Download as pdf or txt
Download as pdf or txt
You are on page 1of 50

Safety of chemical processes

3. Safety aspects during Project Engineering & Execution (Part 1)

Geert Vercruysse
Contents

Introduction

8 Safety functions

Layers of protection - Prevention

Atmospheric storage tank

Distillation column

SIL (Safety Integrity Level) &


LOPA (Layers of Protection Analysis)
Plant life cycle
• Different phases of project
 Study of project
 Basic engineering
 Detailed engineering
 Construction
 Commissioning and start up
 Closing of project
• Plant in operation
 Revision of safety study
 Renewal/revision permit – operating license
Introduction to example
Example: Large scale production of coating product
• Successful trial in R&D lab
• Copolymer of styrene and acrylic acid
• Reaction in presence of a solvent
• Final product in IBC’s* or drums
Raw materials:
• Acrylic acid & styrene as main raw materials
• Solvent storage (very small consumption)
• « Peroxide » as initiator
* IBC = International bulk container (1m3)
May 2019 Geert Vercruysse 4
Start of plant set up

20/12/2018 Geert Vercruysse 5


8 Safety functions for a chemical plant
1. Prevention of loss of containment due to process upsets
2. Prevention of loss of containment due to degradation
3. Limitation of the size of an accidental release
4. Control of spreading of substance accidentally released
5. Prevention of ignition of explosive atmospheres
6. Mitigation of damage due to fire
7. Mitigation of damage due to explosion
8. Mitigation of damage due to toxic release

20/12/2018 Geert Vercruysse 6


Layers of protection
M
I
T
I
G
A
T
I
O
N

P
R
E
V
E
N
T
I
O
N

20/12/2018 Geert Vercruysse 7


Safety critical items - Prevention
● Intrinsic safe design

● Mechanical protections:
 Safety valves

 Rupture discs

● Instrumentational protections:
 Interlocks and safeguarding systems

 Distinction between hard-wired and soft-wired interlocks (SIL classification)

● Organizational protections:
 Key interlocks

 Key arrangements

 Start up and shutdown procedures (spool pieces, spectacle blinds, etc.)

20/12/2018 Geert Vercruysse 8


Process safety study
• Process units to be further discussed:
 Atmospheric storage tank
 Destillation column
 Batch reactor

• Critical process parameters:


 Level
 Pressure
 Temperature
 Flow
 Composition

20/12/2018 Geert Vercruysse 9


Atmospheric storage tanks
• Hazards associated with atmospheric (ambient pressure to 2.5
psig) storage tanks:
 Overfilling

 Overpressure and vacuum

 Spills – tank rupture

 Fire

• To be investigated:
 Health hazards (toxicity)
 Flammability properties

 Conductivity (static electricity)

20/12/2018 Geert Vercruysse 10


Atmospheric storage tanks
• Which type of qualitative method to be used?
Safety review / checklist is sufficient.

 In case of raw materials as described in the example, safety


aspects of acrylic acid and styrene are well known.

 General standards and design guidelines exist and can be


applied as “start” for design review.

• Safety concept for import via truck/train is different from


concept for import via pipeline.

20/12/2018 Geert Vercruysse 11


Atmospheric storage tanks

20/12/2018 Geert Vercruysse 12


Atmospheric storage tanks
How to assess level / prevent overflowing
• Logistic departement:
 Manufacturing Resource Planning (MRP) for truck deliveries.

 Once truck has arrived - control of Certificate of Analysis (CoA).

 Procedure to guarantee that the right tank will be connected


with the truck.

• “What if” normal level measurement is failing


 Foresee level high interlock.

 Independent level high interlock which stops unloading pump and


closes automatic valve.

20/12/2018 Geert Vercruysse 13


Atmospheric storage tanks

20/12/2018 Geert Vercruysse 14


Atmospheric storage tanks
Pressure / prevent overpressure and vacuum
• Overpressure:
 Unloading in tank and pressure controller is not functioning

 Excessive vapor generation (deviation of temperature)

• Vacuum:
 Pumping out of tank and pressure controller is not functioning

 Sudden temperature drop (weather conditions)

• Prevention:
 Pressure control + breather valve

20/12/2018 Geert Vercruysse 15


Atmospheric storage tanks
Composition / prevent internal deflagration
• Causes:
 Presence of a flammable / air mixture in the presence of an iginition
source.

