Moving Walk – Delhi- Monthly Progress

Ghaziabad-Meerut corridor Report-May’24


Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

Delhi Meerut Corridor (NCRTC Project)


Monthly Progress Report
MAY-2024
Document No – NCRTC-DM187-SIP-RP-MW-00019

▪ Project Name Delhi-Ghaziabad-Meerut RRTS Corridor of NCRTC


▪ Employer’s Name National Capital Region Transport Corporation (NCRTC)
▪ General Consultant Ayesa - Italferr - Ayesa India JV (AIAI)
▪ Contract No. DM/EL/COR-OF/187, Package M11 dated on 02-Feb-2023
▪ Work Commencement Date 16-Feb-2023
▪ Scope of Work Design, Manufacturing, Supply, Installation, Testing &
Commissioning of Travellators / Moving walk for Sarai Kale Khan
station FOB (Foot Over Bridge) of Delhi-Ghaziabad- Meerut RRTS
corridor of NCRTC
▪ Completion Period 210 Days (14-Sep-2023)- E.O.T Applied
▪ Contract Value INR 10,49,40,000/- only
▪ No. of Moving Walk 6 Units (1 Station) with Avg. length 65 mtrs

Monthly Progress Report-Submission Revision


Dated
Revision & Addition in MPR
Rev-00 08-06-24 Initial submission of Monthly Progress Report- MAY-24

Akshay Pendharkar

Authorised Signature
1
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

Contents of Monthly Progress report (As per Appendix-5)


1. GENERAL…………………………………………………………………………………………………………………...…3
2. Physical & Financial Progress………………………………………………………………………………………...4
3. PROGRAMME UPDATE…………………………………………………………………………………………..…………6
4. KEY DATES STATUS…………………………………….…………………………………………………………………8
5. THREE MONTHS ROLLING PROGRAMME…………………………………………………..…………………………10
6. PLANNING AND CO-ORDINATION…………………………………………………..…………………………………..11
6.1 Details of Civil contractor for interface…………………………………………………………….……………...11
6.2 Escalator BIM, Schedule & GAD details for Sign off progress report ……………………….……………..11
6.3 Work Progress Report………………………………………………………………………………….……............11

7. Site Inspection...…………………………………………………………………………….………………………………12

8. ENVIORMENTAL………………………………………………………………….…………………………………………15

9. QUALITY…………………………………….……………………………………………………………………………......16

10. Labour Compliance…………………………………………………………………………………………………………17

11. ISF Status Tracker ………………………………………………………………………………………………………….19

12. WORK PROGRAM …………………………….………………………..…………………………………………………..19

Akshay Pendharkar

Authorised Signature
2
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

1. General: -
1.1 Details of Manpower Deployed on Project: -
S.NO Key Staff -Designation Approved Staff
1. Project Manager Mohit Bhardwaj
2. Design Engineer Electrical Credentials Document submission required
3. Design Engineer Mechanical Credentials Document submission required
4. Travellator Specialist Credentials Document submission required
5. Installation Specialist Credentials Document submission required
6. Chief Safety Manager Anurag Sharma CV
7. Maintenance Manager Amritpal Singh
8. Civil & structure Engineer Credentials Document submission required
9. Interface Manager Awanish Kumar Mishra
10. BIM Manager Credentials Document submission required
11. Liaison Officer Abhishek Sharma

✓ Deployment of 02 out of 11 Key project staffs completed.

Akshay Pendharkar

Authorised Signature
3
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

2. Physical & Financial Progress Report: -

• Physical Status

Physical % Physical % Physical % Physical % Physical % Physical %


T otal
Agency Description
Planned Cum. up to Mar- Cum. up to for the month of Cum. up to Apr-
for the month of Apr-24 Cum. up to Apr-24
24 Mar-24 Apr-24 24

Submitted 12 0 12
NOC 0 0 0
Documents 49
Submitted % 24% 0% 24% 0.15% 0.00% 0.15%
NOC % 0% 0% 0% 0.00% 0.00% 0.00%

Manufactured 6 0 6
Manufacturing & Delivery at site 6 0 6
Schindler 6
Delivery Manufactured % 100% 0% 100% 58.00% 0.00% 58.00%
India Pvt.
Delivery at site % 100% 0% 100% 10.00% 0.00% 10.00%
Limited

Installed 0 0 0
T &C and Integration 0 0 0
Installation, T &C and HOC 0 0 0
6
Handing Over Installed %age 0% 0% 0% 0.00% 0.00% 0.00%
T&C and Intergartion %age 0% 0% 0% 0.00% 0.00% 0.00%
HOC %age 0% 0% 0% 0.00% 0.00% 0.00%
68.15% 0.00% 68.15%

