Professional Documents
Culture Documents
Cymdist - Training Manual - 9-11APR2017
Cymdist - Training Manual - 9-11APR2017
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
Major features :
Customizable interface and reports, Load flow, Motor starting, Load allocation,
Fault analysis: • Short-circuit • Fault locator • Series and simultaneous fault •
Voltage sag, Load balancing, Optimal capacitor placement and sizing
The program is designed for planning studies and simulating the behavior of
electrical distribution networks under different operating conditions and
scenarios. It includes several built-in functions that are required for distribution
network planning, operation and analysis.
CYME software provides great flexibility to users with very user friendly GUI
(Graphical User Interface.) User gets all required Tools, functionalities,
customization tools & visual display of network. Great flexibility is User can
modify the Menus configurations while working in CYMDIST as per their
convenience…
x NA desktop client start Network analysis software CYMDIST
x Menu Bar lists all various options (Menus) available in CYMDIST.
x Status bar give information about database path of selected study & gives
status of selected component.
x Area shown under working area where UE can see, edit various modifications
on Network.
x Explorer Bar gives option to Select/connect to any existing study database,
locate any component on N/W, edit display properties etc.
Menu bar
Working Area
Explorer bar
Status bar
Cyme Database dialog box will appear. Choose the database mode.
Select DB type
Click Next
Click on Next.
Choose the desired path for the equipment database.
Then, Click on Next.
Repeat the same procedure for network & project database also if UE wish
to create separate Databases.
Give the required database configuration name.
Click on Finish.
Click Select
Networks
Click OK
From Select network dialog box, user can select any desired network.
Overhead line
balanced
Substation
Sources/Substations
Transformers
OH Lines/Cables
Protective Devices
Capacitors
Generators
Motors
Spot Loads
Distributed Loads.
Sections/Nodes
Zones
Meters
Add Section
Select Node
Click on Add section by keeping selected that Node. Mouse curser will appear
“+ Section” Symbol.
Add new section, fill required details such as conductor details, Transformer
location name etc.
Click Two
Winding
Transformer
Configuration files are used with CYME to keep the different settings of the
application such as the display options, the calculation parameters, the
databases configurations, etc. It is thus important to set up the configuration
files that CYME will be using.
You can create your own configuration that can be distributed to other users,
thus enforcing the use of standards.
c.To select the path of the folder containing the configuration files, click
the Browse button located at the bottom of the dialog box. The default
directory where the files can be found is: C:\ProgramData\CYME.
Once the folder is selected, click the button Select. This gets you back to the
CYME Configuration Setup dialog box.
d. Click on the button Apply to apply the same path to all of the
configuration files. Your new configuration is now complete.
To close the CYME Configuration Setup and to save the new configuration
you have created, press the button OK. Clicking on the button Start
CYME in this dialog box will start the application using the configuration
just selected.
Once CYME is started, you first need to connect to a database containing the
network, equipment and load information. You can also create a new database
that you will populate by importing data. See the Database chapter in the
CYME Reference manual for more information.
a. From the Databases tab of the Explorer Bar, click Create Database
Connection.
b. The wizard displays the Database Type options available. Select Microsoft
d. Once you have selected the full path and the name of the Database
File, in this case: \Tutorial\Samples\Tutorial.mdb, click .
Note: If you enter a new *.mdb filename, CYME will create an empty database
automatically for you.
e. The wizard then asks you to confirm your database configuration setting.
Ensure that you have entered the correct settings and information, and click
Next.
that is displayed in the Database tab of the Explorer tab or in the drop-down
list box of the Database toolbar.
When you open CYME, the background of the work space is gray and most
of the toolbar icons and menu commands are disabled. To enable all of the
functions of the application and get started with a study, click on the New
Study icon or, from the menu, select File > New Study.
4. Load Circuits
a. From the toolbar, click on the Select Networks icon. The dialog
box Select Networks opens and lets you select the networks you wish to
load and view.
b. Check/uncheck
box into load/unload all the circuits in the one- line diagram.
c. Check/uncheck
box in to show or hide the loaded circuits in the one-line diagram, and click OK.
Note: See the chapter Network in the Reference Manual to learn about the
different options available in the Select Networks dialog box.
CYMDIST – Training Manual 17 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
a. From the Main toolbar, click on the Save Study icon , or from the
menu, select File > Save Study As.
b. Enter a name (“Tutorial” for example) for the study file in the field File
Name and press OK.
c. In order to open a study, you first need to close the current study. Do this
using the menu by selecting File > Close Study.
The main window of CYME should now be once again disabled (grayed),
most buttons of the toolbars and menu options as well.
The steps to save and open a self-contained study are exactly the same as for
CYMDIST – Training Manual 18 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
a simple study. The only difference is that when you open a self-contained
study you do not need to be connected to the database it was created with.
The file is autonomous, meaning that it contains all the information to
replicate the network that was loaded when the study was saved.
This tutorial provides a guideline on how to create equipments with the CYME
Software. A self-contained study file (.sxst) to use with this tutorial is provided.
The explanations below are based on the use of that file.
1. General
a. For this tutorial, open the study
EquipmentModeling.sxst.
a. Go to Equipment >
Source Equivalent.
Calculation Method 1
Calculation Method 2
The second calculation method calculates the equivalent impedance from the
sum of the impedance of the substation transformer(s) and the transmission
network. In the Utility Equivalent group box, select Short-Circuit Level as the
calculation Mode.
• Click on the Calculate button next to the Calculate using source details
option and enter the primary network impedance or the short-circuit power.
button.
• In the Harmonic tab, you can
enter the Negative Sequence
Impedance. By default, this
impedance is set equal to the
sub- transient impedance of the
generator.
4. Create a Motor
a. To create a motor, go to Equipment > Motor. There are two types of motors
available: Induction and Synchronous. Select the Induction Motor.
b. You need to enter the following set of data to represent the motor for Power
Flow, Short Circuit and Harmonic Analysis studies.
• Nominal Data (Name plate data) of the motor developed HP, Rated Voltage,
Efficiency and Running Power Factor
• Locked Rotor Data such as locked rotor (starting) power factor, NEMA Code
and KVA/HP or Locked Rotor
Current.(Entering one computes the other value)
• Available impedance estimation methods are Locked Rotor / Full Load Test,
Locked Rotor / No Load Test, Nominal Conditions, Starting Conditions,
From Nameplate Data, and from Performance Characteristics. (for further
details, refer to the Motor Starting Analyses User’s Guide).
