carried out according to the design,
taking into account tolerances for vertical deviations.
It is not allowed to weaken stone structures through holes, grooves, niches, or mounting holes
not provided for in the design.
In case of forced ruptures of the masonry, it is necessary to carry out in the form of an inclined
or vertical cut.
The difference in heights of masonry being built in adjacent areas and when laying junctions of
external and internal walls should not exceed the height of the floor. Installation of fastenings in
places where reinforced concrete structures adjoin masonry should be carried out in accordance
with the design.
Deputy inv.

The verticality of the surfaces and corners of stone masonry, the horizontality of its rows must
No.

be checked as the masonry progresses (every 0.5–0.6 m) with the elimination of any detected
deviations within the tier.
Signature and date

After finishing the laying of the floor, an instrumental check of the horizontality and marks of
the top of the masonry should be carried out, regardless of intermediate checks of the
horizontalness of its rows.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


10
ge Doc.
The mortar prepared for masonry must provide the stone structures with the design strength.
Stone work should be carried out in strict accordance with the standard for “Stone and
reinforced masonry structures”.
Laying of internal walls and partitions made of bricks begins with the construction of corner
and intermediate beacons. Then a mooring cord is attached to the corner and intermediate
beacons.
After tensioning the mooring, the following operations are performed:
- they spread the mortar and lay the walls;
- The bricks are delivered using mini-loaders to the masons' workplaces and manually fed
to the installation horizon.
According to the height of the floor, each wall or partition is divided into three tiers:
- The first tier, 120 cm high, is laid out by the mason while standing on the ceiling;
- For laying the second and third tiers, inventory scaffolding is collected, on which masons'
jobs are organized.
The mason's workplace includes a working area and a materials placement area. The supply of
bricks at the workplace when laying floors (scaffolds) is taken based on a two-hour requirement.
During the masonry process, the supply of masonry materials is replenished.
During the work, the mason monitors the correct dressing and filling of masonry joints with
mortar, the verticality and straightness of surfaces and corners.
The installation of brickwork for the enclosing structures of the house is carried out from the
floor level and using inventory platforms.
The supply of bricks and aerated blocks to the construction site is carried out by vehicles on
pallets or in bags. The supply of bricks, mortar and insulation to workplaces is carried out by an
installation crane to the floor level using remote loading and receiving platforms.
Loading and receiving platforms are installed and secured in accordance with the requirements
of the passport after the concrete floor has reached 100% strength.
Deputy inv.

The movement of materials within the floor is carried out by inventory freight
No.

"rockles".
3.3.2. Installation of facade systems
Signature and date

Work on the installation of enclosing finishing structures of facades is carried out using
hanging cradles and scaffolding.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


ele
ge Doc. ven
The supply of metal-plastic structures for filling openings to workplaces is carried out using a
tower crane to remote platforms. Delivery to workplaces is carried out manually.
Work on the installation of cladding with ceramic tiles and porcelain stoneware materials on
the 1st and ground floors is carried out from platforms or scaffolding according to the technology
adopted in the project.
The construction of facade enclosing structures should be carried out after the installation of
brickwork, installation of window blocks and stained glass according to the project.
The installation of enclosing structures of facades and their finishing should be carried out in
accordance with the developed work execution project (WPP), the requirements of the standard
“Carrying out work on the installation of insulating, finishing, protective coatings of walls, floors
and roofs of buildings and structures.”
3.3.3. Interior finishing work
Finishing work must be carried out under conditions that exclude the possibility of damage to
the finished finish and glazing, as well as contamination of the finish by further work.
Interior finishing work must be carried out only after installing the roof of the building above
the premises, installing door and window frames, installing electrical wiring, internal water
supply and sewerage systems.
By the start of finishing work at the site, the following work must be completed:
- sealing areas around window and door blocks, as well as installing a window sill;
- preparation device for clean floors;
- installation of waterproofing of ceilings and floor screeds in bathrooms, installation of
plumbing faience products;
- laying all internal communications and sealing them;
- installation of power supply, telephone, radio and television networks.
Finishing work must begin from the top floor.
For finishing work, use electric spray guns, spray guns, etc.
Deputy inv.

Finishing work inside the premises should be carried out from the inventory of lightweight
No.

metal prefabricated scaffolding.


The painting solution is prepared in centralized color workshops and delivered to the site in
Signature and date

finished form.
Staircases are used to lift workers to floors.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


12
ge Doc.
3.4. Electrical and plumbing work.
Electrical and plumbing work is carried out in two stages:
- laying wires and cables, installing pipelines and ventilation ducts - for finishing work;
- installation of plumbing fixtures and fittings, installation of lighting fixtures, electrical
appliances - after finishing work.
Plumbing and technological equipment are supplied by taps and small-scale mechanization.
3.5. Installation of technological equipment
For installation of process equipment, it is recommended to use lifting and transport vehicles
involved in construction and installation work (see graphic part of the FOB).
Foundations for equipment must be accepted by an act signed by representatives of the
construction and installation organizations and the technical supervision of the customer.
Before installing the equipment, the premises must be prepared as follows:
- “black” floors are made;
- the first painting and glazing have been completed (if any);
- Construction waste has been removed from the premises;
- If necessary, installation openings are provided.
Installation of process equipment should be carried out using the connected method in
accordance with the Work Performance Project (WPP) developed by the contractor, for which the
delivery time for the largest equipment should be agreed with the Customer. The equipment uses
the mounting openings specified in the relevant sections of the project.
The developed Work Project must also provide for the combination of construction,
installation, and special work.
Lifting of equipment (brackets, guides, etc.) for the installation of elevators is carried out
manually from installation platforms located in the elevator shaft at the floor level. To construct
the platforms, beams made of rolled metal are used, on which wooden panels are laid.
To install heavy equipment (winches, engines), winches are used that are installed on top of the
Deputy inv.

elevator shaft on metal beams.


No.
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


13
ge Doc.
Installation and acceptance of elevator equipment should be carried out in accordance with the
regulations
“Rules for the design and safe operation of elevators” and installation instructions from the
manufacturer.
The developed Work Project must also provide for the combination of construction,
installation, and special work.
3.6. Laying utility networks
Work in the security zones of transit utility networks must be carried out manually according
to a permit in the presence of the responsible contractor and in agreement with the owner of the
network.
The installation of the designed utility networks is provided by the flow method, divided into
sections (sections), the final volume of which is determined by the temporary installation works
and provides for the laying of cable lines for power supply, telephone systems, installation of
household sewerage, rainwater drainage, and water supply in accordance with the master plan.
utility networks
The design of external power supply and communication networks will be installed in the ground
- in trenches with vertical walls without fastenings at a laying depth of up to 1 m from the ground
surface.
Before laying pipelines, the route is laid out:
- the axis of the designed pipeline is drawn from the design into reality;
- fixing signs on the ground at the places where the route turns;
- placement of chambers and wells.
Before breaking trenches, all underground communications that fall into the excavation zone or
are close to the excavation site must be opened (control trenching). Open the communications
manually using paddles, without the use of impact tools. A representative of the organization
operating this underground communication must be present during the opening.
Deputy inv.

The entire length of the route must be fenced on both sides with inventory boards with warning
and safety signs posted on them. In areas of heavy traffic and pedestrian traffic, red lights are
No.

placed on the fence. The fence must be at least 1.2 m in height, solid, painted, with a sign showing
Signature and date

the name of the organization performing the work. To cross the trench, pedestrian bridges with a
width of at least 0.6 m with double-sided railings 1 m high are arranged.
The laying of networks is planned to be carried out in an open way in trenches with slopes
using a JCB 3CX excavator equipped with a backhoe with a bucket with a capacity of 0.5 m3.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


14
ge Doc.
In areas of intersection with existing communications, with parallel laying, when the existing
networks fall into the slope prism, as well as to preserve the concrete surface and green spaces,
trenches are made with vertical walls in wooden fastenings.
Open underground communications crossing the trench must be suspended from a crossbar
thrown over the trench, and, if necessary, also protected by a wooden box.
Installation of pipelines, chamber elements and wells is carried out using KTA-18 truck cranes.
Electric welding of steel pipeline joints is carried out using welding units
STSH-500.
Backfilling of trenches is carried out using a JCB 3CX excavator with a mounted blade (with
preliminary backfilling of the pipelines manually).
Connection to street networks is made in an open way in a wooden frame. Preferably on
weekends and at night.
When performing work in the dark, all workplaces must be illuminated.
Pipeline testing is carried out by workers who have undergone special training and are
authorized to perform this type of work.
The laying and connection of electrical cables, underground pipelines of utility networks
(water supply, sewerage, drainage, telephone sewerage, gas supply) along and under the roadway
of the streets should be carried out in accordance with the relevant parts of the project in
accordance with the agreement with the road service.
Detailed development of work methods for the installation and connection of the designed
networks to street (backbone) networks in the conditions of existing buildings is carried out in the
work execution project (WPP).
3.7. Territory arrangement
When constructing the surface of sites and driveways, it is planned to use a JCB 3CX backhoe
loader with a bucket capacity of 0.5 m3 and a Bomag type self-propelled roller to level the
crushed stone and construct a trough.
Deputy inv.