Akshay Pendharkar

Authorised Signature
4
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

• Financial Status

Financial % Financial % Financial %


T otal
Agency Description
Planned Cum . up to Mar- for the m onth Cum . up to Apr-
24 of Apr-24 24

Subm itted
NOC
Docum ents 49
Submitted %
NOC %

Manufactured
Deliv ery at site
Schindler Manufacturing & Deliv ery 6
Manufactured %
India Pv t. 0% 0% 0%
Lim ited
Delivery at site %

Installed
T &C and Integration
HOC
Installation, T &C and Handing Ov er 6
Installed %age
T&C and Intergartion %age
HOC %age
Payments received till date -
Total Contract Value 10,49,40,000.00

Weightage
Weightage
Documents 2.00%
Mfg. & Supply 58.00%
Delivery at site 10.00%
Installation 15.00%
T&C and Intergartion 10.00%
HOC 5.00%

Akshay Pendharkar

Authorised Signature
5
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

3. Programme Up-date: - Document’s submission Plan & Program status for the month
is given as under: -

CLOSED
OPEN DOCUMENTS
DOCUMENTS
Total Total Documents As per
Final Released Under Review Yet to submit Code-2 Code-3 Code-1
Submitted OCS
Code-1 =0
1 0 42 1 6 0 7 49
Code-2 =1

Plan/
S.No Description Code Given
Submitted
1. Definitive Design Document 27-July-22 CODE-2
2. Work Program 27-Feb-24 Under review
3. Management Quality Plan 30-Jun-24 Code-3
4. Quality Manual 30-Jun-24 Code-3
5. Preliminary Design 30-Jun-24 Code 3
6. Operation & Maintenance Manuals Plan 30-Jun-24 Code-3
7. Spare Parts List 30-Jun-24 Code-3
8. Submissions Programme 30-Jun-24 Yet To Submitted
9. Procurement and Manufacturing Programme 30-Jun-24 Yet To Submitted
10. Material Control Schedule 30-July-24 Yet To Submitted
11. Factory Testing Programme 30-July-24 Code-3
12. Installation Programme 30-July-24 Yet To Submitted
13. Testing & Commissioning Programme 30-July-24 Yet To Submitted
Monthly Progress Report and supporting 30-July-24
14. Yet To Submitted
Documentation
15. Contractor’s Project Plan 30-July-24 Yet To Submitted
16. Interface Management Plan 30-July-24 Yet To Submitted
17. Detailed Interface Document 30-July-24 Yet To Submitted
18. Manufacturing Program 30-July-24 Yet To Submitted
19. Contractor’s Factory Testing Plan 30-July-24 Yet To Submitted
20. Test Reports 30-July-24 Yet To Submitted
Procurement, Manufacturing and Delivery 30-July-24
21. Yet To Submitted
Plan
22.
Contractor’s Health and Safety 30-July-24
Yet To Submitted
Documentation

Akshay Pendharkar

Authorised Signature
6
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

23. Commissioning Plan 30-July-24 Yet To Submitted


24. Installation Test Schedule 30-July-24 Yet To Submitted
25. Partial Acceptance Tests Plan 30-July-24 Yet To Submitted
26. System Acceptance Tests Plan 30-July-24 Yet To Submitted
27. Integration Tests & Commissioning Plan 30-July-24 Yet To Submitted
28. Training Plan 30-July-24 Yet To Submitted
29. Defects Notification Management Plans 31-Aug-24 Yet To Submitted
30. Project Document Control Procedure 31-Aug-24 Yet To Submitted
31. Quality System Procedures 31-Aug-24 Yet To Submitted
32. Details of Quality Manager 31-Aug-24 Yet To Submitted
Proposed Corrective & Preventive Action 31-Aug-24 Yet To Submitted
33.
Plan
34. Site Quality Plan 31-Aug-24 Yet To Submitted
35. Reports of Quarterly Quality Audits 31-Aug-24 Yet To Submitted
Latest drawings, test procedures, 31-Aug-24 Yet To Submitted
36. specifications, and quality documentation for
inspection of equipment
37. Quality Control Register 31-Aug-24 Yet To Submitted
38. Packaging Materials & Procedures 31-Aug-24 Yet To Submitted
39. Installation Tests Reports 31-Aug-24 Yet To Submitted
40. Proposed Partial Acceptance Tests Records 31-Aug-24 Yet To Submitted
41. Partial Acceptance Tests Records 31-Aug-24 Yet To Submitted
42. System Acceptance Tests Records 31-Aug-24 Yet To Submitted
43. Integration Tests & Commissioning Records 31-Aug-24 Yet To Submitted
44. Service Trial Records 31-Aug-24 Yet To Submitted
45. Summaries of Inspection and/or Test 31-Aug-24 Yet To Submitted
Operating & Maintenance instructions and illustrated 31-Aug-24 Yet To Submitted
46.
parts list (Final Submission)
47. Construction & Installation Plan 31-Aug-24 Yet To Submitted
Detailed written report of accidents, incidents and 31-Aug-24 Yet To Submitted
48.
dangerous occurrence
49. 31-Aug-24

