Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Licensed copy: BUROHAPP, Buro Happold Ltd, 16/09/2019, Uncontrolled Copy, © Concrete Society

A single copy of this

Concrete Society

publication is licensed to

BUROHAPP
on
16/09/2019

This is an uncontrolled copy - not for contract use


Buro Happold Ltd

This is an uncontrolled copy. Ensure use of the most current version of this document
by searching the Construction Information Service at http://uk.ihs.com
CONCRETE ADVICE No. 02

Suspended concrete floors:


maximum size of pour allowable and
location of construction joints
Licensed copy: BUROHAPP, Buro Happold Ltd, 16/09/2019, Uncontrolled Copy, © Concrete Society

George Barnbrook BSc CEng MICE ACIArb FCS


Deryk Simpson, BSc CEng MICE FCS

The restraint to movement of suspended floors differs from that of ground floors, hence
the size of allowable pours and location of joints will be based on different factors. This
document provides guidance on the provision of joints and the selection of pour sizes and
sequences.

Additionally, it must be remembered that,


1 Background in common with all normal reinforced
concrete, the slab will crack to a limited
With ground-supported floors, the restraint degree in tension zone areas produced by
is predominantly the continuous contact bending.
with the sub-base material or slip layer. Construction joints directly add to costs of
Suspended concrete floors have some construction and greatly slow down site
minimal restraint to movement from programmes. With suspended floors it is
formwork initially, but the major restraint, the final responsibility of the floor designer
unless precautions are taken, arises from to decide maximum allowable areas of
columns, walls, deep beams and any other pour and the position of any construction
vertical structural stiffness to which the joints.
floors are rigidly connected.
It is only the designer who can appreciate
Precise guidance to eliminate, or control all design constraints and who could adjust
closely, cracking in ordinary reinforced reinforcement, for example, to modify
concrete suspended floors cannot be given allowable maximum areas of pour. The
because of the numerous controlling contractor can, of course, and often does,
factors. advise designers on allowable areas to suit
his proposed method of work.
However, a general guiding rule appears
to be that larger areas of suspended As a general guide, the maximum slab
floor poured at one time are likely to area to be poured at one time will be
give better results than many smaller dependent upon the following factors:
individual pours with the then necessary
many construction joints. • The importance attached to the
avoidance of cracking in the slab,
Each construction joint is a potential either to safeguard its appearance or to
weakness in the slab and liable to be the avoid the adverse influence on finishes.
location of a slab opening, i.e. a crack (For example, is the slab to be directly
visible at the slab surface which may not finished by power trowelling as a
have formed without the presence of the wearing surface? Cracking of
joint. significance could affect durability
under trafficking.)
Page 2 of 3 CONCRETE ADVICE NO. 02

• The position and size of vertical members any two major points of vertical stiffness should
acting as restraints to slab movement. Restraint be divided by a full free movement joint in order
will be provided by columns, walls, and to avoid the opening of the construction joints or
previously cast floor slabs. initiation of other cracks. Slab edges at a
movement joint need stiffening beams.
• The rigidity of restraints as higher rigidity will
increase the likelihood of cracking. The Formation of joints
likelihood of significant early temperature • Thorough compaction of the concrete at
Licensed copy: BUROHAPP, Buro Happold Ltd, 16/09/2019, Uncontrolled Copy, © Concrete Society

changes in the concrete must be considered. In construction joints is most important. The face of
this situation, adequate control measures, such the joint should be prepared by scrubbing the
as shading and insulation during construction, concrete while still immature with a stiff brush
might have to be employed. The use of high and water to expose the larger aggregate
cement content concrete poured in hot weather cleanly and to provide a better key for the
is more likely to lead to early thermal cracking. subsequent adjacent pour. Mechanical
scabbling of joint faces at an early age should
• The likely degree of shrinkage and the not be used as it can remove or dislodge the
percentage of reinforcement in the slab and coarse aggregate.
its orientation; the existence in the floor of
beams or beam strips and their steel • Consideration should be given to the use of
percentages. Some contraction following early permanent built-in precast concrete rails or
concrete temperature rise and long term drying proprietary steel mesh to form construction
shrinkage is inevitable and the characteristics of joints. The precast forms are shaped to provide
the concrete mix have a degree of influence, a good shear key at their location and also
together with the exposure conditions, on the provide a means of obtaining good slab levels.
total extent of shrinkage. They avoid the need for costly split temporary
timber side forms to accommodate reinforcing
• Thermal and moisture movements likely bars. Adequate reinforcement should be placed
during the life of the building. through holes in the precast forms to provide the
necessary designed reinforcement at correct
level across the joint.