Taking into account the conditions of the construction site, laying asphalt concrete is carried
No.

out manually and using small-scale mechanization. Asphalt concrete is compacted using self-
propelled rollers - 12 tons.
Signature and date

Paving with figured concrete elements (FEM) is done using small-scale mechanization and
manually.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


15
ge Doc.
4. Performing work in tropical climates
When performing work in a tropical climate, it is necessary to take additional measures to
perform the work and prepare mixtures and solutions, namely:
- the use of plasticizers and additives for concrete and mortars;
- use chilled aggregates to prepare the concrete mixture;
- reduce the time of delivery of concrete mixture and laying in formwork;
- transportation of concrete mixture in closed containers;
- cover freshly laid concrete with waterproof films.
The formwork should not have the slightest cracks to prevent loss of cement laitance and
moisture. Before laying the concrete mixture, the formwork is moistened. The shape of the
surface of the formwork made of moisture-absorbing materials (wood, plywood) should be
covered with special compounds or polymer films that prevent adhesion to concrete, as well as the
absorption of water from it.
The concrete mixture should be supplied and distributed using methods that prevent its
repeated overloading or rapid dewatering. It is not recommended to feed the mixture from open
conveyors, as well as on long trays. It is most advisable to supply the mixture with concrete
pumps or in large-capacity buckets using cranes. The free fall of the mixture should not exceed
1.5...2 m.
During the initial period of maintenance, concrete must be protected from dehydration, for
which open surfaces are covered with burlap, matting, and tarpaulin; After laying, the concrete is
systematically moistened every 3…4 hours.
The temperature of the concrete mixture when concreting structures with a surface modulus of
more than 3 should not exceed (30 - 35) °C, and for massive structures with a surface modulus of
less than 3 - 20 °C.
If shrinkage cracks appear on the surface of the laid concrete due to plastic shrinkage, repeated
vibration is not allowed.
Deputy inv.

Maintenance of freshly fallen concrete should begin immediately after placing the concrete
No.

mixture and continue until, as a rule, 70% of the design strength is achieved.
During the initial maintenance period, freshly poured concrete mixture must be protected from
Signature and date

dehydration.
There are several ways to protect concrete from drying shrinkage:
- spraying water on the surface of concrete;
- protection of concrete with burlap, which needs to be watered;
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


16
ge Doc.
- watering foundation structures.
Caring for concrete should consist of ensuring a moist surface condition by installing a
moisture-containing coating or continuously spraying moisture over the surface of structures. At
the same time, periodic watering of open surfaces of hardening concrete and reinforced concrete
structures with water is not allowed.
To avoid the possible occurrence of a thermally stressed state in monolithic structures when
directly exposed to sunlight, freshly laid concrete should be protected with self-destructive
polymer foams, inventory thermal insulation coatings, polymer film with a reflectance of more
than 50%, etc.

5. Quality assurance during work execution


Construction contractors must develop a quality manual and quality control program (“Quality
Supervision Plans”) for the work performed.
The quality manual must contain the quality management system established and implemented
in the Contractor's organization in accordance with the requirements of the ISO standard.
The acceptance of critical structures and the preparation of inspection reports for hidden work
should be completed in the manner and to the extent prescribed by the “Construction
Organization” standard. The list of hidden works and critical structures is indicated in the working
documentation.
Quality control programs should include incoming quality control of materials arriving at the
site, structures, parts, and electrodes.
The composition of the incoming inspection program is regulated by the standard, and the list
of items subject to incoming inspection must be agreed upon with the Customer and included in
the incoming inspection program;
– operational control of individual construction processes of production operations. The
composition and content of operational control maps are regulated by local standards and must be
Deputy inv.

developed as part of technological maps and work projects.


No.

- intermediate acceptance control of completed hidden work, stages of work, critical


structures of their parts in accordance with the list established in the project;
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


17
ge Doc.
- inspection control of execution technology, quality of work, design verification of the
work of the Contractor's control services. The subject and schedule of inspections are established
in the developing quality control program by the Contractor.
Based on the results of incoming quality control, conclusions must be drawn up and recorded
in the journal for recording the results of incoming control.
Records based on the results of operational, acceptance and inspection quality control of
construction and installation works must be entered into a general or special work log with a
separate report attached.
After the installation of the ceiling of each floor, an instrumental check of the installation
horizon with a level and selective laboratory quality control of the mortar and concrete are carried
out in accordance with the design grade.
Concrete quality control should be carried out in accordance with the standards "Building
materials. Heavy concrete. Technical conditions" and "Building materials. Concrete. Rules for
strength control."
resultsquality control of work must be recorded in the work log. Hidden work is subject to
inspection and reports are drawn up. In all cases, it is prohibited to carry out subsequent work in
the absence of inspection reports and the closure of previous hidden work. The types of work and
structures for which acts of closure of hidden work must be drawn up are determined taking into
account the instructions of the standard “Organization of construction production” and the
instructions of the detailed design. When performing work on the construction of this facility, it is
necessary to inspect the following types of work:
- earthworks: marks of pits, trenches;
- monolithic concrete and reinforced concrete structures: formwork assembled and
prepared for concreting; compliance of reinforcement and embedded parts with the working
drawing; selection of control concrete samples;
- stone work: masonry reinforcement; installation of jumpers;
Deputy inv.

- metal structures: acceptance of areas for supporting steel structures on supports, anti-
No.

corrosion coating of structures;


- floors: checking the completion of structural elements of floors before installing the next
Signature and date

layers; waterproofing bathroom floors;


- roof: checking the completion of structural elements before installing the next layers;
- sanitary work: readiness of niches, furrows and channels for laying pipelines in them and
installation of sanitary fixtures.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


18
ge Doc.
The connection of structures and reinforcement by welding is checked by ultrasound.
All load-bearing and enclosing structures of buildings, as well as underground utilities, are
subject to geodetic inspection during the installation process. Methods of geodetic control are
selected when developing a project for the production of geodetic work (PGW), taking into
account the building structures adopted in the project, technology for performing work, and
geological conditions.

6. Environmental protection.
In order to protect the natural environment, during the work it is necessary to take measures to
preserve the plant layer of soil and preserve green spaces.
When removing, storing and storing the plant layer of soil, measures must be taken to prevent
deterioration of its quality (mixing with the underlying soil layer, rocks, polluting liquids and
materials, etc.).
In the summer, water the construction site area systematically, at least once or twice a shift.
When carrying out dismantling work, the requirements for preventing dust and gas
contamination in the air must be met.
It is necessary to install garbage chests for household waste and clean them in a timely manner
in the prescribed manner.
The collection of construction waste must be arranged in designated areas. It is strictly
prohibited to bury waste; it must be regularly removed to designated areas or a landfill.
The construction site must be promptly cleared of debris and dirt.
Temporary excavations, drainage ditches and other similar structures must be made in such a
way as to prevent soil erosion, erosion of slopes, and the formation of ravines. In temporary
reserves and dumps, leaching of both plant and mineral soil must be prevented.
Washing, refueling and maintenance of construction equipment must be carried out at specially
equipped sites, where it is necessary to provide a set of measures to prevent the ingress of
Deputy inv.

contaminated water, fuel residues, etc. into groundwater, natural bodies of water and the location
No.

of existing green spaces. When carrying out work, it is necessary to take measures to
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


19
ge Doc.
preventing unorganized drainage of water from the construction site. Do not pollute the
environment, do not allow open fires.
The construction site is illuminated using floodlights located at a height of at least 6.0 m on
metal mobile inventory supports. The beams of the spotlights are directed directly at the work site,
excluding light rays from entering the houses being used.

