SCHEDULING QUESTION

There are six jobs that are awaiting processing at a machining center. The jobs are
shown in the table with their processing time and scheduled completion time. Schedule
the jobs by earliest due date, shortest processing time and the critical ratio rule and
calculate average lateness for all the jobs. Which scheduling technique performs best?
Job Process Due
Time Time
A 12 25
B 8 32
C 15 40
D 10 15
E 20 27
F 17 46

PRINCE DANIELS EXPERT SOLUTIONS

Shortest Processing Time


Job Process Due Completion Lateness
Time Time Time
B 8 32 8 0
D 10 15 18 3
A 12 25 30 5
C 15 40 45 5
F 17 46 62 16
E 20 27 82 55
Average 14.0
Earliest Due Date
Job Process Due Completion Lateness
Time Time Time
D 10 15 10 0
A 12 25 22 0
E 20 27 42 15
B 8 32 50 18
C 15 40 65 25
F 17 46 82 36
Average 15.67
Critical Ratio
Job Process Due Completion Lateness
Time Time Time
E 20 27 20 0
D 10 15 30 15
A 12 25 42 17
C 15 40 57 17
F 17 46 74 28
B 8 32 82 50
Average 21.17

The sequence developed using the shortest processing time (SPT) rule has the lowest
average lateness of 14.0. The earliest due date (EDD) sequence has an average
lateness of 15.67 and the critical ratio sequence has an average lateness of 21.17.
Based on this criterion, the SPT sequence is the best.