5. Create a Transformer
a. Go to Equipment > Transformer in the menu. You have six options: the
Two-winding Transformer, Two- winding Auto-Transformer, Phase
Shifting Transformer, Three-winding Transformer, Three-Winding Auto-
Transformer, and the Grounding Transformer.
be entered accordingly
too.
d. If the transformer has a Load Tap Changer (LTC), select the LTC tab, and
check the Load Tap Changer option.
Upper and Lower Bandwidth in % specifies the range of the desired voltage at
the controlled bus. You will also have to specify the Number of Taps available
in the LTC and the Maximum and Minimum range of the LTC Tap.
6. Create a Line
You can either select a conductor or create one in the database of the
equipment. It is suggested to have an inventory of conductors and spacing
conductors prior to building overhead lines and cables. This will facilitate their
creation as you can select conductors from the inventory in the overhead line
and cable dialog boxes. The steps to create a line/cable
are outlined below.
a. Create conductors
• Go to Equipment
> Conductor to
access the
conductor database.
• For this exercise, click
• Go to Equipment >
Overhead Line > Single-Circuit
Spacing. Double-Circuit
Spacing is also available in the
Overhead Line category.
•Click OK to exit.
c. Create a line
• The balanced type uses the same conductor for all phases, whereas the
unbalanced type uses different conductors for each of the three phases.
• The phase and neutral conductor drop-down menu lists all conductors
created in the conductor database, and likewise the spacing drop-down menu
lists all spacing created in the database. Click on and create a new line called
A_NEW_OH.
• Choose the conductor created earlier, A_NEW_CONDUCTOR, for phase and
neutral.
• Select A_NEW_SPACING for the spacing.
• Once all is selected, click on Update impedances for the current line to
have the equivalent impedance of the line.
• Click OK to exit.
7. Create a Cable
d. The information to fill in the General tab fields is unknown, except for the
type of cable to be Three Core with
Concentric Neutral and PVC insulation. Click on the
CYMDIST – Training Manual 31 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
button.
e. Enter the cable information as follows and also shown in
the figure below:
• Copper, 3/0 AWG, Standard Concentric, with 19 strands, and 0.46 in
diameter
• PVC insulation with 0.24 in thickness
• There are 32 concentric copper wires as neutral, size 12 AWG, and the Lay
Length is 5.64 in.
g. Back in the Cable dialog box, click on the Impedances tab to calculate
impedances based on the construction details entered. Select the option
Computed from construction details and click OK to exit.
The dialog box for a fuse is shown below. It is similar for all the protective
devices where you can enter:
By accessing the Equipment menu, you can create other equipments such as
Shunt/Series Capacitors, Shunt/Series
Reactors, and Harmonic devices.
It is possible to add equipment from the CYME Equipment Library. The latter
provides default equipment which can be used to populate the lists available
a. Go to the Equipment
Inventory section of the Explorer
tab in the Explorer bar. Select the
type of Equipment and an ID. For
this example, go to Line, Cables
and Conductors. You can also
access the same dialog box using
the Equipment menu.
f. To install a new device, drag and drop a symbol from the Symbol Bar of the
Explorer bar onto the one line diagram. Double click on the device.2016
This tutorial provides a guideline on how to create a network with the drag-and-
drop method.
1. Getting Started
bar.
2. Work Space
Once the Type of Network is defined, which for the purpose of this tutorial is
an industrial network, the workspace will be displayed to enable you to drag
and drop devices.
a. Click on the Display Page Layout icon if it is not already selected in the
Main
toolbar.
• Fit Network in
Page to have all the
network elements
fit in the
workspace.
• Portrait or
Landscape.
CYMDIST – Training Manual 38 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
• Page Setup to
specify paper size,
orientation,
margins etc.
• Print and Print
Preview.
3. Symbol Bar
On the left hand side of the workspace is the Symbol Bar, which provides
default categories of equipment that can be dragged and dropped to the
workspace.
Categories are:
x General for Networks and Buses.
x Lines and Cables for interconnecting different devices and circuits.
x Sources and Generators for Equivalent Utility Source, Generators
(Synchronous and Induction) and Wind
Turbines
x Power Electronics comprises additional devices for equipment that can have
special
Bus
x Click on the “Bus” Symbol in the General category of the Symbol Bar tab and
drag to the workspace.
x Double click on the bus symbol to display the Bus Properties dialog box on
screen.
Single Port
• Click on any single port equipment and drag to the workspace to connect to
the desired bus.
• Once the equipment is dragged close enough, the bus color will change to
indicate that the mouse button can be released to complete the connection.
Two-port
• Click on any two-port equipment and drag
to the workspace to connect the “From” bus
in the same manner as connecting single
port equipment.
Node
You can change any bus to a Node and vice
versa using the bus properties dialog box.
Nodes have the same properties as buses and
can be used to connect equipment. This may
be useful to represent single equipment
connected to a certain bus such as a motor.
Connection Port
Bus to node
You can connect a bus to a node by simply
selecting a bus, drag it close to the node, and
once the node color changes, release the
mouse button to complete the connection.
Intermediate node
Group
Selection
• Point the cursor to the desired component and click the left mouse button
once.
• The equipment will change its color as per the selection color specified in
the View Properties tab of the View > Display Options dialog box.
• You can select a group of equipment by simply clicking once on the left
mouse button and drag over the desired network. The Enable automatic
region selection option can be enabled in the View Properties tab of the
Display Options dialog box.
• The color all components will change color as per the selection color
specified.
• You can then Move, Copy / Paste or Delete the entire network.
6. Resize Command
Bus
• Select the desired bus.
• Point the mouse cursor to either side of the bus until the cursor changes to
a double sided arrow, click and hold the left mouse button and slide left or
right to shorten or lengthen the bus.
7. Move Commands
Bus
• Select the desired bus.
• Point to the bus until the cursor changes to , click and hold the left
mouse button and move the bus to the new location.
Single port
• Select the desired single port equipment.
Two-port
• Select the desired branch.
• Point the mouse cursor to the branch until
the cursor changes to double sided arrow,
CYMDIST – Training Manual 44 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
8. Rotate Commands
Bus
• Select the desired bus.
• Point to the located at the right hand side of the bus click and hold the
left mouse button and rotate the mouse until the bus has a vertical
orientation. Only horizontal or vertical positions are available.
Single port
• Select the desired single port equipment.
Single port
• Select the desired single port equipment.
Two-port
• Select the desired two-port equipment.
