Conveyance Charges of Material – Common SoR 2023-24

CONVEYANCE CHARGES OF MATERIALS AS PER SoR 2023-24 (COMMON TO ALL


DEPARTMENTS).

LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS


FOR THE YEAR: 2023-24

1. For total lead up to 150 m (including initial lead) lead charges by head load only shall be
adopted irrespective of mode of conveyance.
2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted
irrespective of mode of conveyance.
3. The rates for loading at quarry including idle hire charges of trucks and hire charges per
for each kilometer and up to 5 km are cumulative and inclusive of total charges for
Preceding lead.
4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and
Stones are for loose volume and not for compacted or in-situ volume.
5. The rates for lift charges, lead charges, hire charges are cumulative and inclusive of rates
for preceding lift, lead and hire charges.
6. Lift charges are not payable where conveyance of materials is by mechanical means to
final placing point.
7. Loading and unloading charges are not payable for conveyance by head load.
8. Loading charges are not payable for conveyance by mechanical means for disposal of
excavated materials beyond initial lead of 50 m wherever specified.
9. Loading and unloading charges are not payable for conveyance by mechanical means
for disposal of excavated materials beyond initial lead of 1 km wherever specified.
10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble,
size stone and cut stone are inclusive of stacking.
11. Hire charges are per 1KM for tippers and trucks for transport of materials from work site
to dump yard and other places are cumulative& includes previous km up to 5 kms
12. The lead & lift charges are exclusive of contractor's profit and overhead charges of
13.615%
13. The loading and unloading charges are also exclusive of Contractor's profit and
overhead charges of 13.615%
14. During the BoCEs meeting held on 10.06.2015,the BoCEs has recommended to withdraw
lead charges, loading and unloading charges for Cement as per the minutes of meeting
of Sub-Committee held on 29.06.2015.(The conveyance charges ,loading & unloading
charges for cement are displayed for information purpose only).
15. As per the BOCE meeting held on 21.08.2019 in order to simplify the procedure of
adding lead charges to the data items in the CFMS work module, the BOCE
recommended to delete the contractor profit and over head charges from the calculation
of Lead, Lift, Loading and Unloading charges. But at the time of preparation of estimates
the contractor profit and over head charges on Lead, Lift, Loading and Unloading
charges shall be added as usual.