Professional Documents
Culture Documents
Optimal Economic Dispatch in Power System
Optimal Economic Dispatch in Power System
1
OPTIMAL ECONOMIC DISPATCH IN
POWER SYSTEM
Mohamad Aminuddin Bin Abd Mutalib, Alia Karmila Binti Mohd Nazlan,
Muhammad Syafiq Aiman Bin Mazlan, Noor Safwanah Binti Mohd Zin,
1.1 ABSTRACT
The operational efficiency of the power grid relies heavily on the functionalities of the control
center, notably Economic Dispatch (ED). ED represents a comprehensive optimization process
conducted by system operators to ensure a balanced supply-load equilibrium while upholding
reliability constraints. This case study endeavors to identify the optimal ED and total cost across
various scenarios, taking into account transmission line capacities and generator output
constraints. A notable factor in the analysis is the inherent unpredictability of Large Scale Solar
(LSS) output power, influenced by site conditions and the absence of storage facilities. Utilizing
Power World software, a 132kV network simulation is performed with three generators, two LSS
units, and connected loads. The study further explores different transmission line distances for
each case, aiming to draw meaningful conclusions and recommend optimal solutions. The
findings from this investigation contribute valuable insights to enhance the operational efficiency
and decision-making processes within the power grid infrastructure.
Power System Control | SEEE4453 | SET 1 | Group 1
1.2 INTRODUCTION
Economic dispatch, denoted as ED, is the process of distributing the entire load on a system
among the different generating plants in order to maximize operational economy [1]. In other
words, as a way to reduce fuel costs while satisfying system constraints, economic dispatch
organized the outputs of all available generation units in a power system.
Next, power economic dispatch's main goal is to minimize the total operating cost of a system by
determining the overall output of power generation across its various generating units. This
involves coordinating the output schedule of the committed generating units to meet the
necessary load demand at the lowest possible operating cost and following different restrictions
on equality and inequality both inside the units and throughout the system. In addition to cost
minimization, other objectives are considered to enhance the sustainability and profitability of
the power system. These include the minimization of emissions, such as SO2, NOx, CO, and
CO2, generated by thermal power plants, contributing to environmental considerations. Profit
maximization is another critical aspect, which is accomplished by lowering the total costs
associated with power generation. Furthermore, sustaining system stability and security
constraints is critical to ensuring the power system's reliability and resilience [3].
In the realm of contemporary power systems, the integration of renewable energy sources
alongside conventional generators introduces new challenges and opportunities for optimizing
economic dispatch. This report focuses on the economic dispatch of a 275kV network
comprising three generators and two large-scale solar (LSS) installations.
The primary goal of this study is to determine the optimal economic dispatch while adhering to
transmission line capacity constraints and respecting the minimum and maximum output limits
of the generators. It's important to note that the LSS units, driven by uncontrollable variations in
solar irradiance and lacking energy storage, add a layer of complexity to the economic dispatch
problem.
The specific cases under examination include various load and Large-Scale Solar (LSS) unit
output configurations. Scenarios range from full load with no LSS 1 & 2 output to 50% load with
various LSS output levels. These diverse cases assess the economic dispatch capabilities of the
275kV network while considering the uncontrollable nature of LSS output due to solar irradiance
and lack of energy storage. The analysis aims to identify optimal economic dispatch solutions,
ensuring compliance with transmission line capacity constraints and generator output limits. This
exploration is crucial for determining effective and reliable solutions in this intricate network
configuration.
Power System Control | SEEE4453 | SET 1 | Group 1
2.0 METHODOLOGY
Based on source online guidance, we learned how to use the PowerWorld Simulator for optimal
economic dispatch load with given parameters.
1 200 100 20 10
2 250 125 30 15
3 450 225 80 40
4 250 125 60 30
Power System Control | SEEE4453 | SET 1 | Group 1
2 50 0.90 25 1200
2. Make sure you are in ‘Edit Mode’ and under the ‘Draw’ tab, click ‘Network’, choose ‘Bus’.
3. A new window will pop up. Rename ‘1’ in the ‘Bus Name’ box field to ‘Bus 1’ and set
the value for nominal voltage to 275kV in ‘Nominal Voltage’ field.
5. Under the ‘Power and Voltage Control’ tab, insert minimum and maximum value for the
generator. Insert the setpoint as minimum power or any value within the range. Set the
generator MVA base as 100 MVA.