• Point the mouse cursor to equipment until the cursor changes to , click
and hold the left mouse button and slide the equipment as detailed in the
illustration below.
Modif.
Pan – Click the right mouse button once and hold it down (the
cursor will show “Pan”). Move the mouse and release the button.
The picture on the screen will move as though you had pulled it.
Zoom – Click the right mouse button twice and hold it down. The
cursor should change to “Zoom”. Move the mouse so that the outline
box surrounds the desired area and release the button.
Display Best Fit. Will resize all drawing elements (line width, font
size, symbol size) in relation to one another. The corresponding
drawing settings found in the Display Options dialog box are
changed. Note that the changes made to the display cannot be
undone using the Undo Modif command.
Branch Motor
Adding any Bus or Device is simply done by clicking with the left mouse
button on the symbol of the desired device in the Symbol Bar tab of the
Explorer Bar, dragging the symbol on the workspace and dropping it at the
desired location.
The illustration below shows the industrial network that you will build using the
following instructions.
click on the icon to create a new source equivalent that you will name
UTIL-
1_SOURCE. Enter the data as illustrated. Click OK to save it in the Equipment
CYMDIST – Training Manual 50 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
Database.
b. Click on the Add Source icon in the Editor Toolbar and double-click on
the workspace near the bus to connect it to the UTILITY-BUS.
selected, click on to
confirm the selection.
The bus dialog box will now indicate that the kVLL of the bus is now 69.0 kV.
a. Drop the device to the desired bus and then slide the mouse towards the
second bus and release the mouse button to complete the connection.
a. From the toolbar, click on the Save Study icon or, from the menu, select
File>Save Study As Self
Contained. This will save the Network and all equipments used into a study file.
b. Enter a name (“Tutorial” for example) for the study file in the field File Name
and press OK.
1. Getting Started
a. Launch CYME.
b. Scaling factor – Whenever building a network, one of the first steps should
be to determine the scaling factor. The scaling factor is the relationship
between the user’s coordinate system and the one in CYME. Usually, it is
determined by the GIS or the DMS database, and CYME imports such
coordinates as defined by the external mapping system. To change the Scaling
factor, go to File > Preferences, Editor tab, under the One-Line Diagram
category.
In both cases, you may also right-click on the toolbar area of the display and
select the toolbar(s) from the pop-up menu.
1. Feeder
b. The cursor, when moved over the work space, should carry the word
Network.
CYMDIST – Training Manual 56 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
2. Section
a. You can create sections from a feeder head-
node or from any node.
b. Select the Add Section icon.
length
and the location of the section by moving the cursor around.
e. As you let go of the mouse button, the Section Properties dialog box will
show up in which you can:
Note: If the Section Properties dialog box does not appear automatically,
access the File > Preferences dialog box. In the Editor tab (Network Editing
Options), enable the option “Display Section Properties dialog when adding a
section or a device”.
d. To view intermediate
nodes, go to View > Display
Options. In the Symbols
category, click on the
Modify button, go to the
Network Symbols branch
and check Intermediate
nodes. You can change the
CYMDIST – Training Manual 60 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
5. Insert Section
d. When you release the mouse button, the Section Properties dialog box for
the new section appears. By default it replicates the existing section. Enter the
data correctly, such as the type and the length. Click OK when all data is
entered. The new section is inserted before the section selected.
6. Split Section
d. When you release the mouse button, the Section Properties dialog box for
the new section appears. By default it takes the total length of the original line,
so enter the length of the first section. Please note that it cannot be longer than
the length of the original section. Click OK when the data is entered and the
original section should be split into two, with the first section having the new
length and the second section having the remaining of the original length.
Building a network using drag-and-drop makes use of the Symbol Bar tab of the
Multi-explorer of CYME.
b. Verify if the Symbol Bar tab is present in the Multi-explorer, if not, right-click
in the free space of the tab area in the Multi- explorer and select Add > Symbol
Bar from the pop-up menu.
CYMDIST – Training Manual 62 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
In the Symbol Bar tab, you can make use of the Default groups
available from CYME. Each group consists of equipments listed so they
are easily accessible for dragging-and-dropping.
a. If you wish to modify the content of the Symbol Bar tab, you can open the
group and select Customize Group from the pop-up menu on the right-click.
b. In the Customize Group dialog box, you can then select which Equipment
Id from which Device is to be included in a certain group. Therefore, you can
only select those equipments most commonly used from the Equipment
database.
c. Likewise, you can create a new group by choosing Add Group from the pop-
up menu upon the right-click. In the
Add Group dialog box, you can name the group and select the equipments
to be included in this new group.
9. Network Building
a. You can drag and drop a network onto the study page. As previously,
the Network Properties dialog box will appear as soon as you have
dropped the Network.
b. Likewise, you can drag and drop a line onto a node (it will change color to
display it has been properly selected) from which a new section is to be
created. Release the mouse button and the line will be attached to the node
onto which it has been dropped. Move the cursor away from the node to select
the location of the end node of the section.
c. When adding a device to a section, you need to place it at the correct location.
Loads and capacitors can be at the from node, at the middle, or at the to node.
Other elements can only be at the from node or the to node.
d. Dragging and dropping a line onto a bus is also possible. You will not
have to create a connector prior to connecting a line: it will be created
automatically.
Select a line from the Symbol Bar tab, drag and drop it onto a bus which
will change its color for it is selected. Move the cursor away to position the
to-node of the section and left-click. The line is created.
many consecutive changes as desired: click the down arrow to see the list
of modifications done. Equivalent menu command: Edit >Undo Modif.
redo as many undone changes as desired. Not available until at least one
change has been undone. Click the down arrow to see a list
CYMDIST – Training Manual 65 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
Pan – Click the right mouse button once and hold it down (the
cursor will show “Pan”). Move the mouse and release the button.
The picture on the screen will move as though you had pulled it.
Zoom – Click the right mouse button twice and hold it down. The
cursor should change to “Zoom”. Move the mouse so that the
outline box surrounds the desired area and release the button.
Zoom – If your mouse is equipped with a wheel, you can zoom in or out
using that wheel. The center of the area that will be zoomed (the focus of
the zoom) will be the location of the cursor on the display. It will remain
visible as you change the zoom level.
increase or decrease the size of the network components and the level of
details displayed. Zoom to fit will bring you to your original display, while
Magnify will allow you to select and magnify a small part of the network.
Display Best Fit. Will resize all drawing elements (line width, font
size, symbol size) in relation to one another. The corresponding
drawing settings found in the Display Options dialog box are
changed. Note that the changes made to the display cannot be
undone using the Undo Modif command.