• Prevention:
 Collect information: conductivity of fluid & flash point.

 Pay attention to type of filling (prevent splashing) e.g. foresee dip


pipe.

 Inerting of gas volume by nitrogen; in case of acrylic acid with lean


air (in order to keep polymerization inhibitor active).

20/12/2018 Geert Vercruysse 16


Atmospheric storage tanks

20/12/2018 Geert Vercruysse 17


Distillation column

20/12/2018 Geert Vercruysse 18


Distillation column
• As the technology is energy intensive there is a strong
focus on the overpressure protection.

• This means that when a failure occurs the design


conditions (pressure/temperature) should not be exceeded.

• Which type of qualitative method to be used?


Cause / consequence analysis.

• In the next slide some generic failures are presented which


should be included in the hazard evaluation technique of
each distillation column or similar unit.

20/12/2018 Geert Vercruysse 19


Process safety – Generic scenarios

20/12/2018 Geert Vercruysse 20


Distillation column - Overpressure protection
Intrinsic safe Mechanical Safety Concept Instrumental Safety Concept

Flare Flare Flare Atmosphere

PSH

PSH

“NA” “OPEN” “CLOSE” “CLOSE”

Design Design Design Design


Intrinsic Safe Relief valve SIL-interlock SIL-interlock

20/12/2018 Geert Vercruysse 21


Mechanical safety concept
• Relief devices are usually designed to protect the
equipment and auxiliaries from overpressure due to any
single cause.

• The probability of two unrelated failures occurring


simultaneously is considered remote and is not normally
designed for.

• API RP 521 defines causes to be unrelated if no process,


mechanical or electrical linkages exist among them.

API RP = American Petroleum Institute Recommended Practice


20/12/2018 Geert Vercruysse 22
Mechanical safety concept

20/12/2018 Geert Vercruysse 23


Mechanical safety concept
Size of relief device must be carefully examined:
• Consequences of undersizing are obvious.
• However, grossly oversizing is no guarantee for proper protection:
 Excessive discharges, with a potential to lower discharge rates:
Excessive vapor flows may cause flooding and gas lifting of the liquid
resulting in a liquid discharge into the relief header and possible
damage to column internals.

 This can be calculated within a design program: gas velocity for


flooding, arising pressure drop capable of lifting internals.

 Expensive.

20/12/2018 Geert Vercruysse 24


Instrumentational safety concept
• Safety instrumented functions are usually designed to protect the
equipment and auxillaries from overpressure due to different
type of causes.

• IEC 61511* is the guideline used in EMEA.

• Specific engineering concepts:


 Functional safety – the complete set up from sensor till actor is
described.

 “Voting systems” 1oo1, 1oo2, 2oo3, …

 Complexity requires on line testing – calibration.


*Standard IEC 61511 « Functional safety – Safety instrumented systems for the process industry sector »
20/12/2018 Geert Vercruysse 25
Instrumentational safety concept
Some definitions
Abbreviation Full expression

BPCS Basic process control system

SIF Safety instrumented function

SIL Safety integrity level

SIS Safety instrumented system

SRS Safety requirement specification

20/12/2018 Geert Vercruysse 26


Instrumentational safety concept
SIL
Safety Demand mode Continuous mode Consequence of a
integrity « Low demand mode » « High demand mode » failure
level
Level Availability Probability of a Probability of a dangerous
failure on demand. failure per hour.

Potential for fatalities


SIL 4 >99,99% ≥10-5 to < 10-4 ≥10-9 to < 10-8
in the community.
Potential for multiple
SIL 3 99,9% ≥10-4 to < 10-3 ≥10-8 to < 10-7
fatalities.
Potential for major
SIL 2 99%-99,9% ≥10-3 to < 10-2 ≥10-7 to < 10-6
injuries or one fatality.
Potential for minor
SIL 1 90%-90% ≥10-2 to < 10-1 ≥10-6 to < 10-5
injuries.