6. Under ‘Cost’ tab → ‘Cost Model’, tick Cubic Cost Model and insert the value for:
Power System Control | SEEE4453 | SET 1 | Group 1
8. Insert the MW value and MVar value for the load under constant power.
Power System Control | SEEE4453 | SET 1 | Group 1
9. For the LSS generator, repeat step 4 and a window will open. Under the ‘Power and
Voltage Control’ → Voltage Control → Mode → Constant Power Factor, change the
power factor to 0.95 for LSS 1 and 0.9 for LSS 2. Under the ‘Power and Voltage Control’
→ Power Control, insert the setpoint as the parameters given.
10. Under the ‘Cost’ tab, insert the cost for ‘Variable O&M (RM/MWh).
11. Change the symbol and color of the LSS under ‘Display Information’.
Power System Control | SEEE4453 | SET 1 | Group 1
12. To display AGC status for each generator, click Field → Generator Field and click a
generator. A window will pop up as in figure 2.13, tick ‘Gen AGC Status’ and click
‘OK’.
13. To activate the economic dispatch mode to perform optimal dispatch of generators. Go to
Case Information → Aggregation → Area. Change the OFF AGC mode to ED mode.
Power System Control | SEEE4453 | SET 1 | Group 1
14. To display total hourly cost, go to Field → Area Field and click anywhere on the drawing
area.
16. To display total load, repeat step 13 and the same window as in figure 2.17 will pop up
but tick ‘MW Load’.
17. To display incremental cost, repeat step 13 and the same window as in figure 2.17 will
pop up but tick ‘Select a Field’ and choose OPF\Lambda.
Power System Control | SEEE4453 | SET 1 | Group 1
18. To insert text, go to Background → Text and click anywhere on the drawing area. A
window will pop up as in figure 2.20, enter a text and click ‘OK’.
19. To insert a transmission line, repeat step 2 and choose ‘Transmission Line’.
20. Under the ‘Geography’ tab, enter the line length under km field and save.
22. Under the ‘Length Units’, tick kilometers. Insert impedances per distance value as in
Table 2.2 under ‘Actual Impedance and Current Limits’. Finally, enter the value of max
MVA capacity under ‘Per Unit Impedance and MVA Limits’ → ‘Limit A (MVA)’.
23. To display power flow through the transmission line, go to Field → transmission Line
Field and click on any transmission line.
24. A window will appear and click ‘OK’.
To identify the optimal economic dispatch and total cost based on the following cases as
well as does not violate the transmission line capacity and generator minimum and maximum
output, we have studied through video tutorials on online sources. Also, the results obtained and
the best solution for results were analyzed.
b) Full Load as per Table 4 with full output from LSS 1 only
Power System Control | SEEE4453 | SET 1 | Group 1
c) Full Load as per Table 4 with 50% output from LSS 1 only
d) 50% Load as per Table 4 with full output from LSS 1 only
Power System Control | SEEE4453 | SET 1 | Group 1
e) 50% Load as per Table 4 with 50% output from LSS 1 only
f) Full Load as per Table 4 with full output from LSS 2 only
Power System Control | SEEE4453 | SET 1 | Group 1
g) Full Load as per Table 4 with 50% output from LSS 2 only
h) 50% Load as per Table 4 with full output from LSS 2 only
Power System Control | SEEE4453 | SET 1 | Group 1
i) 50% Load as per Table 4 with 50% output from LSS 2 only
j) Full Load as per Table 4 with full output from LSS 1 & 2
Power System Control | SEEE4453 | SET 1 | Group 1
k) Full Load as per Table 4 with 50% output from LSS 1 & 2
l) 50% Load as per Table 4 with full output from LSS 1 & 2
Power System Control | SEEE4453 | SET 1 | Group 1
m) 50% Load as per Table 4 with 50% output from LSS 1 & 2
Table 3.1: Simulation results for full loads and 50% of load condition.
50 % Load Condition
From observation in Table 3.1, The additional cost is significantly smaller as compared to
the full load and 50% load states. This is due to the situations when LSS 1 and LSS 2 are fully
operational. The data demonstrate that the highest price is seen when LSS 1 and LSS 2 do not
produce. The electricity generated will be sold to the grid. Higher returns can be obtained by
selling more on-site generated electricity to the grid. Without both LSS, the generator must run at
full capacity to meet the system's demands. When both LSS 1 and LSS 2 are fully utilized, it will
be one of the causes contributing to the price being much lower. This is also tolerable if the cost
of the full output from LSS 1 alone is significantly less than the cost of the 50% output from LSS
1. It is nearly impossible to control because there is no storage and the LSS output power is
dependent on the availability of a sunlight source.