Section: Motor:
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
1. Getting Started
2. Substation
a. On the Left
Hand side of the
workspace, click on
the Network icon in
the Symbol Bar
and drag and drop
onto the workspace.
Or, use the Add
Network icon
and double click on
CYMDIST – Training Manual 68 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
the workspace at
the location desired
for the substation.
b. In the Network Properties dialog
box, specify a name for the
substation (for example,SUB-1), set
the
Network type to Substation, and the
View style of the network to
Schematic to obtain a single-line
diagram view.
3. Building a Substation
a. Double click on the Sub-1 symbol to
open the workspace of the new network in
a new tab window in the main display. Or
right click on the substation and select
View in the pop-up menu.
b. To build inside the substation, use the Add Section icon .Select the
source node, slide the mouse away from the source node, and double-click on
create a section. The Section Properties dialog box will appear in which you can
click on to add the devices desired to the section created.
d. The second method to draw a bus is to: (1) select a node and put the
cursor on either side of the node so the cursor shows a horizontal double-
arrow, (2) drag to lengthen the side and (3) repeat for the other side of the
node.
Note that only Nodes can be used as connection ports to and from nested
networks.
4. Connecting to a Substation
b. If you choose to connect the node to another node, the Assistant will then
prompt you to select the node to which the feeder is to be connected to. Select
a node in the substation by clicking on it; its Node Id will appear in the
Selection box. Click on Connect when finished.
c. If you choose to Drop the node inside this view, it will then drop the node
CYMDIST – Training Manual 73 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
inside the substation, without attaching it. It is then up to you to drag the
feeder connection node to attach it to a node in the substation.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
The CYME program includes the option to model secondary networks, which
are networks along the primary distribution networks. Examples are
underground networks, secondary grids, etc.
1. Getting Started
e. Click on OK.
d. Choose the option Connect the node to another node, select the source
node inside the secondary network.
e.Click
g. Click on the
Connect button to
complete the
connection.
Once the connections from the primary networks to the secondary network
are completed, we can then proceed to building the secondary network.
The building of the secondary network is the same as the building of the
primary networks. Sections with devices can be added via the Section
Properties dialog box or by dragging and dropping the elements from the
Symbol bar tab of the Multi-Explorer pane.
CYMDIST – Training Manual 79 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
c. Drag and drop the Network Protector to the node 32. Connect to the bus
36.
It is possible to work with only the secondary network without loading the
primary feeders.
b. In the Select Networks dialog box, check only the Secondary Networks
(note: the network type column indicates it) and click OK.
d. Click on Run.
1. Getting Started
The CYME program includes the option to model substations, and to create
nested networks which could be used to represent industrial plants, motor
control centers, panel boards, etc.
2. Nested Networks
a. To model a sub-
network such as an
industrial plant or
motor control center,
click on the Nested
View Icon and drag as
close as possible to
the desired node.
the right),
Load Model
Load Models are created using the Load Model Manager. All analysis, reports
and result boxes will use the active load model.
To create load models names. The customer types part of the load model are
created using the Customer Type button. This data is saved with the self-
contained study. Same as Network > Load Model Manager.
To create load models names. Click on New to create a new name (do not use
spaces between characters). You can either create a blank model or copy an
existing model. The Delete command deletes from the database the data related
to the load model name, whereas the Reset command sets to zero the loads of
the model while not removing the name from the database.
For a blank load model, you may need to import the data using the menu
command Database > Import. If this option is not checked, the software will
copy the model from the load model which name is selected.
The customer load data is typically set through the load Settings group boxes
of the Section Properties dialog box of each section for which a load is
specified. You can also associate a load model to a source specified with user-
defined parameters (see Equivalent Tab)
Customer Types:
Display the Customer Types dialog box where you can edit the existing
customer types and create new ones. You can also access this function
from the menu Network > Customer Types
This command enables you to define and manage customer types and
categories. The four categories, “Residential”, “Commercial”, “Industrial”, and
“Other” are the base classes, and as such cannot be deleted. Click on New to
create new ones to be added to this list.
To specify the portion of the load that is the constant power (P), the constant
current (I) and the constant impedance (Z).
Under settings, select Load Model, Customer Type and select format for
study like Kw-Kvar, Amp-PF etc.
Load Modeling
Two self-contained study files (.sxst) to use with this tutorial are provided. The
explanations below are based on the use of that file. The
Substation Modeling module is required for this tutorial.
This Network Equivalent calculation runs for the networks in the database
and not only for the ones displayed.
c. For the purposes of this tutorial, display the properties of feeder GA06
before running the Network Equivalence Calculation module. To do so, click
on the GA06 feeder icon (as shown in the figure).You will be directed to the
GA06 head node in the geographical view. Click on that node to access the
corresponding Network properties dialog box.
The properties we are looking for are in the Equivalent tab window. Select
the Equivalent Impedances mode. Click OK to close the dialog box and
proceed with the next steps.
2. Network Reduction
b. Select the menu command Network > Network Reduction to display the
Network Reduction dialog box.
c. Click Add to
create a
configuration
name: Tutorial-
demo.
The tab Device Restrictions allows the user to select the devices that are not
to be included in the network reduction. You may set some Filter rules for any
j. To start the
network reduction
simulation, click
Run.
CYMDIST – Training Manual 96 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
After performing a Network Reduction, you will notice that the size of the feeder
GA04 has been reduced, as shown.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
The Load Allocation analysis is used to adjust the connected load to match
the metered demand. CYME will assign a portion of the metered demand to
each phase of each section according to the distribution transformer size
(connected kVA), the customer consumption data (kWh), the real
consumptions (kVA or kW) or the REA method.
b. In the Analysis menu, select the Load Allocation option to display the Load
Allocation Analysis dialog box.
c. You need to select the Networks, the Allocation Method, the Tolerance
and the Demand Type that are going to be used for this process:
CYMDIST – Training Manual 98 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
• Select Connected kVA in the Allocation Method drop down list (b)
• Click on the
button to access the
parameters of the load
allocation (c)
Using this method, one can expect that a load point having a connected kVA
value of 100 kVA would get twice the load of another load point having a
connected kVA of 50 kVA since this method distributes the demand
proportionally to the connected kVA of each load point. As an example, review
the load at section 6156 versus section 6366. Open the related Section
Properties dialog boxes to view the details.
Now, let’s assume that not only the demand of the feeder is available to the
user, but other points on the feeder have been recorded as well. The user
has the total demand of the feeder, plus other measurements on the feeder.
