Chief Executive Officer, ASCL apprised the meeting on the status of the
projects and the following decisions were arrived at:
7 Steps & Stairs Out of the 28 locations, work has stated only
improvement, Major & in one location i.e. near Sikulpuikawn. The
Minor Monitoring team visited the ongoing work in
the said location and found that about 80%
of the work has been completed in this
particular location. PMC & contractors are
instructed to pursue the supply of flooring
materials for speedy delivery at the site.
Construction of
Site development permit to be obtained from
20 Multipurpose Ground at
AMC and ASCL will submit an application to
High Field, Zarkawt
AMC for the same. Post construction
management / ownership to be worked out
as soon as possible.
21 Laldenga Cultural Centre Further decision to be taken on whether to
drop the project and work on alternative
projects.
22 Establishment of Aizawl Letter of acceptance given to contractor and
Tourism Centre performance guarantee is awaited.
23 Construction of Playground Site development permit to be obtained from
at Zemabawk AMC and ASCL will submit an application to
AMC for the same.
24 Construction of Playground Waiting shed toilet etc.
at Chite
25 Construction of Playground Site visit/inspection to be conducted at the
at Durtlang earliest.
26 Modernisation of Bara Work expected to take up at least 24 months.
Bazar – Trade Facility –
cum – Exhibition Areas
27 Construction of Smart AMC will write to the administrative
Street at Upper Khatla department on the issues and challenges
faced by them in connection with the
relocation of the market vendors to AMC
building at Tuikual for further necessary
action.
28 Energy Efficiency – LED Work expected to complete within 3 months.
Street lighting with Digital Priority is to be given to this project.
Hoarding
29 Energy Efficiency for Solar Work expected to complete within 3 months.
LED lighting with Digital Priority is to be given to this project.
Hoarding
30 Construction of Chaltlang Work expected to take up at least 24 months.
Sports Multipurpose Hall
31 On road Smart Parking Awaiting NOC from GAD. Meeting to be
including CCTV, Boom called with concerned stakeholders under the
chairmanship of the Hon’ble Deputy Chief
Minister, Mizoram.
32 Smart Water Management Project expected to be completed within 1
excluding ABD smart meter (one) year.
33 Establishment of Music
DPR is finalized and is to be submitted for
City
Government approval.
34 Urban Landscape – Avenue DPR to be submitted for Government
Plantation to increase approval by 20.01.2023 (Friday).
green cover and Bio
Remediation plants,
pollution absorbing plants
(LALMALSAWMA PACHUAU)
Secretary to the Government of Mizoram
Urban Development & Poverty Alleviation Department
Copy to:
1) PS to the Hon’ble Deputy Chief Minister, Mizoram.
2) PPS to Secretary, UD&PA Department.
3) Chief Executive Officer, ASCL.
4) All Members Concerned
5) Guard File.
(ZORAMSIAMA HMAR)
Under Secretary to the Govt of Mizoram
Urban Development & Poverty Alleviation Department