Furthermore, all of the generators' values are between the minimum and maximum
requirements. As a result, the simulation circuits do not go over the generator limit. Overloads
are discovered under full load conditions throughout the simulation. Overload problems are
taken into account when the MW of the transmission line exceeds 100%. An overload can occur
in real life due to a lack of reactive power, a limit on the amount of power that can be generated,
a limit on the capacity of transmission lines or transformers, a supply disruption, and etc [2]. If
nothing changes, blackouts, destabilization, and cascade outages may occur [4]. This can also
increase load demand, which raises the cost. Overload problems can be solved in a variety of
methods, including the addition of parallel transmission lines, parallel generators to the main
generators, distribution generators near severely laden equipment, and parallel distribution
transformers to replace old equipment [2].
To obtain the highest economic dispatch, these overload issues must be resolved. As part
of the suggested options, three more transmission lines—TL1, TL3, and TL5—are to be built in
parallel with the overloaded line, as well as the addition of a second generator at bus 4 due to its
Power System Control | SEEE4453 | SET 1 | Group 1
greater load value. The results of simulating these two approaches are displayed in the table
below.
Table 3.2: Simulation results after adding transmission line with full load condition and 50%
load condition.
50 % Load Condition
Table 3.3: Simulation results after adding generator at bus 4 with full load condition and 50%
load condition.
50 % Load Condition
In method 1, the transmission line can then be used to prevent the base circuit from overflowing.
Parallel to the TL1, TL3, and TL5, three transmission lines have been added. This is because
these three specific lines experience the most overload. The figures in table 3.3 show that while
the total load decreases, the overall price for a 50% load is much cheaper than the price for a full
load. The cost is highest when LSS 1 and 2 do not have any output. The cost is lowest when they
generate all of their production. The sole difference is the modification of absence overload
conditions.
A 325 MW generator has been added at bus 4, according to Method 2. Following the inclusion of
a generator, it has been proved that the circuit does not overflow under full load conditions.
Power System Control | SEEE4453 | SET 1 | Group 1
Reading data at the base circuit, on the other hand, is far better for situations with half load.
Since the load decreases to 50%, the price is much less than the price for a full load.
Two techniques to bypass the overflow circuit were simulated, and both were successful in
removing overload problems while keeping generator constraints. Furthermore, the technique of
adding an additional generator at bus 4 has the best outcomes when compared to building three
new transmission lines and has a lower incremental cost when compared to method 1.
The total hourly cost and incremental cost for method 2 at full load conditions with full output
from LSS 1 & 2 are 32103.14 RM/h and 29.62 RM/MWh, respectively. It is significantly less
expensive than method 1, where the total hourly cost is 43477.74 RM/h and the incremental cost
is 41.20 RM/MWh. Furthermore, installing a generator will be cheaper than installing three new
transmission lines.. As a result, installing a generator strengthens the system and allows for the
most economical dispatch.
Power System Control | SEEE4453 | SET 1 | Group 1
4.0 CONCLUSION
In summary, for Case A, addressing the conditions of full load with no output from LSS 1
& 2, full load with 50% output from LSS 1 & 2, full load with full output from LSS 1 & 2, full
load with full output from LSS 1 only, and full load with 50% output from LSS 1 only involved
the strategic addition of transmission lines between specific buses. Notably, for conditions
involving LSS 2 only, one transmission line was added between Bus 1 and Bus 2, Bus 2 and Bus
4, and Bus 3 and Bus 5. In Case B, the proposed solutions for all conditions align with those
identified in Case A.
5.0 ACKNOWLEDGEMENT
We extend our sincere appreciation to Dr. Mohd. Hafiz Habibuddin, our esteemed
lecturer, for his invaluable guidance and patient supervision, which proved instrumental in the
successful completion of this assignment. Our gratitude is also extended to the entire team whose
collaborative efforts and unwavering cooperation significantly contributed to the
accomplishment of our goals. Special thanks are due to each team member who played a crucial
role in this endeavor. Their dedication and collective contributions were pivotal in navigating the
challenges and ensuring the successful fulfillment of the assignment requirements. We
acknowledge the integral role played by our lecturer and team members, making this a
collaborative and rewarding experience.
Power System Control | SEEE4453 | SET 1 | Group 1
REFERENCES
1. DR. MOHAMMAD YUSRI HASSAN. (2023). POWER SYSTEM CONTROL (5th ed.).
dESKTOP Publisher.
5. How to reduce losses in transmission lines. (2022, October 13). Cadence System Analysis.
https://resources.system-analysis.cadence.com/blog/msa2021-how-to-reduce-losses-in-transmis
sion-lines
8. Zhao, Baining, et al. "A data-enhanced distributionally robust optimization method for
economic dispatch of integrated electricity and natural gas systems with wind uncertainty."
Energy 243 (2022): 123113.