Having more measured points will allow the load allocation function to
adjust the load points of the network more precisely. This will allow for a
more accurate representation of the system.
In this situation, we
know the total
demand on the
feeder (Meter #1,
switch on section
6156); and we also
know the demand
flowing through the
switch on section
CYMDIST – Training Manual 101 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
8654 (Meter#2,
switch on section
8654).
b. Locate the two switches on which you want to create meters to enter the
demand to be allocated.
d. Once the two meters have been added, select Load Allocation from the
e. You need to select the Networks, the Allocation Method, the Tolerance and the
g. To verify the results of the load allocation, open the result box called Load
Flow Box and select the locations of the meters. You should see that the
d d h dh b ll d l b
1. Getting Started
2. Network Description
Simulation icon in
the Simulation toolbar
to
open the Load Flow Analysis dialog
box.
Parameters
b. Convergence Parameters.
For this tutorial, they are set to 0.01
%(V) tolerances and the maximum
number of Iterations to 40.
e. Voltage and
Frequency Sensitivity
Load Model is used to
account for the variation
of the load with the bus
or node voltage.
i. Voltage threshold Vz is the voltage below which all loads are converted to
constant impedance. Once the voltage recovers they are switched back to their
original state. Vz is set to 80% for all load types in this case.
CYMDIST – Training Manual 107 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
j. Click on OK.
Note: The Frequency Sensitivity component Pfreq and Qfreq of the load will
only be considered during transient stability studies.
Networks
Controls
a. Include all Capacitors, Generators, and Motors and select the Normal
operation of the transformer tap controls.
Loading Limits
b. The corresponding
column for the % Loading
Limits data entry will be
activated (blue) to allow
entry of the individual
loading limits for any
network component.
CYMDIST – Training Manual 108 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
Voltage Limits
Output
Click OK.
5. Simulation Results
a. Display the load flow result tags by selecting Power Flow Results from
the Tag Layer drop-down menu. Click on the icon to display the dialog
box where you will be able to specify, for each type of equipment, the data
that will appear in the tags; such as the Bus Voltage (p.u.), angle in deg.,
cable current flows, MW and MVAR’s, etc.
6. Abnormal Conditions
b. As an example the
following abnormal
conditions from section T3
can be noted:
The cable supplying power to the motor PM2 is overloaded since it is color
coded in yellow. The current through the cable is 180.8A on each phase, which
exceeds the
85 % loading limit of the standard rating of the cable.
h. An example would be the balanced current $IBal$ in amps (A). This would
be entered as $IBal$ A.
9. Reports
The abnormal
conditions are
highlighted in the
reports using the
same colors as on
the one- line
diagram.
The Load Growth command allows the user to specify the percentage change
for loads during specific years, modify the loads accordingly and run the
simulation to evaluate the effect of such load changes on the network. The
growth factor (s) may be general or user defined, the latter giving the
possibility to specify annual growth rates for loads on specific sections, zones,
feeders and nested networks.
1. General Mode
The General growth option allows entering a growth percentage that is either
a total percentage of growth regardless of the number of years or a percentage
of growth per year from the actual year to the final year of the simulation.
c. Select section 6252 and open the result box called Load Flow Box
(Ctrl+V). Observe the real power through on each phase.
Note: You can use the Detailed View tab of the Multi-Explorer pane to search
for the section.
d. Now, select section 6514, on which is connected the first load on the
network, and open the Section Properties dialog box. Click on the Spot
Load By Phase item in the Devices group box on the left-hand side to see
that the load is 10.35 kW per phase.
e. Go to Network > Load Growth > Apply Factors. Select the Feeder GA07 and
choose to perform a load growth of 5% total on all types of load until the end
of year 2007:
• Select the feeders on which the load growth is to be performed. You can select
one or more feeders at a time.
For the purpose of this exercise, we will apply load growth on the feeder GA07,
which consists of spot loads of residential (143), commercial (38) and
industrial (1) types. (1)
• You can view the Actual year(s) of the load(s) belonging to the feeder
selected. (2)
• Type in the year (2007) to which the load will be set to after the load growth
process. (3)
• Select the General Growth option and enter the growth factor. Decide
whether the growth factor is Total or
Per Year. (4)
f. Once the OK button is clicked, CYME will apply the growth factor to the
customer type(s) of the load type(s) selected.
2. User-defined Mode :
The User defined growth allows defining more precise growth percentages
through the Edit Growth Factor
dialog box. The factors can be entered per feeder, section, zone, substation and
secondary network.
a. Go to Network > Load Growth > Edit Factors to access the Edit Growth
Factors dialog box.
b. Select the Year to which the factors will be associated to. More than one
year can be selected at the same time by holding down the Ctrl button, but
the same factors will be associated to each.
c. Growth factors can be specified per feeder, section, zone, substation and
secondary
network. Filters can be applied on the locations displayed.
d. The Growth Rate can be specified for each load type (spot or distributed) and
then for each customer class (residential, other, commercial, industrial, and/or
any user-defined).
You repeat this process if growth factors are to be set for other years, or for
the same year but by different types of factors.
e. We are setting a
load growth to year
2008 such that the
residential spot
load on section
6514 will grow by
10%.
g. To apply the
factors, go to
Network > Load
Growth > Apply
Factors, select the
User defined
growth option, set
Load growth to
end of year 2008
and run the
analysis.
h. After the load growth simulation, view the load on section 6514. The
load value is 11.96 kW per phase, which represents a 10% increase on its
previous value of 10.87 kW.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
c. Click on .
The one-line diagram color will change to indicate that there are low voltage
problems on almost the entire feeder.
f. Go to Report > Analysis menu option and open the Load Flow – Summary
Report. From the report, it can be seen that the kW losses are 154.14 kW. The
Abnormal Conditions table also indicates 1016 sections with low-voltage
conditions, and 3 sections with overload conditions on the phase A.
a. Select the Load Balancing analysis from the drop down list in the
Simulation toolbar and click on the Run
b. Four objective functions are available: Minimize the KW losses, Balance the
c. Include all possible overhead line sections and underground cables (i.e.
uncheck all the options in the Restrictions group box). These are the line
sections which are to be considered in the analysis.
e. The program will then identify all possible re-phasing of conductors that
can be implemented on the feeder and display the results on the screen.
