Professional Documents
Culture Documents
Monthly Progress Report Moon Walk
Monthly Progress Report Moon Walk
Akshay Pendharkar
Authorised Signature
1
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
7. Site Inspection...…………………………………………………………………………….………………………………12
8. ENVIORMENTAL………………………………………………………………….…………………………………………15
9. QUALITY…………………………………….……………………………………………………………………………......16
Akshay Pendharkar
Authorised Signature
2
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
1. General: -
1.1 Details of Manpower Deployed on Project: -
S.NO Key Staff -Designation Approved Staff
1. Project Manager Mohit Bhardwaj
2. Design Engineer Electrical Credentials Document submission required
3. Design Engineer Mechanical Credentials Document submission required
4. Travellator Specialist Credentials Document submission required
5. Installation Specialist Credentials Document submission required
6. Chief Safety Manager Anurag Sharma CV
7. Maintenance Manager Amritpal Singh
8. Civil & structure Engineer Credentials Document submission required
9. Interface Manager Awanish Kumar Mishra
10. BIM Manager Credentials Document submission required
11. Liaison Officer Abhishek Sharma
Akshay Pendharkar
Authorised Signature
3
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
• Physical Status
Submitted 12 0 12
NOC 0 0 0
Documents 49
Submitted % 24% 0% 24% 0.15% 0.00% 0.15%
NOC % 0% 0% 0% 0.00% 0.00% 0.00%
Manufactured 6 0 6
Manufacturing & Delivery at site 6 0 6
Schindler 6
Delivery Manufactured % 100% 0% 100% 58.00% 0.00% 58.00%
India Pvt.
Delivery at site % 100% 0% 100% 10.00% 0.00% 10.00%
Limited
Installed 0 0 0
T &C and Integration 0 0 0
Installation, T &C and HOC 0 0 0
6
Handing Over Installed %age 0% 0% 0% 0.00% 0.00% 0.00%
T&C and Intergartion %age 0% 0% 0% 0.00% 0.00% 0.00%
HOC %age 0% 0% 0% 0.00% 0.00% 0.00%
68.15% 0.00% 68.15%
Akshay Pendharkar
Authorised Signature
4
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
• Financial Status
Subm itted
NOC
Docum ents 49
Submitted %
NOC %
Manufactured
Deliv ery at site
Schindler Manufacturing & Deliv ery 6
Manufactured %
India Pv t. 0% 0% 0%
Lim ited
Delivery at site %
Installed
T &C and Integration
HOC
Installation, T &C and Handing Ov er 6
Installed %age
T&C and Intergartion %age
HOC %age
Payments received till date -
Total Contract Value 10,49,40,000.00
Weightage
Weightage
Documents 2.00%
Mfg. & Supply 58.00%
Delivery at site 10.00%
Installation 15.00%
T&C and Intergartion 10.00%
HOC 5.00%
Akshay Pendharkar
Authorised Signature
5
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
3. Programme Up-date: - Document’s submission Plan & Program status for the month
is given as under: -
CLOSED
OPEN DOCUMENTS
DOCUMENTS
Total Total Documents As per
Final Released Under Review Yet to submit Code-2 Code-3 Code-1
Submitted OCS
Code-1 =0
1 0 42 1 6 0 7 49
Code-2 =1
Plan/
S.No Description Code Given
Submitted
1. Definitive Design Document 27-July-22 CODE-2
2. Work Program 27-Feb-24 Under review
3. Management Quality Plan 30-Jun-24 Code-3
4. Quality Manual 30-Jun-24 Code-3
5. Preliminary Design 30-Jun-24 Code 3
6. Operation & Maintenance Manuals Plan 30-Jun-24 Code-3
7. Spare Parts List 30-Jun-24 Code-3
8. Submissions Programme 30-Jun-24 Yet To Submitted
9. Procurement and Manufacturing Programme 30-Jun-24 Yet To Submitted
10. Material Control Schedule 30-July-24 Yet To Submitted
11. Factory Testing Programme 30-July-24 Code-3
12. Installation Programme 30-July-24 Yet To Submitted
13. Testing & Commissioning Programme 30-July-24 Yet To Submitted
Monthly Progress Report and supporting 30-July-24
14. Yet To Submitted
Documentation
15. Contractor’s Project Plan 30-July-24 Yet To Submitted
16. Interface Management Plan 30-July-24 Yet To Submitted
17. Detailed Interface Document 30-July-24 Yet To Submitted
18. Manufacturing Program 30-July-24 Yet To Submitted
19. Contractor’s Factory Testing Plan 30-July-24 Yet To Submitted
20. Test Reports 30-July-24 Yet To Submitted
Procurement, Manufacturing and Delivery 30-July-24
21. Yet To Submitted
Plan
22.
Contractor’s Health and Safety 30-July-24
Yet To Submitted
Documentation
Akshay Pendharkar
Authorised Signature
6
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
Akshay Pendharkar
Authorised Signature
7
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
Akshay Pendharkar
Authorised Signature
8
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
Akshay Pendharkar
Authorised Signature
9
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
June-24
1. Shaft Handover
July-24
2. Hoisting Plan
August-24
3. Mechanical Assembly
August--24
4. Commissioning Assembly
Sep.-24
5. Handing Over
Akshay Pendharkar
Authorised Signature
10
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
6.1 Details of Civil contractor for Interface: -Contact Details Site Interface: -
6.2 Moving Walk BIM, Schedule & GAD details for Sign off progress report:
Akshay Pendharkar
Authorised Signature
11
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
06-05-2024
Sarai Kale
Pit work for 2 travelator
khan Station (Parallel) is under
1. process. Still ½ pit is
(Pit
prepared out of 65meter
Constructed) length of M.W.
Total 0 1 2
8. Safety: -
Akshay Pendharkar
Authorised Signature
12
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
9. Environment: -
Akshay Pendharkar
Authorised Signature
13
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
Akshay Pendharkar
Authorised Signature
14
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
Akshay Pendharkar
Authorised Signature
15
Moving Walk – Delhi- Monthly Progress
Ghaziabad-Meerut corridor Report-May’24
Package-M11
PKG-06 05 - - 05
Akshay Pendharkar
Authorised Signature
16