7. General requirements for labor protection and industrial sanitation.


The composition and content of decisions on labor protection, industrial sanitation and safety
measures must comply with the requirements of the standards for “Occupational Health and
Industrial Safety in Construction”, “Occupational Health and Safety Rules for the Operation of
Lifting Cranes, Lifting Devices and Related Equipment”, as well as safety regulations, approved
by state supervisory authorities and relevant ministries and departments.
At the construction site, hazardous areas must be designated near places where goods are
moved by lifting and transport equipment, near a house or structure under construction, as well as
overhead power lines.
Dangerous borderszones are established in accordance with the requirements of the standard
Labor protection and industrial safety in construction.
The construction master plan indicates the locations of sanitary facilities, automobile and
pedestrian routes, which were determined taking into account hazardous areas, the placement of
lighting sources and the fencing of the construction site.Sanitary facilities must be located in non-
hazardous areas
located in relation to objects that emit dust, harmful vapors and gas (bunkers, concrete and mortar
units, etc.) on the windward side of the prevailing
directions.
Temporary vehicular and pedestrian routes should be located outside hazardous areas. In the
case where roadways are located in the area where cargo is moved by crane, it is necessary to
Deputy inv.

provide a signal fence, warning signs and road signs about entering the dangerous zone.
No.

Car routes should be designed as circular routes; if necessary, it is necessary to provide areas
for turning cars. The radius of curvature of temporary tracks is taken to be at least 12.0 m, the
Signature and date

width of the roadway is at least 3.5 m at


Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


20
ge Doc.
movement of vehicles in one direction and 6.0 m when moving in two directions.
Lighting of construction sites and areas must be carried out in accordance with the
requirements of the Standards for Lighting Construction Sites. Lighting should be provided for
work, security and emergency lighting.
When installing fencing for the construction site and work areas, take into account the
requirements of the standard “Fencing of inventory construction sites and construction and
installation work areas.”
The placement of construction machines should be determined in such a way as to provide
space sufficient for inspection of the work area and maneuvering while maintaining a safety
distance near an unsecured excavation, stacks of cargo, and equipment.
Workplaces must be placed on stable and strong structures, taking into account the location of
hazardous areas.
When organizing workplaces, the issues of providing collective protective equipment, rational
technological equipment, small-scale mechanization, power tools, and devices to ensure the safe
performance of work must be resolved.
For workplaces and passages to them at a height of 1.3 m or more and a distance of less than
2.0 m from the boundary of the difference in height, it is necessary to provide temporary fencing.
Protective barriers must meet the requirements of the standard.
The main requirements for fences when constructing a building superstructure are:
- possibility of repeated use;
- ease of installation and dismantling;
- reliability of the attachment point for the fence to the elements of building structures.
When concreting using a concrete pump, installation, dismantling and repair of concrete
pipelines, as well as removal of plugs from them, are carried out only after the pressure in the
pipeline and hydraulic system of the concrete pump has been relieved.
With a sharp increase in the injection pressure of the concrete mixture and reaching peak loads
Deputy inv.

up to 0.9 of the maximum pressure that is developed by the concrete pump, the concreting process
No.

is stopped and then restored at the minimum speed of supply of the concrete mixture. After the
injection process has stabilized, the feed rates are increased in accordance with the specified
Signature and date

concreting intensity.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


21
ge Doc.
When cleaning a concrete pipeline with compressed air, workers not engaged in these
operations should not be at a distance of less than 10 m from the concrete pump.

8. Labor protection during construction work.


8.1. Basic rules of labor protection
All work on dismantling structures and equipment must be carried out under the constant
supervision of the person responsible for the safe performance of work.
All workers involved in the demolition of buildings must be provided with
personal equipment, protective clothing and helmets and respiratory, eye and hand protection.
Zone,dangerous for people when dismantling and moving structures must be protected.
The limits of dangerous zones are determined by the distance from the horizontal projection of
the trajectory of the maximum dimensions of the cargo moved by machines or the distance from
the outer perimeter of the building.
Workplaces and passages to them at a height of 1.3 m or more at a distance of less than 2 m
from the height difference boundary must be protected by temporary fences with a height of at
least 1.1 m. If it is impossible to install these fences, all work at height must be carried out using
safety ropes and safety belts in accordance with the standard “Individual equipment for protection
against falls from a height. Restraint and restraint belts and restraint straps.”
It is prohibited for people to remain on elements and structures when lifting and moving them.
Slinging of elements and structures should be carried out using inventory slings, and, if
necessary, specially designed load-handling devices. Slinging schemes must be developed in the
work project.
Cylinders with compressed gases must be stored in special ventilated rooms, isolated from
open flame sources and welding areas.
It is prohibited to store lubricants, cylinders with oxygen, acetylene and other explosive and
flammable gases in the same room.
Deputy inv.

Cylinders should be stored vertically in the sockets of special racks.


No.

Empty cylinders must be stored separately from cylinders filled with gas.
Electric tools may only be used in accordance with the requirements specified in the
Signature and date

manufacturer's data sheet and instructions. During breaks in


Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


22
ge Doc.
During operation or when moving an electric tool to another place, it must be turned off. Do not
leave it unattended with the engine running or connected to the mains or compressed air network.
When using electric tools, do not pull or bend hoses or cables. Their intersection with cables,
electric cables and wires of electric welding units is also not allowed.
The handles of an electrified tool must be insulated with rubber or plastic, and the body must
be grounded when operating at voltages above 36 V (regardless of the current frequency).
When working with electrified tools, you need to use electric rubber gloves, mats, galoshes and
safety glasses.
Permission to work with pneumatic hand-held machines is issued by order of the organization.
Pneumatic machines are adjusted and mounted by specially designated and trained craftsmen.
Those working with pneumatic machines are provided with vibration-proof gloves and special
shoes.
8.2. Labor protection during construction and installation work
Earthen
The conditions that ensure the stability of the vertical walls of excavations without fastenings
are determined by the standard “Occupational Safety and Health in Construction”.
If they are exceeded, as well as in the presence of limited production conditions and soils
saturated with water, it is necessary to provide for fastenings. When constructing excavations with
a depth of 3 m or more, a fastening design must be developed in the PPR. When placing lifting
equipment and vehicles near an unsecured excavation, the safety distance specified in
standard “Occupational health and safety in construction”.
Reinforcement
During reinforcement work, the installed reinforcement elements must be secured; they are not
allowed to be left unsecured. Knitting or welding reinforcement while standing on tied or welded
clamps or rods is prohibited.
You cannot stand on reinforcement and formwork blocks until they are completely installed
Deputy inv.

and secured.
No.

Weldingdevices and units installed in an open area are protected from precipitation (with
canopies or tarpaulins) and mechanical damage.
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


23
ge Doc.
Carrying out electric welding work outdoors during rain and thunderstorms is prohibited.
Carrying out welding work at height from scaffolding, scaffolding and cradles is permitted
only after the work manager has checked the reliability of these devices, and measures have been
taken to prevent the flooring from catching fire and molten metal falling on people working
below.
Installation work
Installation work must be carried out under the supervision of the person responsible for the
safe performance of work, appointed by order for the construction organization from among the
engineering staff.
All workers involved in installation must wear safety helmets.
People are not allowed to be under the mounted structures until they are installed in the design
position and secured.
Loading and unloading operations should be carried out, as a rule, by mechanization.
Methods for slinging elements and structures must ensure their delivery to the installation site
in a position close to the design one.
All lifting mechanisms and rigging devices must be tested and marked.
When moving a structure, the installer must be outside the contour of the structure being
installed (outside the danger zone from the element being moved) on the side opposite to the
direction of supply by the crane.
Elements and structures installed in the design position must be securely fastened temporarily
or permanently so as to ensure their stability and geometric immutability.
Unslinging of structures installed in the design position should be done after alignment and
reliable permanent or temporary fastening.
Lubricants and other devices that ensure the safety of work must meet the requirements of
regulations on labor protection and fencing of work areas.
Electrical safety at the construction site, work sites and workplaces must be ensured in
Deputy inv.

accordance with the requirements of the electrical safety standard.


No.

Safety requirements for electric welding work must be ensured in accordance with the standard
“Occupational Safety Rules for Metal Welding”.
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


24
ge Doc.
Installation of long structures should be carried out using guy ropes to avoid impacts on the
mounted structures.
When working on installation sites, installers must use safety belts.
Roofing
Admission of workers to perform roofing work is permitted after inspection by the foreman or
foreman together with the foreman of the serviceability of the load-bearing structures of the roof
and fences.
It is necessary to climb onto the roof and descend from it only using flights of stairs and
stepladders equipped for climbing to the roof. The use of a fire escape for this purpose is
prohibited.
When performing work on flat roofs that do not have a permanent fence (parapet), workplaces
must be fenced.
When performing work on a roof with a slope of more than 20%, workers must use safety
belts.
Materials can be placed on the roof only in places provided by the temporary installation
works, and measures must be taken to prevent them from falling, in particular under the influence
of wind. The stock of materials should not exceed variable demand. During a break in work, tools,
technological devices, and materials must be secured or removed from the roof to prevent them
from falling from gusts of wind.
Not allowedperforming roofing work during ice, fog, excluding visibility within the work
front, thunderstorms and wind speeds of 10 m/s or more.