Each re-phasing step recommended includes specific information as to which
phase(s) is (are) involved, the Load transferred and the Total losses before
and after the re-phasing operation.
f. Right click on
h. The Show Abnormal Conditions option should still be activated. The one-
line diagram will show that there are no more low voltage problems on the
feeder.
j. Access the Load Flow – Summary Report again. It can be seen that the losses
have dropped to 62.43 kW. Also, the Abnormal Conditions table does not show
any sections with a voltage problem anymore
A self-contained study file (.sxst)and map files to use with this tutorial are
provided. The explanations below are based on the use of those files.
The user can display raster or vector map images (geographical land-base
such as DWG, DXF, SHP, etc) as layers directly underneath the electrical
model.
With this option, you will be able to perform your simulation and visualize the
results just as if you were in a view of your CAD or AM/FM/GIS system.
a. Along with this tutorial are the background map files used for this exercise,
which are located inside the installation folder CYME\Tutorial\How-
to\BackgroundMap.
d. In the Background Map tab under the field Type, you can select to display
three types of file: MapServer Files (*.gds), AutoCAD Files (*.DWG and *.DXF)
or Shape Files (*.shp). The Map Server program supports numerous formats
for Geographical Map information, such as Windows bitmap (.bmp), Atlas GIS
(.bna), AutoCAD (.dxf), Tagged Image File Format (.tiff), etc.
• Browse for the Background Map folder as mentioned in step 1, and select all
the files listed. Click on Open.
• To customize the
map layers, right-
click on the layer
and select
Properties from the
pop- up menu. The
Layer Properties
dialog box allows
users to change the
color and the
thickness of the
lines used for the
area.
a. Importing a map into the database enables the automatic map loading
when selected feeders are loaded. Files of type AutoCAD can be imported
when a database is connected. Create a new study for the next steps (File >
New Study).
b. In the Background Map tab of the Multi-explorer pane, click on the
Database button (when connected to a database).
c. Select the Browse button and choose the directory where the AutoCAD
files are stored. Once the selection is done, click on the Import button.
d. Once the file is imported, check the Automatically load the map(s) from
the database checkbox to enable the automatic loading of the map layers
covering the area shown in the main display.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
1. Getting Started
Click on .
Verify that there are no abnormal conditions on the network by clicking on the
Show Abnormal Conditions button
d. Run the Load Flow analysis on the network and click on the Show Abnormal
Conditions button. As indicated by the red color, the addition of the industrial
load has caused a substantial voltage drop on the feeder.
3. Capacitor Placement Analysis
b. Select the Objectives tab and choose the following options in the dialog box:
f. Click on the Run button to launch the analysis and display the results.
g. Under the Results tab, click on all the buttons to expand the tree view
and show the optimal location suggested for the installation of the capacitor
bank, i.e. section 15097. Clicking on 15097 will make the size of the banks
(fixed and switched) and the reduction in KW losses displayed.
h. Select Peak Load: 100.0 % and click on the Apply Capacitor button to
install the capacitor on section 15097.
Click on OK.
h. Run the Load Flow analysis again, click on the Show Abnormal
Conditions button and generate the Load Flow Summary report. As it can be
noticed, the addition of the capacitor bank has eliminated all voltage
problems on phases A and B while reducing significantly the low voltage
problem on phase C of the feeder.
1. Getting Started
Launch the CYME program. Open the ShortCircuit.sxst self contained study
file provided with this tutorial.
2. Network Description
3. Short-Circuit Analysis
b. You can also select this analysis from the Analysis > Fault
Analysis > Short-circuit menu option. c. The Short-circuit
Analysis dialog box is composed of five tabs that allow you to set
the:
• Calculation Mode,
which includes a
network-wide short-
circuit analysis along
with the options for the
fault flow analysis of a
single fault.
• Short-circuit analysis
Parameters, including
fault impedances,
machine impedances
and to include or not
motor contributions.
• The Networks tab,
where you can select the
network(s) to analyze.
• The Short-Circuit
CYMDIST – Training Manual 135 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
4. Parameters
• Fault impedance set to zero which implies the computation of bolted faults
5. Simulation Results
a. Activate the Tag Layer toolbar in View > Toolbars > Tag
Layer
6. Result Boxes
e. It is also possible to
customize the result box
to display different
keywords per device. To
do so, click on the
Manager button, or go to
Customize > Result Box
> Short-circuit Box.
7. Graphs
a. Let us now add the fault level MVA keywords to the Summary on all buses
layer.
c. Select the
“Bus” option
under the
Network Tags
category to display
the tag defined for
buses.
d. Click on the
button
Component Keywords Description
to access the list of
Bus $BusId$ Bus Id
keywords available. $LLLmva$ LLL MVA Fault Level
$LGmvaMax$ LG MVA Fault
$LLmva$ Level LL MVA
$LLGmva$ Fault Level LLG
e. Select the MVA Fault Level
keywords as
listed in the table
below.
Note: Inside the Format field, characters in black are user text and
characters in blue appearing between “$” are the software keywords.
a. Scroll down the list of Symbols to display in the left-hand side to find
the Abnormal conditions category.
c. Select the abnormal conditions you wish to display. Only the abnormal
conditions relevant to the current studies
(such as the withstanding and interrupting ratings for the short circuit study)
will be highlighted.
e. You may also see the abnormal conditions listed in the Explorer Bar. To
display Abnormal Condition, go to View > Explorer Bars and add Abnormal
Condition to the list of used bars.
f. Results can be viewed by accessing the Load Flow Result Box (Ctrl-V).
With this result box opened, click on any node/section, in this case Bus -
B1, of the network and view its results in the box.
g. Results of the Fault
Flow analysis can
also be displayed in
reports. The Fault
Flow reports can be
found in Report
> Analysis and select Valid
Analysis Reports.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
1. Getting Started
2. Network Description
3. Short-Circuit Analysis
b. You can also select this analysis from the Analysis > Fault Analysis
> Short-circuit ANSI menu option. c. The Short-circuit ANSI dialog
box is composed of four tabs that allow you to set the:
• Calculation Mode,
which includes a
network-wide short-
circuit analysis along
with the options for the
fault flow analysis of a
single fault.
• ANSI Short-circuit
analysis Parameters,
including Duty types
and to include or not
motor contributions.
• The Short-Circuit
CYMDIST – Training Manual 147 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
4. Parameters
• Select Short Circuit Levels at All Buses and Nodes in the Calculation
tab.
5. Simulation Results
The ANSI result box will automatically appear once the calculations are
done. You can customize the result boxes in order to display results as
desired; see section 6 of this tutorial for the explanations.