Akshay Pendharkar

Authorised Signature
7
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

4. Key Dates Status: -

Non-Achieving the KD (% Per day


Pkg M-11 contract amount)

KD-1 Preliminary design


16-02-2023 0.00%
submission

KD-2 Definitive design submission 17-04-2023 0.00%

KD-3 Delievery of Moving Walkway


16-07-2023 0.01%
to site

KD-4 Installation at site, testing &


15-08-2023 0.01%
commissioning

KD-5 Take over by Employer 14-09-2023 0.01%

Akshay Pendharkar

Authorised Signature
8
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

Moving Walk Status of Section 3: -

Actual shaft Material


Length Hoisting on Mechanical
Station Po Number Location taken over Delivery date
(Mtr) dated Assembly
date on site

Sarai kale khan 11755539 F3 to F5 65 13-Nov-23


Sarai kale khan 11755541 F3 to F5 65 13-Nov-23
Sarai kale khan 11755542 F6 to F8 65 13-Nov-23
Sarai kale khan 11755544 F6 to F8 65 13-Nov-23
Sarai kale khan 11755545 F9 to F11 65 13-Nov-23
Sarai kale khan 11755546 F9 to F11 65 13-Nov-23

• Details of Key Access dates for Section 3: -

Revised Access Date


Station Units Location
received on 28-01-2023

Sarai Kale Khan 1 F3 to F5 30-June-2024

Sarai Kale Khan 1 F3 to F5 30-June-2024

Sarai Kale Khan 1 F6 to F8 30-June-2024

Sarai Kale Khan 1 F6 to F8 30-June-2024

Sarai Kale Khan 1 F9 to F11 30-June-2024

Sarai Kale Khan 1 F9 to F11 30-June-2024

Akshay Pendharkar

Authorised Signature
9
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

5. Three Months Rolling Programme: -

S. No. Description Planned Month Remarks

June-24
1. Shaft Handover

July-24
2. Hoisting Plan

August-24
3. Mechanical Assembly

August--24
4. Commissioning Assembly

Sep.-24
5. Handing Over

Akshay Pendharkar

Authorised Signature
10
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

6. Planning & Coordination: -

6.1 Details of Civil contractor for Interface: -Contact Details Site Interface: -

Civil Contactor details (Name


S.No. Station Name/Depot Name DDC Details (Name with Mob. NCRTC Details (Name with Mob.
with Mob. No.)
No.) No.)

(Fountain head) Mani Ram Meena /JE-9971078598 Pradhuman Murya(AFCON)/SM-


1 Sarai Kale khan Sushree Mathur -9811046126 7017941103
Pardeep Yadav/ XEN- 9811877572

6.2 Moving Walk BIM, Schedule & GAD details for Sign off progress report:

Package / Section- DDC


Moving Walk Schedule BIM Model GAD
& Drg Status

Fountain head Sarai kale Khan Approved


Schedule – Closed 11-10-2023 23-11-2023

Akshay Pendharkar

Authorised Signature
11
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

7. Site Visit Photographs: -


Sr.no Station Work on Site Activity

06-05-2024

Sarai Kale
Pit work for 2 travelator
khan Station (Parallel) is under
1. process. Still ½ pit is
(Pit
prepared out of 65meter
Constructed) length of M.W.

PIT Summary for Sarai Kale Khan Working Progress


Travellator Pit
Stage CASTED WIP* YTS** Remarks
Status

Sarai Kale Khan 3 0 1 2

Total 0 1 2

8. Safety: -

➢ CSM – Resume has been submitted on Wrench dated 4th June’2024

Akshay Pendharkar

Authorised Signature
12
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

9. Environment: -

Check Noise Level and found 87.3 db

Check the Lux level and found 740 lux

Akshay Pendharkar

Authorised Signature
13
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

10. Labour Compliance

Akshay Pendharkar

Authorised Signature
14
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

Akshay Pendharkar

Authorised Signature
15
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11

Contract: Package-M11 Ref No: - SIPL/NCRTC/MPR/MAY -24/Rev00


To: NCRTC Doc No – NCRTC-DM187-SIP-RP-MW-00019 Date: 08-06-2024

11. ISF Tracker Updates


PKG Total Closed Weekly Open
Closed

PKG-06 05 - - 05

12. Work Program related documents: -


Work Program Tracker- Package-M11
Document Name Date
Transmittal no/Letter No
Moving Walkway Spare Part List- NCRTC- 23-05-2024
NCRTC-DM187-SIP-LS-OM-00011
Package-M11

Akshay Pendharkar

Authorised Signature