Doc.No.

: MIPL/QA-F09
#VALUE! LIGHT LUX LEVEL MONITORING Rev.No.: 00
Rev.Date: 17.05.2023
As per IS 6665-1972 Standards considered for Specification limit to the Areas
Lux Level Inspection Frequency:
Lux Level Inspection Time: 8 AM Month:
Monthly Once
Name of Location / Machine Area / Specification in Lux Lux Level Recorded
Inspection Date Sign.
Specified Zone Units in Lux Units

RM Inward Area / Storage Above 450

CNC TPP Above 300

RM Feeding Table to TPP Above 700

CNC Bending Above 700

RM Inward Inspection Area Above 700

All Fabrication Area Above 300

Tube Cutting Above 300

Secondary Operations Above 300

Inspection Before Powder Coating Above 700

Powder Coating Works Above 700

Powder Coating Inspection Above 1000

Packing & Dispatch Above 300