Select any bus to view results in the result box.
a. If the Tag Layer toolbar is not activated, activate it from View > Toolbars >
Tag Layer.
6. Result Boxes
a. To display the Short-Circuit ANSI result box, press Ctrl-5 from your
keyboard or go to View > Result Box > Short- Circuit ANSI Box. To see the
results at a particular bus or node, click on that element.
e. It is also possible to customize the result box to display different keywords per
device. To do so, click on the
Manager button.
c. Click on the
button
to access the list of
keywords available.
d. In the Format
field, edit the list of
keywords to add
the ones indicated
in the table below.
Note: Inside the
Format field,
characters in
black are user text
and characters in
blue appearing
between “$” are
the software
CYMDIST – Training Manual 152 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
keywords.
Bus Id
ANSI Three phase half cycle current
ANSI Three phase half cycle multiplicative factor
ANSI Three phase peak current
ANSI Three phase peak multiplicative factor
ANSI Line to ground half cycle current
ANSI Line to ground peak current
e. Click on followed by the button to save and exit the
Tag and Text properties dialog box. f. Once the keywords added,
the tag layer
should look as
shown in the
illustration.
9. Simulation Results
b. On the one-line
diagram, results can
be viewed by accessing
the Fault Flow Result
Box (Ctrl-4). With this
result box opened,
click on any
node/section of the
network and view its
results in
the box. The result
a. Scroll down the list of Symbols to display in the left-hand side to find
the Abnormal conditions category. b. Expand the list.
c. Select the abnormal conditions you wish to display. Only the abnormal
conditions relevant to the current studies
(such as the withstanding and interrupting ratings for the short circuit study)
will be highlighted.
e. You may also see the abnormal conditions listed in the Explorer Bar. To
display the Abnormal Condition, go to View > Explorer Bars and add
Abnormal Condition to the list of used bars.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
1. Getting Started
2. Network Description
3. Short-Circuit Analysis
a. Select Short-circuit IEC 60909 from the list of available analyses in the
Simulation toolbar (to activate this toolbar, go to View > Toolbars>
b. You can also select this analysis from the Analysis > Fault Analysis >
Short-circuit IEC 60909 menu option. c. The Short-Circuit IEC 60909
dialog box is composed of four tabs that allow you to set the:
• Calculation Mode,
which includes a
network-wide short-
circuit analysis along
with the options for the
fault flow analysis of a
single fault.
• IEC Short-circuit
analysis Parameters,
including Fault Current
type, Duty types, R/X
Ratio, Impedance
Correction Factors and
to include or not motor
contributions.
• The Short-Circuit
Rating tab where you
d. For the purposes of this tutorial, select Short-Circuit Levels at all Buses
and Nodes as the Calculation Mode.
4. Parameters
5. Simulation Results
a. Activate the Tag Layer toolbar in View > Toolbars > Tag Layer.
c.You can click on the icon to customize the tag results available.
6. Result Boxes
a. To display the Short-Circuit IEC 60909 result box, press Ctrl-6 from your
keyboard or go to View > Result Box > Short-Circuit Box. To see the
results, click on any element.
7. Graphs
a. Let us now add the fault level MVA keywords to the Summary on all buses
layer.
d. Select IEC 60909 Short-Circuit – Summary on all Buses from the Tag
Layer toolbar, and click on to access that layer tag properties.
c. Select the “Bus” option
under the Network Tags
category to display the tag
defined for buses.
d. Click on the
button
to access the list of
keywords available.
e. Select the
keywords as
listed in the table
below.
Component Keywords
Description
Bus $NodeId$
$IEC_LLL_Initial$
$IEC_LLL_ip$
$IEC_LLL_Ib$
$IEC_LLL_Ik$
$IEC_LLL_Idc$
Note: Inside the Format field, characters in black are user text and
characters in blue appearing between “$” are the software keywords.
a. Scroll down the list of Symbols to display in the left-hand side to find
the Abnormal conditions category. b. Expand the list.
c. Select the abnormal conditions you wish to display. Only the abnormal
conditions relevant to the current studies (such as the withstanding and
interrupting ratings for the short circuit study) will be highlighted.
f. Results can be viewed by accessing the Load Flow Result Box (Ctrl-V).
With this result box opened, click on any node/section of the network and
view its results in the box.g. Results of the Fault Flow analysis can also be
displayed in reports. The Fault Flow reports can be found in Report >
Analysis and select Valid Analysis
Reports.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
1. Getting Started
2. Network Description
3. Short-Circuit Analysis
a. Select Short-circuit IEC 61363 from the list of available analyses in the
Simulation toolbar (to activate this toolbar, go to View > Toolbars>
• IEC Short-circuit
analysis Parameters,
including Interrupting
Time, Time Parameters
and Time Constant.
• Calculation Mode,
which includes a Pre-
Fault Voltage, Fault
Impedances, Impedance
Adjustments and the
Equipment
CYMDIST – Training Manual 171 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
Contributions.
• The Output tab, which includes the reports and one line diagram result
tags that you want to display upon completion of the analysis.
Note: For more explanations and details about the parameters, you located
right top of Short-Circuit IEC 61363 windows to open the
associated help file.
b. Click on the
button to generate the
graph of the Short-Circuit
IEC 61363 for the Bus
B1. Click on
Close to dismiss the
Chart Selector and view
the graph.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
1. Getting Started
a.Open the self contained study:
SwitchOptimiz.sxst.
d. After running a Load flow analysis, the one line diagram would be color-coded
as shown.
You can see that the feeders GA04 and GA05 have an overload (yellow color)
and an under voltage (red color) problem. Both feeders GA05 and GA04 are
experiencing many abnormal conditions.
2. Switch Load from Feeder to Feeder Automatically
d. Click on Parameters.
n. You should obtain the following report with all the switching operations and
the feeder’s summary.
A self-contained study file (.sxst) to use with this tutorial is provided. The
explanations below are based on the use of it.
1. Getting Started
b. The first tab is used to define the sections of the feeder that have experienced
an outage.
c. The Contingency
CYMDIST – Training Manual 178 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
Assessment and
Restoration analysis
module can simulate
single or multiple
contingencies (non
simultaneous) on given
networks. These outages
can be saved in a text
file, which can be loaded
and applied on the
network for any future
contingency analysis
studies. To locate an
outage text file, click on
d. For the purposes of this tutorial, an outage on Sections 9509 and 13072 is
to be simulated.
e. You can use the Find ( ) command to locate a desired device or a section
using its ID. Once located in the tree list, place a check mark next to the ID
of the device or section you wish to use for your analysis. You can save these
selections in a new .txt file for future use.