9. Fire safety requirements.


Fire safety at the construction site, work sites and workplaces must be ensured in accordance
with the requirements of the “Fire Safety of Construction Facilities”, “Fire Safety Rules”.
Electrical safety on a construction site must be ensured in accordance with the requirements
Deputy inv.

of the Electrical Safety standard.


No.

The order for the organization appoints those responsible for fire safety at the construction
site, areas responsible for the availability and proper maintenance of fire extinguishing equipment,
Signature and date

and the timely implementation of fire safety measures provided for by the project.
At the stage of preparatory work, an information board on fire safety measures is installed
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


25
ge Doc.
Responsibility for fire safety of household, auxiliary and utility premises lies with the
subordinate officials in which these premises are located.
Before the start of work, fire safety briefings and fire safety training must be carried out for
all workers and engineers in accordance with fire safety rules.
To ensure fire safety and prevent unauthorized persons from entering the construction site,
24-hour security is organized.
Boxes with sand, barrels of water and a fire shield with fire extinguishing equipment and a
sound signal (bell, siren) are installed on the construction site. Fire-fighting equipment is located
in the places specified during the development of the PPR.
Fire extinguishers are installed in all domestic premises.
Forhot work, it is necessary to provide the place for hot work with primary fire extinguishing
means (fire extinguisher, containers with sand and water, steel hook, felt);
The hot work site is cleared of flammable materials, welding units, gas cylinders, and
containers with flammable liquids within a radius of 5 m.
It is prohibited to light an open fire, smoke or light matches within 10m of oxygen and
acetylene cylinders.
In the event of a fire in an energized mechanism or lifting machine, the driver must jump to the
ground with his legs together and without touching the machine with his hands, walk away from it
at a distance of at least 8 m, moving his feet along the ground and without lifting them from each
other.
On the construction site it is prohibited:
- make a fire;
- Smoking in areas where flammable liquids, synthetic resins and other materials are stored
and used. (Smoking is permitted only in specially designated areas equipped with fire
extinguishing equipment, bins, a box of sand and a barrel of water. The smoking area must be
marked “Smoking area”);
Deputy inv.

- store flammable and flammable liquids in open containers, pour water over them;
No.

- use flammable and combustible liquids for degreasing building structures and equipment;
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


26
ge Doc.
- block passages, entrances and exits, as well as approaches to the fire shield, equipment
and communications. All entrances and roads must be maintained in proper condition and free for
travel and access to them, and illuminated at night;
- combine welding work with work involving the use of flammable and combustible
liquids.

10. Geodetic support for construction.


A geodetic alignment basis for construction must be created by the customer no less than 10
days before the start of construction and installation work in the form of a network of geodetic
points fixed with signs, which will ensure the implementation of further constructions and
measurements with the required accuracy. For the stability of the leveling network signs at the
construction site, temporary benchmarks in the amount of at least 3 pieces with an accuracy of 2
m are laid, the locations and method of fastening of which must be indicated in the work plan.
Geodetic alignment work in construction is carried out by a construction organization from the
points of the geodetic alignment base to determine the planned and altitude position of individual
elements and structures of buildings and structures. All load-bearing and enclosing structures of
buildings, as well as underground and above-ground utility lines, are subject to geodetic
inspection during the installation process.
For laying rappers and signs, it is necessary to provide free spaces with the expectation of
ensuring the mutual alignment of all points in the plan, in height and line of sight between
neighboring points, as well as the required height of the sighting beam above the ground and
ensuring the preservation and stability of the anchoring points of the signs.
The customer is obliged to create a geodetic alignment basis for construction and transfer
technical documentation to the contractor, namely:
- construction grid points, red lines;
- axes indicating the position and dimensions of buildings and structures in plan, fixed by
Deputy inv.

created signs in the amount of at least four for each axis, as well as transport and engineering on-
No.

site communications;
- benchmarks on the borders and inside the territory, which is being built up at least two near a
Signature and date

separate building.
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


27
ge Doc.
The accuracy of constructing a geodetic alignment base must be taken according to the
accuracy class in accordance with the requirements of the standard “System for ensuring the
accuracy of geometric parameters in construction. Geodetic work in construction.
Geodetic alignment work during the construction process is carried out by a contracting
construction organization, ensuring the safety of the geodetic alignment marks.
The breakdown of intermediate axes of a building must be done, as a rule, by direct
measurements of distances from the main axes. In this case, lines can be drawn into nature,
parallel shifted relative to the axes and edges of the structures.
Altitude breakdown of the position of structures, as a rule, must be carried out using the
method of geometric leveling from the benchmarks of the geodetic alignment base. The number
of rappers must be at least two.
Technical means and methods for performing geodetic marking work in construction must be
selected taking into account the conditions for ensuring accuracy specified in the standards
“Geodetic work in construction”.
All measurements of instrumental testing are applied to the as-built diagram of geodetic
survey, which is attached to the act for hidden work.
Methods of geodetic control are selected when developing a project for the production of
geodetic work (PGW), taking into account the building structures adopted in the project,
technology for performing work, and geological conditions.

11. Assessment of impact on the natural environment.


Construction and installation work during construction must be carried out in compliance with
the requirements of environmental legislation and ensure effective protection of the environment
from pollution and damage.
The construction mechanisms adopted in the project during the construction process do not
create emergency emissions of harmful substances into the air or negative impact on the
Deputy inv.

environment: land, flora, fauna. The removal of atmospheric water from the site is assumed to be
No.

through the surface and trays of intra-block driveways with the release of technical specifications
accordingly.
Signature and date

To comply with the requirements and reduce harmful production factors (noise, dust formation
and vibration) on workers and residents of the adjacent territory when performing construction
and installation work, use serviceable construction machines and mechanisms, eliminate idle
operation of internal combustion engines,
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


28
ge Doc.
use electric welding machines, compressors, pumps, and small-scale mechanization equipment
primarily powered by electricity.
A temporary paved access road is being constructed at the construction site in compliance with
the requirements to prevent dust formation and air pollution.
Temporary household premises are located in mobile inventory trailers used in construction
organizations. Household wastewater is discharged into a temporary sewer network with a
connection to city networks. On the site for the collection of construction waste and garbage,
bunkers are used - storage bins, which, when filled, are transported to certain places agreed upon
with the relevant services.
In order to preserve the environment during the preparatory and main construction periods, the
following conditions must be observed:
- prevent the accumulation of construction waste at the construction site, remove it in a
timely manner to specially designated cities;
- keep temporary access roads and internal roads in good condition;
- to transport cement, concrete, prefabricated reinforced concrete structures, use special
vehicles (cement trucks, panel trucks, etc.);
- transportation and storage of building materials, hardening retarders and accelerators,
plasticizers, organic solvents, varnishes, synthetic paints and other chemicals must be carried out
in compliance with established technical requirements;
- limit the operation of internal combustion engines of construction machines and
mechanisms only for the time necessary for this; use electric welding machines, pumps, and
small-scale mechanization equipment primarily powered by electricity;
- establish control over water consumption for construction needs and not exceed the
allocated limits;
– ensure a high level of operation of construction equipment, machines and mechanisms;
- maintain green spaces available near the construction site - trees, shrubs, lawns.
Deputy inv.

It is not allowed to demolish trees and shrubs and cover the root collars and trunks of growing
No.

trees with soil that is not provided for in the design documentation.
Signature and date
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


29
ge Doc.
trees. If it is necessary to preserve trees, clips made of boards to a height of 2.0 m are used.

12. Determination of the duration of construction of the facility


Determination of the duration of construction of the facility is carried out
according tostandard Determination
of the duration of construction of facilities.
The duration of construction is determined by the formula:
TWITHx K1x
K2TSTR=
-------------------
TO3 , Where:
TWITH– average indicator of construction duration;
TO1– coefficient that takes into account the totality of specific construction conditions object
(difficult engineering and geological conditions, building density, seismic conditions;
TO2– coefficient that takes into account the totality of design features buildings (type of
foundation, both underground and above-ground parts of the building, their relationship,
complexity of the structural design;
TO2– coefficient that takes into account work shifts.

TO1= Kelevenx K12x K13

TOeleven– we accept 1.1 (a coefficient that takes into account the complexity of
engineeringgeological conditions);
TO12 – we accept 1.1 (coefficient that takes into account the construction
Vseismically unsafe conditions);
TO13– coefficient that takes into account the level of influence of dense development
conditionsfor the duration of construction and is calculated:
Deputy inv.