2 General rules for good practice Restraint and provision of reinforcement


• Grids of downstand beams in a floor structure
Types and location of joints with normal percentages of steel cause the
• In large buildings wide free movement joints, contraction of the enclosed slab to be resisted. If
sometimes called expansion joints, may need to the percentage of steel is high enough and
be specified by the designer to allow seasonal evenly distributed in the beams, there is little
movements and long term drying effects. They reason to restrict the length of slab pour in either
add to cost, slow construction and can lead to direction, over several grids, except from the
water-leakage problems at roof and wall point of view of early temperature effects. If
positions. there are beams in one direction only, then
unless the slab in the transverse direction has a
• Construction joints parallel to and between high enough percentage of steel, cracks are
movement joints are planes of discontinuity, likely to occur within each bay parallel to the
which, if overall tensions are produced due to main beams. The important requirement here is
restrained contraction, will open to form straight to provide continuous top reinforcement
crack lines. They are potential points of tension throughout the slab panels in order to control
release. any shrinkage cracking that might occur.

• Construction joints likely to be subject to tensile • Openings in floors may cause more severe,
strain, and therefore likely to open slightly, locally tensile stresses and call for particular
should normally be positioned between the care to avoid cracking. Diagonal reinforcing bars
quarter and third points of any slab span. at corners of openings will be beneficial, for
However, the moment and shear capacity of controlling cracking at permanent openings, as
beams and slabs is only marginally affected by well as temporary openings, e.g. for tower
the positioning of construction joints at either the cranes.
point of maximum bending or maximum shear.
Thus the precise joint position in the slab span is Sequence and area of pours
not vitally important. • The location of construction joints and allowable
pour sequences should be agreed between the
• Where it is essential to avoid cracking in a designer and the contractor well before
special building, a slab attached to and between construction commences.
Page 3 of 3 CONCRETE ADVICE NO. 02

• There is no arbitrary limit on the size of a pour.


• Progressive (consecutive) sequences of pours The size of a pour will be determined by
are preferred to alternate pours, e.g. ‘hit and practical considerations. The maximum area of
miss’, chequer-board casting patterns. a slab pour must be controlled such that it can
be properly concreted and finished by the labour
• Proceed with slab pouring and pours sequence force in the allowable working day, and
in a direction away from any point of extreme adequate equipment and concrete supply must
vertical stiffness (staircase or lift shaft), i.e. be available to the contractor during the
Licensed copy: BUROHAPP, Buro Happold Ltd, 16/09/2019, Uncontrolled Copy, © Concrete Society

commence the first pour at the staircase or lift proposed working period. If a job is
shaft. undermanned, or the equipment is not
appropriate, there is a greater risk of inadequate
compaction, poor quality of floor finishing and
plastic cracking due to poor curing and
protection.

Further reading
THE CONCRETE SOCIETY, Non-structural cracks in concrete, Technical Report 22, Fourth Edition, The
Concrete Society, Camberley, 2010.
CIRIA, Early-age thermal crack control in concrete. C660, CIRIA London, 2007 (revision expected 2016)
BSI. BS 8007: 1987, Code of practice for design of concrete structures for retaining aqueous liquids, BSI,
London, (withdrawn).
BSI. BS EN 1992-3: 2006, Eurocode 2. Design of concrete structures. Liquid retaining and containing
structures, BSI, London.
BSI. BS EN 1992-1-1: 2004, Eurocode 2: Design of Concrete structures, Part 1-1, General rules and rules
for buildings, BSI, London.

Impartial advice can be sought from The Concrete Society. Members are entitled to Contacts
substantial discounts on services and products including site visits and investigations,
dependent on status. For publications and information, The Concrete Society The Concrete Society 01276 607140
Bookshop holds a wide range of books and pamphlets along with an extensive library Bookshop 07004 607777
stock. We provide many services such as literature searches and notification of new www.concrete.org.uk
references to our extensive catalogue. www.concretebookshop.com

Issued Jul 2003


Reviewed Oct 2016

CONCRETE Advice Sheets are produced and published by The Concrete Society. The information and advice
contained in the Advice Sheets is based on the experience and knowledge of the Concrete Society’s Technical Staff.
Although The Society does its best to ensure that any advice, recommendation or information it gives is accurate, no
liability or responsibility of any kind (including liability for negligence), howsoever and from whatsoever cause arising,
is accepted in this respect by The Concrete Society, its servants or agents. Readers should also note that all
Concrete Society publications are subject to revision from time to time and should therefore ensure that they are in
possession of the latest version.

You might also like