Vexil Business Process Services Pvt. Ltd.
Management System Audit Report VE XIL
BP S
Client : Oil and Natural Gas Corporation Limited, Assam Asset
CLIENT INFORMATION
Registered office HSE Dept: Assam Asset, Ground Floor, ROE III, Nazira 785 640,
address Assam, India
Tel & Fax.: 03772-241821
Contact Person / Mr. Rajendra Prasad Bharsakle - Mob. 9969223388, 9435717046
Alternate details GM(E) & Head HSE and E mail: bharskle_r@ongc.co.in;
Mr. D J Dutta - DGM(D) dutta2_dibyajyoti@ongc.co.in;
assamahse@ongc.co.in
Site(s) Site 1 to Site 64
Address
Products/Services
Activities/Processes
See Annexure A
Language(s) Spoken
Contact Person
Telephone
Organization personnel details Site 1 to Site 64
G I II III G I II III
Total Number of personnel shift wise
Number of part time personnel, if any
Number of unskilled / temporary
personnel (material handling, loading/
unloading, etc.)
Number of personnel carrying out See Annexure A
similar simple functions/
processes /activities in each shift
(transport, line work, assembly lines)
Total area (Sq. Mtrs.) including area
covered
AUDIT OBJECTIVE
To evaluate the implementation and effectiveness of the Management System for Certification
To evaluate the implementation and effectiveness of the Management System for extension of
scope/ change of site / addition of site.
To assess and verify the effectiveness of actions taken on the non conformances raised during
previous audit (Follow up Audit).
To evaluate the continued implementation and effectiveness of the Management System
(Recertification audit)
Transfer of certification
AUDIT CONDUCTED AGAINST
ISO 9001: 2015 ISO 14001: 2004:2015 OHSMS 45001:2018
M/s. ONGC Ltd, Assam Asset has documented & maintained the QHSE management system in line
with the requirements of ISO 9001:2015 for QMS, ISO 14001:2015 for EMS and OHSAS 18001:2007
for Health & Safety in their different locations (64nos), i.e. Drilling Services, Production units like GGS,
GCS, EPS etc., WORs, Logging, RCMT, Fire Services, Security Services to Supply the Crude Oil &
Natural Gas as Product to different Customers.
DR E 1400 I
3) Sand bag may be kept at landing platform (top
man escape device)
DR EV 2000 V
4) Canopy may be provided for fire extinguishers.
DR E 1400 VI
6) Canopy may be provided for fire extinguishers.
DR F (M) 6100 I
7) Dos and don'ts Portable board may be kept during
the rig building time.
CWS
8) Segregation of wastes may be done.
9) Oil spillages need to be cleaned in CT shop.
SDC
11) Fire extinguisher layout plan may be displayed.
DR E 2000 VI
12) Fire pump may be repaired at the earliest.
WOR IR 500 II
13) Oil Spillage at store may be cleaned.
RDS GGS I
14) Ambulance beacon light was not working properly.
RDS ETP
15) Leakage was found in the dispatch pump.
RDS GGS II
16) Scraped items may be kept in the designated
area.
17) Grass cutting may be done at the earliest
Logging
20) Proper Shelf may be provided for Fire
extinguishers.
21) Housekeeping at radiation area may be improved.
Fire Station-Geleky
25) Locations may be identified and indicated for
placing and hanging the fire extinguishers'
v) a statement on the conformity and the PLEASE PROVIDE DATES OF INTERNAL AUDIT
effectiveness of the management system AND MANAGEMENT REVIEW, INCLUDING DATES
together with a summary of the evidence AND EVIDENCES
relating to:
the capability of the management
system to meet applicable
requirements and expected outcomes;
the internal audit and management
review process
vi) a conclusion on the appropriateness of the Scope of Certification is appropriate
certification scope
vii) confirmation that the audit objectives have Yes, audit objectives have been fulfilled
been fulfilled
Opportunities for Improvement:
CORRECTIVE ACTION
You are required to take effective corrective actions which should be based on investigation of the root
cause for identified nonconformities. And take further actions as indicated below.
Send Corrective action plan within 10 days* of issue of this report. Please send evidence of
corrective action taken within 60 days from the last date of this audit.
Please communicate to Lead Auditor by email at:__________________Or by courier to Vexil office at
80-F, Kamla Nagar, Delhi 110 007.
* Note: When the certification expiration date is before 10 days for submission of corrective action plan,
the submission of corrective action plan and the agreement on time limits for correction & corrective
action to be implemented, shall be prior to the expiration of certification.
The verification of corrective actions shall be done by on-site verification of evidences of corrective
actions taken.
The verification of corrective actions shall be done by off-site verification of evidences of corrective
actions taken.
It is mandatory that all non conformities must be closed/ resolved within 90 days from the last date of
this audit.
AUDIT CONCLUSION
We are pleased to recommend Certification/Recertification/Restoration of Certification (See
Certification details below)
Recommend Certification/Recertification with condition (subject to effective resolution/closure of
identified non conformities – see corrective action box above)
Recommend Limited Follow up audit of ____ manday(s) to verify effectiveness of corrective
actions. (Dates for audit shall be mutually agreed subject to conditions stated above)
Recommend Complete re-audit.
Recommend Continuation of certification
Recommend Continuation of Certification with condition (subject to effective resolution/closure
of identified non conformities – see corrective action box above)
Nonconformance(s) indicate that you have failed to implement Management system on
continuous basis and continued validity of your certificate no(s). _________ is (are) at risk.
Recommend Extension/Reduction of scope/ Addition of site/ Deletion of site and re-issue of
certificate as indicated in certification details box
Recommend Suspension of certification {Certificate no.(s).____________} due to __________
Please note that In case of suspension, your certificate shall be temporarily invalid. You shall
take appropriate corrective actions within 120 days form the last day of this audit. Upon
verification of these actions your certificate will be reinstated in register of certified companies
NOTE:
1. Issue/Reissue of certificate is subject to taking effective Corrective Action on identified non-
conformities. It is mandatory that all nonconformities must be closed / resolved within 90 days from the
last date of this audit. Accordingly the recommendation shall be made.
2. The recommendation will be independently verified by Certification Decision Group of Vexil before
issue of Certificate.
Report number Report Date Lead Auditor Name
B-A022218 (I, II & III) 21 June 2021 Ranajit Bhattacharya
F1601(ii)C07 Page 7 of 9
Vexil Business Process Services Pvt. Ltd.
Management System Audit Report VE XIL
BP S
Client : Oil and Natural Gas Corporation Limited, Assam Asset
CERTIFICATION DETAILS
Reason for issue Recertification Audit
Client name Oil and Natural Gas Corporation Limited,
(as to appear in certificate)
Recommended Scope of Details at Annexure B
Certification:
Site Details
Site Site Address Site Activity
1 Details at Annexure B Details at Annexure B (Please add if there is
any new activity started at any location)
Billing Address Same as Above
Accreditation: JAS-ANZ NACE Code/IAF B06, B09.10, D35.2, H49.50, H52.10, (CA11.10,
Code: CA11.20, E 40.20, I 60.30, I 63.12 & L 75.14
according to NACE 1.1)/IAF02, 26 & 31
CEO/Head Mr. Sanjeev Kakrans, ED- Asset Manager
Additional Information – The audit will be conducted online due to COVID-19 pandemic.
SIGN OFF
This assessment is conducted according to the requirements of Vexil policies and procedures for the
assessment of Management Systems. The report is subject to review by authorized management
personnel of Vexil.
The contents of this report are confidential between the client and Vexil. No information contained
herein will be disclosed by Vexil to any third party except where required by a recognized accreditation
body in order to establish compliance with accreditation requirements.
The audit is conducted on random sampling basis. Nonconformities may exist in the system which may
not have been identified.
You are required to promptly inform Vexil about any intended changes to the Management or
other changes which may affect conformity to the Management System. This includes but not
limited to :
Vexil, on examination, shall take appropriate decision including additional visit, if necessary.
If you wish to distribute copies of this report to anyone outside the organization then complete report
must be distributed.
Please note that timely conduct of surveillance audits is one of the mandatory conditions for
continuation of certificate.
On completion of each three year cycle, a re-assessment of complete Management System, covering
all areas will be conducted. If found satisfactory, new certificate shall be issued.