TO13= 1 + P1+ P2+ P3


No.

P1– we accept 0.06 (the presence of cramped conditions for storing materials);
P2– not taken into account (a coefficient that takes into account the presence at the construction
Signature and date

siteengineering networks);
P3– not taken into account (a coefficient that takes into account traffic intensity vehicles and
pedestrians near the work site);
Then K13= 1.0 + 0.06 = 1.06, henceWe define:
Inventory No.

Shee
CUBE Apartments-PZ t
orig.

ChanQty SheetNo. Signature date


thir
ge Doc. ty
TO1= Keleven* TO12* TO13=1.1 * 1.1 * 1.06 = 1.28.
We accept:
K2 – 1.1 (according to clause 4.2.9);
K3 – 1.0 (according to clause 4.2.10).
Aboveground part (approximate area 8000m2)
We accept the interpolation method based on the area indicators for exhibition halls available
in the standards - 5000.0 m2 and 10000.0 m2 with construction duration standards of 10.5 months.
and 15.0 months. according.
The duration of construction per unit increase in area will be: (15.0-10.5) : (10.0-
5.0) = 0.9 ms.
The increase in area will be:
8000 – 5000.0 = 3000 m2.
The average construction duration using the interpolation method will be:
TS.supervision=10.5 + 0.9 x 3.0 ≈ 13.2 ms.
The duration of construction of the above-ground part is calculated according to (1):
Tsupervising= TC * K1 * K2 / K3 = 13.2 * 1.28 * 1.1/1.0 = 18.5 ms.
Parking (approximate area 1500m2)
We accept the average duration of parking construction: TS.park. = 10.0
months.
We calculate the duration of parking construction according to (1): T
= TC * K1 * K2 / K3 = 10.0 * 1.28 * 1.1/1.0 = 14.0 ms.
The duration of construction of the facility is assumed to be 25.0 months. taking into account the
combination of work.
The duration of preparatory work is assumed to be 2.0 months.
Deputy inv.

13. List of requirements for basic construction machinery, mechanisms and equipment
No Quanti
Name
No.

. ty,
pcs.
Construction equipment
1 Hitachi 250 excavator 2
Signature and

2 Bomag roller 1
3 JCB 3CX backhoe loader 1
4 Concrete pump type Ford Trucks 3542M BST 37 1
date

Krani:
5 Tower crane Lstr = 70.0 m, lifting capacity – 12.0 t 1
Inventory
No. orig.

Sheet
CUBE Apartments- 31
Change Quantity Sheet Signatur date PZ
Doc. No. e
6 Tower crane Lstr = 60.0 m, lifting capacity – 10.0 t 1
7 Truck crane XCMG QY25K5, Lstr = 38.0 m, lifting capacity – 25.0 t 1
8 Truck crane type KTA-18, Lstr= 15.7 m, lifting capacity – 18.0 t 1
Motor transport:
9 Dump truck 4
elev Airborne transport 4
en
12 Long transport 2
13 Compressor 6 – 8 atm. 1
14 Concrete pump Putzmeister 1407 BSA 1
Instrumentation and equipment:
15 Electric welding machine STN - 500 3
16 Step-down transformer IV - 4 1
17 Pneumatic rammers TR-1, IZ-4501 2
18 Hammer – rotary hammer Bosch 6045 S 6
19 Deep vibrator IV – 67 4
20 The same, surface type C – 414, C – 802 1
21 Electric wood saw PFZ 1200 A 2
22 Electric rotary hammer HR 4000C 6
23 Impact electric drill GSB 182RE 2
24 BOSCH angle grinder 4
25 Bucket for supplying concrete 2
26 Tura unified 4
27 Theodolite TL - 5 1
28 Level TD-5 2
29 Scissors for cutting reinforcement (SMZh-172A) 1
When constructing a facility, it is necessary to use sets of manual machines, mechanisms, and
tools that facilitate construction and installation work, as well as improve quality.
The availability of machines and mechanisms is specified in the temporary residence permit by
the contracting organization according to their availability in the construction organization’s fleet.

14. Calculation of energy resource requirements


14.1. Calculation of construction site lighting
Deputy inv.

External security lighting of a construction site and selection of floodlights


No.

is carried out according to the standard


“Lighting Standards for Construction Sites”.
Calculation of outdoor lighting (number of spotlights) is determined by the formula:
m x Ep x S
Signature and

n=
RL, where:
m is a coefficient that takes into account the luminous efficiency of light sources, the
date

efficiency of floodlights and the coefficient of utilization of the luminous flux, taken according to
the table in Appendix 3 p. 25 – equal to 0.25;
Inventory
No. orig.

D .
o N
c o.
Change Quantity Sheet Signature date
She
CUBE Apartments- et
PZ 32
R l – lamp power, types of spotlights used (100 W);S-
construction site area, m2;
E r – calculated illumination, adopted according to the
formula: E r = K x E n = 1.7 x 0.5 = 0.85
K – safety factor for floodlights with gas-discharge lamps = 1.7 (Table 2, page
12);
E n - standard illumination for security lighting = 0.5 l (general
provisions of clause 1.10 p. 3)
m x Ep xS0.25 x 0.85 x 3775
n == = 8.0 ave.
RL100
The total need for floodlights is 8.0 pcs.

14.2. Calculation of the need for energy resources at a construction site.


Determination of power consumers of temporary power supply is carried out for the period of
full reversal of work.
The need for electricity at a construction site is determined according to the Guidelines for the
development of work projects using the formula:
1.1
R cos
( K P
1 1
 2
 K 
3
, de
K P 2 P)3

P is the total power demand, kVA;


1.1 - coefficient establishing power loss in the network;
K1, K2, K3, K4 - simultaneity coefficients, depending on the type and number of consumers
(0.6 - 1.0);
P1 – power consumed by construction machines, tools, mechanisms, kW;
Р2 – power consumption for technological needs, kW;
Deputy inv.

P3 – power consumption for interior lighting, kW; сos ψ – power factor


(0.75).
No.

Reduced
Number of Installed Coef. Ʃ use, Ks
No Name of power of
consumers, power,
. consumers consumers,
Signature and

pcs. kWt
kW
1 2 3 5 6
1. Tower crane 2.0 60.0 0.8 96.0
date

2. Welding machine STN – 500 3.0 20.0 0.4 24.0


Inventory
No. orig.

Sheet
CUBE Apartments- 33
Change Quantity Sheet Signatur date PZ
Doc. No. e
Vibrators for compacting
3. concrete mixture IV – 66, IV-47 4.0 0.75 0.6 1.8
deep
Scissors for cutting
4. 1.0 3.0 0.5 1.5
reinforcement SMZh-172A
5. Plastering unit PFT G5 2.0 6 0.6 7.2
Other consumers, hand power
6. 25.0 1.0 0.6 15.0
tools
Lighting:
7. - external 8.0 0.1 1.0 0.8
- internal 60.0 0.1 0.9 5.4
Total x 1.1, kW 166.9
Total, kVA 222.5

14.3. Water requirement.


1. Water consumption for production needs
The need for water is provided by a connection device to a temporary water supply system arranged
according to a permanent scheme.
Calculation in water is carried out in accordance with the “Guidelines for the development of
construction organization projects and work projects.
The total water consumption for production needs is determined by the formula:
Q1 =K1хq1 n1 Ky
t1 x 3600
Where:
q1 - specific water consumption for production needs;
n1 is the number of production consumers in the busiest change; K1 - coefficient for
unaccounted water consumption (equal to 1.2);
kй is the coefficient of hourly unevenness of water consumption (equal to 1.5); t1
- number of hours per shift.
Number of
No Name of Unit Regulatory General
Deputy inv.

similar
. consumers expenses requirement
consumers
1 Excavator l/year. 15 5 75
No.

Cars (washing,
2 l/year. 25 6 150
refueling)
Compressor
3 l/year. 10 1 10
station
Signature and

4 Painting works l/year. 1.0 75 75


Total 310
date

Q1 = 1.2 x 310 x 5 x1.5 = 0.1 l/s


8 x 3600
Inventory
No. orig.

Sheet
D c. o.
Change Quantity Sheet o N
C
Signature date U
B
E
A
p
a
rt
m
e
n
ts
-
P
Z

34
2. Water consumption for household needs.
Water consumption for household needs is determined by the formula:
Q2 = K2 x q2 n2 K2 + Q2 N2
t1 x 3600t2, de:
q2 - specific water consumption for household needs - 15 l;
n2 - number of productionconsumers in the busiest change – 43 people;N2- the number
of workers using the shower (40%) – 43*0.4=17 people;
Q2- water consumption for showering by one employee is 30 l;
K2- coefficient of hourly unevenness of water consumption (equal to 1.50);
t2 – duration of use of the shower unit (45 min.) – 45x220 = 9900 sec.
Q2 = 1.5 x (15 x 43 x 1.5) + 30 x 17 = 0.05 + 0.05 = 0.1 l/s
8 x 36009900
3. Requirement of water for fire extinguishing.
Water consumption indicators for extinguishing a fire at a construction site through hydrants
are determined according to the “Guidelines for the development of construction organization
projects and work projects”
Ql.= 10 l/s.
4. Water requirement for workers' drinking needs
To meet water needs, fountains should be installed at a rate of one per 150 workers at a
distance of no more than 75 m from workplaces. The fountain is installed under a special canopy
or in isolated rooms with the inscription “Drinking Water”.
If it is not possible to organize a centralized water supply for drinking needs, water should be
delivered in special tanks with a volume of 30 liters at the rate of 2 liters per shift per worker.
5.Total water consumption for the needs of the construction site.
The total water consumption for supplying the construction site consists of the total water
consumption for production, economic and domestic needs and fire extinguishing:
Deputy inv.

Q total = 0.1 + 0.1 + 10 = 10.2 l/sec.


No.

14.4. Calculation of compressed air requirements


Regulatory Regulatory
Consumers Qty requirement demand by type of
Signature and

per unit, m3/hv consumer, m3/sw


Pneumatic rammer 2 0.8 1.6
Plastering station 2 2.0 4.0
date

Painting machine 2 0.2 0.4


ΣE= 6.0 m3/min
Inventory
No. orig.

Sheet
CUBE Apartments- 35
Change Quantity Sheet Signatur date PZ
Doc. No. e
The total demand for compressed air, taking into account the simultaneous operation coefficient of
the mechanisms, is:
E
E = 0.7* = 0.7*6.0 = 4.2 m3/hv,
Power of the compressor unit taking into account the coefficient of air loss in pipelines:
N = 1.3*4.2 = 5.5 m3/hv.
1 mobile compressor type PKS-5.25 is accepted
productivity5.0m3/min.

15. Determining workforce needs


Demand for
No Category of Share of
construction
. workers employees in %
workers
people
1 Workers 100 60
including:
2 workers 84.5 50
3 engineers eleven 7
4 employees 3.2 2
5 MOP and security 1.3 1
6 workers x 0.7
Busiest shift 43
+ ITR x 0.8

16. Need for temporary living quarters


When compiling a set of temporary buildings and structures located on a construction site, the
following are taken into account:
- the need to provide construction with temporary buildings
industrial purposes;
- the need to provide living quarters for workers;
Deputy inv.

– the need to ensure safety and fire protection requirements.


All temporary structures must be located outside the danger zone of crawler and truck-mounted
No.

cranes and meet the following requirements:


- do not interfere with the execution of work during the construction period;
- ensure safety and convenience of approaches;
Signature and

- provide optimal connection schemes for all types of energy resources.


Open areasfor storing building structures, they must be placed within the range of the erection
date

crane.
Inventory
No. orig.

Sheet
CUBE Apartments- 36
Change Quantity Sheet Signatur date PZ
Doc. No. e
To accommodate administrative, engineering, technical and office personnel, a mobile-type
foreman's office with an area of 18.0 m2 and plan dimensions of 6.0 x 3.0 m is being adopted.
To meet the domestic needs of construction we accept:
- dressing room - mobile shower with an area of 18 m2, dimensions 6.0 x 3.0 m.
- drying and room for heating workers - dimensions in plan 6.0x3.0 m, area
– 18 m2.
Workers and engineers eat meals in household premises, or workers use city canteens and
cafes. It is not planned to install temporary canteens on the territory of the camp.
Calculation of areas of inventory buildings
Normal Effective Required in
No Name of premises and
index, Calculat area, room,
. dimensions in plan m2 per m2 PC.
ion
person
1 2 3 4 5 6
1 Dressing room - shower 0.7 0.7 x 43 30.0 2
2 Shower 0.5 0.5 x 17 8.5 1
3 Drying 0.2 0.2 x 43 8.6 1
4 Room for heating workers 0.1 0.1 x 43 4.3 1

5 Proslavery 4.0 4.0 x 7 28 2


6 Toilet (dry toilet) 0.1 0.1 x 43 4.3 4

17. Technical and economic indicators


Unit
Pos. Name Qty Notes
1 2 3 4 5
1 Duration of construction, in months 25.0
including:
Deputy inv.

2 preparation period months 2.0


3 Amount of workers people 60.0
No.

4 Electricity requirement kW 166.9


5 Water requirement l/s 10.2
Signature and

6 Compressed air requirement m3/min 5.5


date
Inventory
No. orig.

Sheet
CUBE Apartments- 37
Change Quantity Sheet Signatur date PZ
Doc. No. e
U

96.417
9 TE
7. <topToAltvalue> BI 96.649
96.942 5
99.170
NG
0 9
B T 99.170 0 96.44996.746 7.
5
0
0
96.710
99.307

99.717
99.307

Scheme of the construction plan of the 96.986


99.717

S underground part 10
0.0
100.460
0
99.827
099.827
.
100.460
00
Symbols for the construction plan 10
0
97.032
0
0
2.5 97.303 100.440

Temporary fencing
99.750
00 Capture #1 100.440
Load height characteristics of the XCMG QY25K5 crane
100.974

construction site temporary passages pl. shield fire station 99.750


100.974
danger zone Metal 100.974

boundarypossible fall of a spacers 97.684


Crane working area LED spotlight -4.800
load from a building profiles 103.170
95.45
boundary
99.190

temporary gate parking placesvehicles 98.571


during unloading and Crane
shield Tower crane shield
loading
Capture #2
Post location forvehicle wheel temporary storage areas for -1.700
Entry - exit washing structures and materials R 98.55
36 98.845
temporary buildings and 99.877 98.704
direction of movement of
.0
Technological direction of work structures
Parking for truck crane
101.04 0
execution vehicles 101.382101.382
1 01.040
type XCMG QY5K
capacity -25.0t
Lpage=38.5m, Liebherr
LTM 1045, concrete R
103.208
pump 100.314 103.208
22
.6
99.718
100.412 100.298
100.000
88.819 98.822

100.021
98.880
Gates Information stand with a
passport of the object 100.148

100.046
99.842 101.42
18 01.428
99.719 98.785
JALAN 99.041
ASPAL 88.9568899..
005342
10
0.0
98.774
00
89.216
88.992 5

89.145
99.979
99.69491.22 Capture #3
9
89.142 -1.200
99.05
102.787
88.769 102.977
99.564 102.977
102.787

98.614
Security
post
-5.900
89.115 94.35
102.611
102.178
98.292
10 102.178 102.611 99.458
2.5
Set warning signs, speed limit sign 9 00
and traffic pattern 89.821 0. 98.331
89.699
0 Vehicle turning 101.663 101.770
98.515
0 102.101
0
point 96.338 97.003
9 10 99.519 100.148
0. 98.008 0.0 100.244
91.202 9 99.547 98.727
0 95.358 00
7.
0 5
99.0
Z7A5gripANo
0 0 98.041
.4
95.198 97.387
0
-5.900
9
Fire shield with fire-fighting equipment. 2.
96.33196.598 98.598
5
92.861 96.73596.735 94.939
97.387 98.778 94.3
0 5
0 95.751
9 95.444 95.595 Склад 98.218
1. fire extinguishers; 5. - 97.499 арматури
2. sand box; 0 98.672
93.093
0 95.237 7.100
3. blanket made of non- 96.811 96.873
9 0 95.195 96.476
97.416 93.15 Capture #7
flammable material - 2x2m; 2.
96.685

4. hooks; 94.810 95.849 97.411 97.618


5
5. shovels; 0 96.685 98.474
97.654
6. crowbars; 0 97.646
7. axes; 96.304 97.532
8. bucket; 94.838 97.412
9. barrel of water. 99.068
97.906
95.242 98.399
9 97.858
5. 97.312 98.442
0 97.701 98.261 98.569
98.430 98.623
0
0 пож 97.616 Capture #5
. BANGU
-7.100
Schematic diagram of temporary fastening щит NAN 97.842 98.367
93.15
of fences of surrounding buildings -
99.461
98.751 98.526
7.100
99.200
Wood 93.15
Fence shield
Metal spacer Е 98.105
Capture #6 99.444
98.235
П
Fence
99.410
99.301
99.87046
99.553 99.115
10
Installation location of the 100.157
100.020
0.0
concrete mixing unit 99.228 pohon 00