The second tab is used to specify the objective functions as shown below.
analysis with a new study base case (undo all modifications) or with the
currently loaded study with all applied modifications.
• The Contingency Analysis module offers five Objective Functions with the
option to apply a weight factor for each objective. However, note that the
restoration of service will always start with restoring power according to the
priority set in the Restoration Priority group box.
f. For the
purposes of this
tutorial, select
the option Pick-
up the
customers by
switching as
the restoration
mode,
g. Start with
a base case.
h. Check the
four objective
functions as
shown.
i. The next step is to select the analysis Restriction tab to set the Loading
Limits of devices (contingency levels) for voltage drop analysis. The loading
limits should be at 100% for all devices.
j. Under Recovery Area, enter the value3 for the maximum layers of back up
feeders that may be used to pick up un- served customers.
For every switching scenario, the loading limits will be validated with the
load flow analysis to insure that none have been exceeded.
l. The Cold Load Pickup tab is used to define the analysis period along
with the load factors applied during that period.
m. Cold load
pick-up can be
specified by
entering Stage
1 (%) values in
the table of this
tab window.
This implies
that all un-
served
customers shall
be multiplied by
CYMDIST – Training Manual 181 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
these factors.
(Nominal Load
x Period Factor
x Stage Factor).
n. For the purposes of this tutorial, select Contingency Analysis as the
Analysis Period.
o. Click on the Display tab to select and specify color coding to be displayed
on the one-line-diagram along with the color of the open and closed device
tags.
q. The
General
Options group
box offers the
user the option
to display the
Navigator and
whether to
display
all feeders or not.
r. Contingency
Reports allows
the user to
define filters
for the outage
reporting
options. This
includes
outages with a
user defined
limit for un-
served
customers
such as more
than
100 KW, 1000 KW
or 5000 KW.
s. Select the error log and the weak points options to view the possible causes
that left
some customers un- served.
t. Once all the analysis parameters are set, click on the Run button.
The Display Options dialog box is the main interface for controlling and
customizing the network display. Use this command to customize the
equipment symbols, their color, the size of the text, the line thickness and
its type; and to display the network in different colors and modes, with or
without analysis results, etc
1. Getting Started
You open the Display Options dialog box by clicking the Display Options
button located in the Display toolbar, or by using the View > Display Options
menu item.
In any of the windows of the dialog box, clicking Save would save the changes
permanently, while clicking OK makes the changes applicable for the current
study only
b. The View Properties tab is used to customize the general look and feel of the
graphic user interface and what you would like to view in the workspace.
c. The Search tab allows users to search for a display option by typing in a
string.
2. Symbols
In the Symbols category, for each type of equipment, you can define the symbol
to be used in the O.L.D.
d. Finally, the Find field and button below the tree list are used to locate the
desired item to be modified. To do so, type in the name (or part of the name) of
the item wanted in the field and click onFind.
3. Color Coding
button.
Color Coding and click on . Once you have properly defined your layer, the
CYMDIST – Training Manual 188 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
4. Tags
Tags are boxes that appear on the one-line diagram at specific locations to
display information or results. The list of tag layers available can be found in
To add a new layer, go to Customize > One-Line Diagram > Tags and Text.
Once the Layer Properties dialog box is open, type in the layer name and
select its category and click OK. Once you have created the layer, select from
the list on the left hand side of the dialog box which devices require a tag.
Then select each device, and, in the Format field, type in the information to be
displayed in the tag of that device.
Click on the Keywords button in the dialog box to access the list of keywords
available and insert the keyword needed in the Format field. Text, border and
background of the tags can also be customized, and you can select among a
CYMDIST – Training Manual 190 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
5. Tooltips
Tooltips display information or results when the mouse cursor is kept idle on
a device for a few seconds. To view and modify existing layers, click on the
button Modify after selecting the layer from the drop-down menu. Select the
device in the list appearing on the left-hand side of the dialog box, and define
the contents of the tooltip for the device type selected in the Format group box.
Clicking on Keywords will display the Keyword Selection dialog box where
you can select and automatically insert the necessary keyword(s).
To create new layers for tooltips, go to Customize > One-Line Diagram >
Tooltips and click on Add.
The program is supplied with two layers already configured for the two most
common analyses performed – Voltage
Drop and Short-Circuit – where tooltips for devices display the corresponding
analysis results. Note that you can create a new tooltip layer for any analysis,
and modify the existing ones.
7. Search Tab
clicking on CYME
will direct you to the
appropriate dialog box where
you will be able to make the
appropriate changes.
1. Analysis
This menu command displays the
Analysis Reports dialog box that
will show all the reports available in
the software; and if an analysis has
just been executed, the list will
show only the reports relevant to
the analysis in question. This dialog
box can also be displayed by
clicking on the Reports button in
the Main toolbar. The reports
available in this dialog box are
classified into two categories:
Analysis and Input Data-Network.
The Analysis group includes the
reports available for each
simulation, and is classified within
the list under analysis type names.
You will find the explanations about
this category in this chapter. The
second category regroups reports
about the installed equipment. For
2. Report Properties
3. Keywords
4. Selection Tab
x Networks: To generate the reports for the networks selected in the tree list. If
you choose two or more networks, enabling the option Include all networks in
same report in the Report Properties dialog box of the reports selected will
CYMDIST – Training Manual 196 | P a g e
Network Analysis – CYMDIST :
`
GIS Based Distribution Network System and Preparation of
a 20 Years Distribution System Master Plan for DPDC
5. Output
Check the reports check boxes to display various analysis results reports after
the simulation.
A self-contained study file (.sxst) to use with this document is provided. The
explanations below are based on the use of that file.
1. Highlights
b. Select the Analysis > Load Flow menu option. Check that the Calculation
method is Voltage drop-unbalanced
c. Click on to Run
the analysis.
3. Comparison of Results
The following tables of comparison show the differences between CYME Load
flow analysis voltage drop unbalanced method results and those published in
the reference document. The percent difference for all bus voltages, voltages
angles, lines currents and currents angles is less than 0.44%*.
Bus Voltages
Voltages Angles
Lines Currents
Currents Angles
Notes: For regulators settings, since there are many solutions for tap
selection within their bandwidth using the R&X settings, results were obtained
using fixed taps. Cables (Undergrounds lines) were modeled as overheads lines
unbalanced to get unbalanced matrix impedances.
We suggest that you generate a report with these settings to ease the
comparison of the results: