MS of Haul Road For Hotel 11
MS of Haul Road For Hotel 11
MS of Haul Road For Hotel 11
Document No :
Revision : 01
中国港湾工程沙特阿拉伯有限责任公司
China Harbour Engineering Arabia Co. Ltd.
Table of Contents
Contents
1 INTRODUCTION..................................................................................................................4
2 PURPOSE............................................................................................................................4
3 SCOPE OF WORK...............................................................................................................5
4 RESOURCES.......................................................................................................................5
4.2 Manpower...................................................................................................................5
4.3 Materials.....................................................................................................................6
5 REFERENCES.....................................................................................................................6
7.6 QC Inspector..............................................................................................................8
7.7 Surveyor.....................................................................................................................8
8 METHODOLOGY...............................................................................................................15
10 QUALITY ASSURANCE...................................................................................................24
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 4/24
TRSDC Ref. No.: R 1 2 -
1 INTRODUCTION
The haul road will be built on UAS 9-3 islands to facilitate construction materials,
manpower, and equipment movements.Including 2 kinds of haul road, Primary
Construction Haul Road 8M Wide (2 Ways) and Secondary Construction Haul Road
7M Wide (1 Way ).The haul road map is shown in the Fig1-1.
2 PURPOSE
The purpose of this method statement is to explain haul road layout, section form
and construction method of UAS 9-3 islands.
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 5/24
TRSDC Ref. No.: R 1 2 -
3 SCOPE OF WORK
As per TRSDC’s requirement, there are 2 types of haul roads. One is primary haul
road with 8m wide, the other is secondary haul road with 7m wide.
The road section will only compose compacted sand as per TRSDC’s requirement.
The sidewalk will be included in the 8m wide road and 7m wide road, which means
that 8m wide primary haul road , 7m wide secondary haul road . This scope of
works comprises the following activity:
Compacting and levelling the existing soil, the compaction degree should
meet design requirement.
Construct barricades.
4 RESOURCES
4.1 Main Construction Equipment’s
All plant to be fit for purpose, checked and certified prior to commencement of
works.
4.2 Manpower
Table: 4.2 -1 Manpower’s
Sr No Description Quantity Remarks
4.3 Materials
5 REFERENCES
This project shall be designed and implemented in accordance with the latest
revision of applicable drawings.
1. Employers Requirement;
2. Design Documentation Requirements;
3. Contractual Requirement;
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 7/24
TRSDC Ref. No.: R 1 2 -
Organization Chart
7.1 Project Director has overall responsibility for the implementation of this project
procedure. Specific responsibilities have been assigned to members of the project
management team as described below.
7.2 Construction Director through his civil execution team is responsible for
executing the work as per the approved drawings, safe work excursion on site,
promoting the ridership towards HSE commitments and within the approved quality
procedure as per contract. He shall plan and resource site construction facilities and
ensure safety programs. Construction director will act as a construction manager.
7.3 Site Manager the core duties that must be executed by a site manager is to
oversee and direct the activities of a range of contractors and subcontractors which
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 8/24
TRSDC Ref. No.: R 1 2 -
may begin with site preparation work to the final stages of the particular construction
project. Preparing, coordinating, and updating site reports, drawings, and other
necessary documents.
7.4 Site Engineer shall report to the CM and are responsible for the day to day
planning and supervision as well as implementing the technical requirements,
dimensions, and measurements related to the execution of work and equipment
preparation.
7.5 QA/QC Manager shall monitor all QA/QC activities for all disciplines needed in the
project. Set up the Quality Systems onsite and ensure Quality Assurance Plans and
Procedures are implemented as per TRSDC Standard Specification and
International Standard requirements. Supervises multidiscipline team of QC
Engineers or inspectors onsite and perform quality audits. He reports directly to the
Quality Director and Project Manager.
7.6 QC Inspector shall monitor all the ongoing activities and will make sure that work
is being done as per the approved Method Statement, IFC and approved shop
drawings, He will make sure that material being used in the site is approved and
received by ARCADIS.
7.7 Surveyor shall report to the CM and Site Engineers, also responsible in
determining the precise location, distances, directions and elevation of points, lines
and contours of important features in the survey area. Records the results of
surveys and verify the accuracy of data, prepares plots for documentation.
7.8 HSE Manager shall report to the Project manager, shall have the following
responsibilities as a minimum.
7.9 Safety Supervisor shall report to the Project HSE manager, shall visibly
demonstrate the priority of safety in all activities, including setting a good personal
example and as follows.
To be conversant with the Client contractual requirements, HSE
Specifications/Standards and applicable laws.
Report directly to client HSE Lead on all matters relating to Health / Safety /
Environment.
To conduct training and counselling sessions on group and individual basis
and lead the process of passing on safety information to the work force
through HSE Officers / safety supervisors or site Supervisors.
To participate/ conduct emergency response drills, provide scenarios for the
monthly emergency drills, exercises.
To attend, participate in the supervisors HSE meeting, keep records of the
meeting and monitor implementations of action points.
To suspend immediately any work in progress which he considers being
proceeding in a dangerous or unsafe manner.
To monitor and report on the any ignorance of the rules and regulations set
out in CHEAEC and RED SEA safety reference documents.
To ensure that the HSE training given to staff is of sufficient with efficient
quality material for regular tool box talks.