98.095
Metal support 100.207

99.990 99.561
100.137 pohon
97.993 100.019
pohon 10 pohon
Subset Layout Number
Symbols for the construction plan
U
Temporary fencing
construction site temporary passages pl. shield fire station

danger zone
boundarypossible fall of a Gallery for the passage of LED spotlight 96.417
load from a building workers to their workplaces 9 TE
7 BI 96.649
N
Departure limit line parking placesvehicles during
96.942 .
99.170
5 G
B T 99.170 9
Crane
tower crane hook unloading and loading shield Tower crane shield
0
0
96.44996.746 7
.
Post location for 5
temporary sites 0
99.30
0
976.710
temporary gate vehicle wheel washing storage of structures and 99.717 99.307
materials 96.879 99.717
96.986
10
Entry - exit direction of movement temporary buildingsAnd 10
0.
99.827
00
S
motor transport structures 0. 100.46099.827
0
00 100.460

4
7
6
5
3
2
1
0 8 97.032
10 91
Technological direction of work 2.
01
11

execution Tower crane fence trash can 50


21
1
3
41 99.750
97.303
0 15
61 100.440100.917040.440
99.750 71
1
8
2
9
0
100.974
100.974
97.684

Load characteristics of the Comansa 10LC90 crane 103.170 103.170

99.190
98.571

s
1

99.877 98.845
98.704
101.014001.040
101.382
101.382

103.208
100.314
103.208 99.718
100.412 100.298
100.000
88.819 98.822

Option #1 100.021
98.880
Gates Information stand with a
passport of the object 100.148

Tower crane type 100.046


Comansa 10 LC90, 99.842 101.412081.428
lifting capacity - 3
32
99.719
99.041
98.785
JALAN
6.0t, Lpage=40m
31

ASPAL
88.956 20
29
89.032
89.054 Щит 8
кра
s на 10
2 0.
98.774
00
89.216 2 0
88.992 5 27
26
25
42
3
89.145
99.69491.229
99.979

R40
2
22
2 1
10
19
102.787 8

.0
88.769 102.977
99.564 102.977
102.787
Tower crane type 1
98.614
Comansa 10 LC90,
17
16
Burial 15
14

post lifting capacity - 3

89.115
6.0t, Lpage=50m
102.611 1
12
102.178 11
09
8
98.292
102.171802.61 99.458
10
Set warning signs, speed limit sign 9 2. 1
and traffic pattern 89.821 0 50 98.331
89.699 .
0
Vehicle turning 101.663 101.770 0 7
6

0 point 96.338 97.003


102.101
102.101
98.515 4
5
0 99.519 100.148 3
9 10 101.770 2
1
0 98.008 0. 100.244
91.202 9 95.358 99.547 100.148 101.663 98.727
. 00
0 7 100.244
. 97.45298.008 97.949 99.547
0 99.519 99.075
0
0 9 5 97.949 95.510
95.19897.387 0 95.394
2 97.452 98.041
. 0 96.331 96.598 98.598
92.861 96.735 94.939 95.403 98.778
5 96.735 95.582
0 95.751 97.387
0 9 95.444 95.595 Склад 98.218
5 97.499 арматури
.
93.093 0 95.237 98.672
0 96.811 96.873
9 95.195 96.476
2 0 97.416
96.685
. 94.810 95.849 97.411 97.618
5 98.474
0 96.685 97.654 Щит
0 кра
1 97.646 на 97.532
96.304
2
3
4
94.838 5
6 97.412
7
8 99.068
91
10
11 97.906
12
95.242 13 98.399
9
14
15 97.858
16
5 7
97.312 98.442
. 97.701 98.569
0 98.261 98.430 98.623
0
0 пож
.
112222222
890123456
97.616
222
789
BANGU
R50
.0
NAN 97.842 98.367
щит
99.461
s
4 98.751 98.526
99.200 6
1 2 3 87
Fire shield with fire-fighting equipment. Е 98.105 99.444 91
10
4 5

11

П 98.235 12
13
14
1. fire extinguishers; 2222 2
3
15
16
132 2 2 2 72 2 1 1
2. sand box; 9876 5
2 3210 98
0
92
54
99.410 2
8
3. blanket made of non- 2
42
99.301 72
6
flammable material - 2x2m; 32
22
21
99.87046
4. hooks; 01
99.553 99.115 pohon
1 10
Installation location of the
9
81
5. shovels; 1 11111 7 100.020 0.
7 8 91 2 3 4 5 6
123456 01
6. crowbars; concrete mixing unit 100.157 00
0
7. axes; 9 99.228 pohon
7
8. bucket; .
98.095
9. barrel of water. 5 100.207
0
0 99.990 99.561
100.137 s
pohon
97.993
100.019 7
pohon 10
5 0. pohon
00
0
Subset Layout Number
Symbols for the construction plan
U
Temporary fencing
construction site temporary passages pl. shield fire station

danger zone
boundarypossible fall of a Gallery for the passage of LED spotlight 96.417
load from a building workers to their workplaces 9 TE
7 BI 96.649
N
Departure limit line parking placesvehicles during
96.942 .
99.170
5 G
B T 99.170 9
Crane
tower crane hook unloading and loading shield Tower crane shield
0
0
96.44996.746 7
.
Post location for 5
temporary sites 0
99.30
0
976.710
temporary gate vehicle wheel washing storage of structures and 99.717 99.307
materials 96.879 99.717
96.986
10
Entry - exit direction of movement temporary buildingsAnd 10
0.
99.827
00
S
motor transport structures 0. 100.46099.827
0
00 100.460

4
7
6
5
3
2
1
0 8 97.032
10 91
Technological direction of work 2.
01
11

execution Tower crane fence trash can 50


21
1
3
41 99.750
97.303
0 15
61 100.440100.917040.440
99.750 71
1
8
2
9
0
100.974
100.974
97.684

Load characteristics of the Comansa 11LC160 crane 103.170 103.170

99.190
98.571

s
1

R55
99.877 98.845
98.704
101.014001.040

.0 101.382
101.382

103.208
100.314
103.208 99.718
100.412 100.298
100.000
88.819 98.822

Option No. 2
100.021
98.880
Gates Information stand with a
passport of the object 100.148

100.046
99.842 101.412081.428
3 99.719 98.785
99.041
Tower crane type
32
JALAN 31

ASPAL
88.956 20
29
89.032
89.054
Comansa 11 LC160 s
8

10
Zoomlion 7025 2 98.774 0.
89.216 SYM K30/30 2
00
0
88.992 g/p-10...12.0t 27
26
25
24
5
89.145 Lpage=55...65m 3

99.69491.229
99.979

2
22
2 1
10
19
102.787 8

88.769 102.977
99.564 102.977
102.787
Щит1
кра17
1
98.614
на156
Burial 14
3
post
89.115
102.611 1
12
102.178 11
09
8
98.292
102.171802.61 99.458
10
Set warning signs, speed limit sign 9 2. 1
and traffic pattern 89.821 0 50 98.331
89.699 .
0
Vehicle turning 101.663 101.770 0 7
6

0 point 96.338 97.003


102.101
102.101
98.515 4
5
0 99.519 100.148 3
9 10 101.770 2
1
0 98.008 0. 100.244
91.202 9 95.358 99.547 100.148 101.663 98.727
. 00
0 7 100.244
. 97.45298.008 97.949 99.547
0 99.519 99.075
0
0 9 5 97.949 95.510
95.19897.387 0 95.394
2 97.452 98.041
. 0 96.331 96.598 98.598
92.861 96.735 94.939 95.403 98.778
5 96.735 95.582
0 95.751 97.387
0 9 95.444 95.595 Склад 98.218
5 97.499 арматури
.
93.093 0 95.237 98.672
0 96.811 96.873
9 95.195 96.476
2 0 97.416
96.685
. 94.810 95.849 Щит 97.411 97.618
5 кра
98.474
0 96.685 на 97.654
0 97.646
96.304 2
1 97.532
3
4
94.838 5
6 97.412
7
8 99.068
91
10
11 97.906
12
95.242 13 98.399
9
14
15 97.858
16
5 7
97.312 98.442
. 97.701 98.569
0 98.261 98.430 98.623
0
пож
R65
0 97.616
222
112222222
789
890123456
. BANGU
NAN 97.842 98.367
щит
s
4
.0 98.751 98.526
99.461

99.200 6
1 2 3 87
Fire shield with fire-fighting equipment. Е 98.105 99.444 91
10
4 5