SIL 0 No requirement N/A

20/12/2018 Geert Vercruysse 27


Instrumentational safety concept
SIL

20/12/2018 Geert Vercruysse 28


LOPA - Overview
COMMUNITY EMERGENCY RESPONSE

PLANT EMERGENCY RESPONSE

PHYSICAL PROTECTION (DIKES)

PHYSICAL PROTECTION (RELIEF DEVICES)

AUTOMATIC ACTION Safety Instrumented System


OR Electronic Shutdown system

CRITICAL ALARMS, OPERATOR SUPERVISION,


AND MANUAL INTERVENTION

BASIC CONTROLS, PROCESS ALARMS,


AND OPERATOR SUPERVISION
PROCESS
DESIGN
I

LAH
1

20/12/2018 Geert Vercruysse 29


LOPA - Introduction
Layer of protection analysis (LOPA) is a semiquantitative
tool for analyzing and assessing risk.

KEY QUESTIONS FOR PROTECTION LAYERS

• How safe is safe enough?

• How many protection layers are needed?

• How much risk reduction should each layer provide?

20/12/2018 Geert Vercruysse 30


LOPA - Definition

LOPA has its origins in the desire to answer these key


questions using a rational, objective, risk-based approach.

In LOPA, the independent protection layers (IPL) proposed or


provided are analyzed for their effectiveness. The combined
effects of the protection layers are then compared against
risk tolerance criteria.

20/12/2018 Geert Vercruysse 31


Distillation column – P&ID

20/12/2018 Geert Vercruysse 32


Distillation column - PHA
Project name: Date: Page of
Process : Steamcracker
Section: C3/C4 Splitter K5001 Reference drawing: P&ID xx1 till P&ID xx4

Study Process Deviations Possible


Item Possible consequences Safeguards Type IPL
node parameters (guide words) causes

Overpressurizing of K5001
Pdesign is 9.5 bar Design Y5001/02/30 is based on
Loss of
Column worst case scenario, i.e. closed
Pressure High cooling Y 10-2
K5001 Risk matrix resulting in a outlet or loss of condenser.
water
target factor of 10-3

Minimum selector on reboiler


controller will limit hot water flow to BPCS_1 10-1
reboiler W5001.

As column pressure further


increases, PVP5004 (SPHH
BPCS_2 10-1
controller) will take over. Part of top
product will be directed to flare.

Total 10-3

20/12/2018 Geert Vercruysse 33


Distillation column – Layers of protection

20/12/2018 Geert Vercruysse 34


Distillation column - PHA
Project name: Date: Page of
Process : Steamcracker
Section: C3/C4 Splitter K5001 Reference drawing: P&ID xx1 till P&ID xx4

Study Process Deviations Possible


Item Possible consequences Safeguards Type IPL
node parameters (guide words) causes

Overpressurizing of K5001
Gas
Pdesign is 9.5 bar Design Y5001/02/30 is based on
breakthrough
Column worst case scenario, i.e. closed
Pressure High from previous Y 10-2
K5001 Risk matrix resulting in a outlet or loss of condenser.
column
target factor of 10-3
C2/C3 splitter

Minimum selector on reboiler


controller will limit hot water flow to BPCS_1 10-1
reboiler W5001.

As column pressure further


increases, PVP5004 (SPHH
BPCS_2 10-1
controller) will take over. Part of top
product will be directed to flare.

Total 10-3

20/12/2018 Geert Vercruysse 35


Distillation column - PHA
Project name: Date: Page of
Process : Steamcracker
Section: C3/C4 Splitter K5001 Reference drawing: P&ID xx1 till P&ID xx4

Study Process Deviations Possible


Item Possible consequences Safeguards Type IPL
node parameters (guide words) causes

Overpressurizing of K5001
Pdesign is 9.5 bar Design Y5001/02/30 is based on worst
Column Maximum case scenario, i.e. closed outlet or loss
Pressure High Y 10-2
K5001 heat input Risk matrix resulting in a of condenser.
target factor of 10-3

As column pressure further increases,


PVP5004 (SPHH controller) will take
BPCS 10-1
over. Part of top product will be directed
to flare.

Total 10-3

20/12/2018 Geert Vercruysse 36


Distillation column - PHA
Project name: Date: Page of
Process : Steamcracker
Section: C3/C4 Splitter K5001 Reference drawing: P&ID xx1 till P&ID xx4

Study Process Deviations (guide Possible


Item Possible consequences Safeguards Type IPL
node parameters words) causes

Overpressurizing of K5001
Pdesign is 9.5 bar Design Y5001/02/30 is based on worst
Column case scenario, i.e. closed outlet or loss
Pressure High Fire Y 10-2
K5001 Risk matrix resulting in a of condensor.
target factor of 10-2

Total 10-2

20/12/2018 Geert Vercruysse 37


Distillation column – « Other » safety concept

20/12/2018 Geert Vercruysse 38


Distillation column – Other scenarios
Other scenarios to be discussed in a similar way:

• Deviation composition feed due to disturbance in previous column


and/or reactor conditions upset.

• Too much flow (feed)or reflux will lead to an hydraulic overload in the
column = flooding regime. If not properly handled this will lead to
damage of the internals and in the worst case to a possible liquid relief
via safety valve.

• Temperature deviations will mostly be handled by pressure protection


as distillation is a typical boiling process.

• API guidelines how to deal with internal leakage in heat exchangers.

• Reflux pump - general pump protection concept is applicable.

20/12/2018 Geert Vercruysse 39


Pump protection – Blocked pump
M

blocked suction side


(early cavitation)

blocked
discharge side
M

• Usually, an intolerable pressure increase will not apply.


• The liquid temperature in the pump can climb to the boiling point. This might
lead to comparably slight damage.
• A higher hazard has to be considered with regard to substances that can
decompose. As for the case of a completely blocked-in pump, the increasing
temperature could lead to an explosive energy release at the Onset
Temperature Point.
20/12/2018 Geert Vercruysse 40
Pump protection - Countermeasures

20/12/2018 Geert Vercruysse 41


Pump protection - Countermeasures

20/12/2018 Geert Vercruysse 42


Back up

20/12/2018 Geert Vercruysse 43


Inherent Safer Design (ISD)
• An inherently safer design avoids hazards instead of
controlling them
• Strategy:
 Minimize

 Substitute

 Moderate

 Simplify (KISS “keep it safe and simple”)

20/12/2018 Geert Vercruysse 44


Inherent Safer Design
• Minimize: Reduce the inventory of hazardous materials.
• Methods:
 Storing smaller amounts of material
 Reducing the size of equipment
 Intensify the processes
• Examples (non-exhaustive list):
 Replace batch process by continuous one
 Replace stirred tank reactors by tubular ones
 Add reactants continuously to a batch reactor
 Intensify reactions (use catalysts, ultrasound, lasers)
 Intensify mass transfer (spinning disk reactor, jet reactor and other
strong mixing devices).
 …
20/12/2018 Geert Vercruysse 45
Inherent Safer Design
• Minimize

20/12/2018 Geert Vercruysse 46


Inherent Safer Design
• Substitute:
Substitute hazardous materials by less hazardous materials.

• Examples (non-exhaustive list):


 Physical agents in reactors, separation processes, utilities and
other applications: refrigerants, thermal fluids, degreasing agents,
solvents, foaming agents…

 Chemical reactions: different reaction routes to have less


hazardous reagents or intermediates.

 Change the physical process (e.g. separation method) to use less


hazardous materials

20/12/2018 Geert Vercruysse 47


Inherent Safer Design
Substitute

20/12/2018 Geert Vercruysse 48


Inherent Safer Design
• Moderate:
Reduce risks by moderating conditions (attenuation)
• Methods:
Less extreme conditions; less hazardous form of the material;
facilities that attenuate/minimize consequences of process
deviations
• Examples (non-exhaustive list):
 Reduce high pressure, high vacuum, high temperature, high
concentration.
 For particle processing: use larger particles or replace by slurry
processing.
 Work in gas phase rather than in the liquid one.
 Moderate potential damage by proper plant location and layout.
 To liquify gases: use cooling rather than compression.
20/12/2018 Geert Vercruysse 49
Inherent Safer Design
• Simplify:
Reduce complexities that increase probability of failure/leakage and
opportunities for errors/mistakes.

• Methods:
 Dedicated rather than multipurpose plants or items.

 Single stream rather than multiple streams.

 Simple and clear procedures.

20/12/2018 Geert Vercruysse 50

You might also like