Conduct HSE Inspections and Audits to ensure that adequate controls are in
place to prevent injury to personnel, damage to plant equipment, and
minimum damage to environment.
Participate in Client’s HSE Contractor meetings, when required.
Ensure that unsafe acts and unsafe conditions are reported and corrected.
To prepare inspection & statistics reports of all incidents/injuries and damage
at the site as per contractual requirements by proper investigation and
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 11/24
TRSDC Ref. No.: R 1 2 -
promote action to prevent recurrence. Besides, maintain and keep all records
relevant to HSE matters.
Act as Focal Point for HSE management of Contract.
7.10 HSE Officer
Familiar With the requirements set out in the project ESIA and the CEMP.
Fully responsible to implement Project CESMP.
Accountable to the Project Manager and is responsible for the implementation
of the Project “Environment Management Plan”.
To ensure that the Environmental Compliance supervisors have adequate
resources to carry out their duties and responsibilities to implement the Project
“Environment Management Plan”.
To establish and maintain a direct line of communication with the CHEC HSE
Representative, Engineer/Supervisor.
To chair the Environmental compliance meetings.
To monitor the site operation to ensure they are conducted in accordance with
the Project “Environment Management Plan”. Take urgent and appropriate
action to prevent unsafe working practices or other infringements of statutory
requirements.
To make himself available to participate in some of the Environment
inspections.
To ensure that CHEAEC and all subcontractors comply with the requirements
of the Project “Environment Management Plan”.
To ensure that all necessary Written Safe Work Procedures, Risk Assessment
sand Method Statements are prepared and issued for safe operation of the
works on the Project.
To ensure that the CESMP and their EMS is established, implemented and
maintained in accordance with the requirements of the CESMP and other legal
requirements.
The EMS shall identify.
Risks associated with their activities.
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 13/24
TRSDC Ref. No.: R 1 2 -
Familiar With the requirements set out in the project ESIA and the CESMP.
Fully responsible to implement Project CESMP.
Responsible for the implementation of the Project “Environment Management
Plan”.
Lead Environmental compliance at project site.
To monitor the site operation to ensure they are conducted in accordance with
the Project “Environment Management Plan”. Take urgent and appropriate
action to prevent unsafe working practices or other infringements of statutory
requirements.
Lead Daily Environment inspections to ensure that CHEAC and all
subcontractors comply with the requirements of the Project “Environment
Management Plan”.
Appropriate monitoring to ascertain compliance with relevant legislation,
standards, guidelines and guidelines.
To record all environmental incidents and social issues, including complaints
and grievances from local communities or other interested parties; and
To attend the weekly environmental performance meeting.
Will lead Environmental Awareness programs and Training Programs for the
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 15/24
TRSDC Ref. No.: R 1 2 -
construction staff.
Will be responsible for preparation of Daily Environmental Monitoring Reports.
7.13 Site Supervisor / Foreman
8 METHODOLOGY
8.1 Materials Taking
In the areas designated by the employer, excavator are used for loading and dump
trucks are used to transport backfilling materials to designated locations during
temporary road construction.
Before paving sand, grader will be used to level the original ground without reducing
the elevation. After ground leveling, the material will be one time backfilled (after
compaction thickness is 25cm), and grader or loader will be used for placement .
A water truck will be used to spray water until it is completely wet , then the roller
will come to do compaction . The compaction should meet the design requirements.
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 16/24
TRSDC Ref. No.: R 1 2 -
The sidewalk only be included in the 7m wide road , which means that 7m wide
secondary haul road (5.5m wide + 1.5m wide sidewalk).
CHEAC will monitor and maintenance the access roads till R10-H11 project
completed.
The Typical haul road section is shown in the Fig8.6-1 and Fig8.6-2
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 17/24
TRSDC Ref. No.: R 1 2 -
CHEAC will perform plate load test to confirm the ground service bearing capacity meets
the requirement.
(1) Pay attention to Oil spillage from equipment, check the equipment every day
before work starts, ensuring the equipment can work properly.
HOTEL 10, 11 & 12 DOCUMENT
PILING AND Method statement of Haul NUMBER
FOUNDATION Road for Hotel 11
PACKAGE REVISION 01
ISSUED BY CHEAC ISSUED DATE 14-JUN-24 PAGE 24/24
TRSDC Ref. No.: R 1 2 -
(2) All works associated with construction shall occur within the defined works area.
(3) AII personnel involved should wear complete personal protective equipment
(PPE) in accordance with safe work requirements.
(4) All the work shall comply with the approved safety management plan. Risk
assessment will be submitted for approval before work commence.
(5) If the weather condition turns bad, (sand storms, wind storms, rains, flooding
and hailstorms), there should be immediate coordination with CHEAC Safety
Department and Construction Management in cases where the works will be
stopped. If in case night observation or monitoring is necessary to be carried out,
adequate lighting must be prepared by the Construction Manager.
(6)Pedestrians isolation during construction: During temporary road construction, all
construction areas need to be safely enclosed with tapered buckets and warning
tape, accompanied by safety personnel. Flashing lights are used as a warning
during night construction.
10 QUALITY ASSURANCE
Before the commencement of the work, QC Inspector will check the site condition.
Site clearance and preparation will depend on the site conditions. All the materials to
be inspected before the installation.