11

П 98.235 12
13
14
1. fire extinguishers; 2222 2
3
15
16
132 2 2 2 72 2 1 1
2. sand box; 9876 5
2 3210 98
0
92
54
99.410 2
8
3. blanket made of non- 2
42
99.301 72
6
flammable material - 2x2m; 32
22
21
99.87046
4. hooks; 01
99.553 99.115 pohon
1 10
Installation location of the
9
81
5. shovels; 1 11111 7 100.020 0.
7 8 91 2 3 4 5 6
123456 01
6. crowbars; concrete mixing unit 100.157 00
0
7. axes; 9 99.228 pohon
7
8. bucket; .
98.095
9. barrel of water. 5 100.207
0
0 99.990 99.561
100.137 s
pohon
97.993
100.019 7
pohon 10
5 0. pohon
00
0
Subset Layout Number
Symbols for the construction plan
U
Temporary fencing
construction site temporary passages pl. shield fire station

danger zone
boundarypossible fall of a Gallery for the passage of LED spotlight 96.417
load from a building workers to their workplaces 9 TE
7 BI 96.649
N
Departure limit line parking placesvehicles during
96.942 .
99.170
5 G
B T 99.170 9
Crane
tower crane hook unloading and loading shield Tower crane shield
0
0
96.44996.746 7
.
Post location for 5
temporary sites 0
99.30
0
976.710
temporary gate vehicle wheel washing storage of structures and 99.717 99.307
materials 96.879 99.717
96.986
10
Entry - exit direction of movement temporary buildingsAnd 10
0.
99.827
00
S
motor transport structures 0. 100.46099.827
0
00 100.460

4
7
6
5
3
2
1
0 8 97.032
10 91
Technological direction of work 2.
01
11

execution Tower crane fence trash can 50


21
1
3
41 99.750
97.303
0 15
61 100.440100.917040.440
99.750 71
1
8
2
9
0
100.974
100.974
97.684

103.170 103.170

99.190
98.571

Option #3 s
1

Tower crane type 99.877 98.845


Load characteristics of the Potain_GTMR 336B_1 crane EUROGRU E42.10
98.704
101.014001.040
Potain IGO40 101.382
101.382
Potain GTMR 336B
SanMarco SMH400
g/p-4.0t Lpage=40...43m
103.208
R40
100.314

100.412
103.208 .0 99.718
100.298
100.000
88.819
Load characteristics of the Potain_Eurogru E42.10 crane 98.822

100.021
98.880
Gates Information stand with a
passport of the object 100.148

100.046
99.842 101.412081.428
3 99.719 98.785
32 99.041
JALAN 31

ASPAL
88.956 20
29
89.032
89.054 8
Щит
s кра 10
на
2 98.774 0.
00
89.216 2 0
88.992 27

Load characteristics of the Liebherr 63K crane


26
25
24
5 3
89.145
99.69491.2
99.979 29

2
22
2 1
10
19
102.787 8

88.769 102.977
99.564 102.977
102.787
1
17
16
98.614
Burial 15
14
3
post
89.115
Tower crane type 102.611 1

EUROGRU E42.10 102.178


12
11

Potain IGO40 09
8
98.292
102.171802.61 99.458
Set warning signs, speed limit sign 9 Potain GTMR 336B 10
2. 1
and traffic pattern 89.699
89.821 0 SanMarco SMH400 50 98.331
.
0
Vehicle turning g/p-4.0t 101.663 101.770 0 7
6

0 point Lpage=40...43m
96.338 97.003
102.101
102.101
98.515 4
5
0 99.519 100.148 3
10 101.770 1
2
9 0. 100.244
91.202 99.547 100.148 101.663 98.727
0 00
. 98.008
9 95.358 0
0
7 100.244
0
. 97.45298.008 97.949 99.547 99.519 99.075
0
9 5 97.949 95.510
95.19897.387 0 95.394
2 97.452 98.041
. 0 96.331 96.598 98.598
92.861 96.735 94.939 95.403 98.778
5 96.735 95.582
0 95.751 97.387
0 9 95.444 95.595 Склад 98.218
5 97.499 арматури
.
93.093 0 95.237 98.672
9 0 96.811 96.873
95.195 96.476
2 0 97.416
96.685 Щит
. 94.810 95.849 кра 97.411 97.618
5 на 98.474
0 96.685 97.654
0 97.646
96.304 2
1 97.532
3
4
94.838 5
6 97.412
7
8 99.068
91
10
11 97.906
12
95.242 13 98.399
9
14
15 97.858
16
5 7
97.312 98.442
. 97.701 98.569
0 98.261 98.430 98.623
0
0 пож 112222222
97.616
222
789
890123456
. BANGU
NAN 97.842 98.367
щит
99.461
s
4
R40 98.751
99.200
98.526

1 2 3 87
6

Fire shield with fire-fighting equipment. Е


.0
4 5
98.105 99.444 91
10
11

П 98.235 12
13
14
1. fire extinguishers; 2222 2
3
15
16
132 2 2 2 72 2 1 1
2. sand box; 9876 5
2 3210 98
0
92
54
99.410 2
8
3. blanket made of non- 2
42
99.301 72
6
flammable material - 2x2m; 32
22
21
99.87046
4. hooks; 01
99.553 99.115 pohon
1 10
Installation location of the
9
81
5. shovels; 1 11111 7 100.020 0.
7 8 91 2 3 4 5 6
123456 01
6. crowbars; concrete mixing unit 100.157 00
0
7. axes; 9 99.228 pohon
7
8. bucket; .
98.095
9. barrel of water. 5 100.207
0
0 99.990 99.561
100.137 s
pohon
97.993
100.019 7
pohon 10
5 0. pohon
00
0
Subset Layout Number
NAMA PROYEK:

CUBE
Apa gtme nt s

LOKASY PROYEK:

Pecatu1-.SouthKuta,
Badung,oalli,lndonesia

PEMILIK PROYEK:

Organizational and technological diagram (option 3)

'' NO CATATAN PARAF

R=40...43.0m {

4.2
'
¼1f-/,J,f,Y/,J,},/,/,/,1 ///,;tt,f/,,;t_ 1,f?./.1f-f/ / , / ,,J,;4;,
,, ;,ofY/ #, fY#f , Y,N J

W>=>Sh№y# >F_ j =>- "-“#•MS


NAMA GAMBAR SKALA

h;

,I
t 1¼ ' / , / ¾ 1 / - ' ; / / ,'/,Y,;/,J,v;, , ,;1,-.-\'·/f /,f,;,,1//!Mf/,J,f;:,,/:f¼/,/-,, Section 1:300
1
26.1

,}{//,M'','. ' ,/,/,J,J,Y,;,tJ,;r;;,;-1/,:;,;f,f,?,,:7,f,?f/.)d, ,/,,?,Jr,1/,Y,)) -IZZ/


4414.0

-
F
D.I.GAMBAR

_,.
_ PENANGGUNGJAWAB PARAF
- 1/,¼f-J/d{, / At f-1///¾ L'! j.1//,J,f-½ / f « - 1 / , / ',1/x½f,Y,)
A.R.S.IT
EKSKA
,7,Y,/-,/ ' NO.

'
1/,,

STRUKTUR:
---;
-
1/,/,Ai(/,7,71,-'/,!,f,Y/,,/Mt,l,lf ",1/,;,;,{1/;,,oAY,/,;f ;,y ,• SKA NO.
;, 1/,1/,
MEP:SK

\
.P P
A NO.
5.17


G.
_,L PEMILKI:
'
"71= ""

-
;?,/,/" /.½½/,/',/,U;,' ;/,/',/,
r,r,;,,,,r'v;;/ ,-/'/ ½ Y//,,1,1/,/,,/ /', PERNY ATAAN:
(:1/,;/,,,',/',/,½¼i
//-/

j
:1/,1/,/,/ 1/.½ ¼½7

4.4

1. BERTANGGUNGJAWABPERUHTERH
ADAP BANGUNAIANGTHOSELANBERDINI
BAIKM.E.NYANGKUTKEKUAT AN
KONTRUKSIKEKOKOHAN &KUALITAS
STRUKTURBANGUNANSERT A
KESELA.M.A.TANUMUMDILINGKUNGANSE
KIT ARNY A DARI
KEGAGALANKONTRUKSI
2 BERTANGGUNG JAWAB PERUH TERHADAP
SEGALA DAMPAK YANG TIMBUL AKIBAT
BERDIRINYА BANGUNANTERSEBUT
3.MENYATAKAN BAHWA GAMBAR SESUAI
DENGANKETENTUAN УANG BER.L.A.KU

DIP. DIK. DIS

MENGETAHUI

NO.GDR JUM. GDR TGLACC


#Layout NumberByrecruitment