Professional Documents
Culture Documents
Prime ROMP REVed With PPT Slidesdocx
Prime ROMP REVed With PPT Slidesdocx
Prime ROMP REVed With PPT Slidesdocx
Issued: 2/6/2020
Revision: A
Revised: 3/17/2020
___________________________
A.Groenke
SPEED RACER Systems Engineering Lead
Approved By:
___________________________
J.Pokora
SPEED RACER Program Manager
___________________________
J.Scheinost
SPEED RACER Chief Engineer
___________________________
S.Hood
SPEED RACER Vehicle Lead
DOCUMENT CHANGE HISTORY
The table below illustrates the version of each document and the reasons for the
changes. Comparing two versions of the same document helps one identify
differences
Table of Contents
1.0 INTRODUCTION............................................................................................................ 1
1.1 Overview............................................................................................................................ 1
1.2 Applicable Documents..................................................................................................... 1
1.3 Risk and Opportunity Management Plan (ROMP)..........................................................2
1.3.1 Risk Matrix.................................................................................................................. 2
2.0 SCOPE............................................................................................................................... 3
2.1 Strategy.............................................................................................................................. 3
List of Tables
Table 1 – R/O Management Roles and Responsibilities
Table 2 – Risk Definitions......................................................................................9
Table 3 – Sample Mitigation Plan............................................................................
Table 4 – Probability of Occurrence........................................................................
List of Figures
Figure 1 - Continuous Lifecycle Process 1
Figure 2 - Risk Process Flow...................................................................................
Figure 3 – Identification Flowchart...........................................................................
Figure 4 – Risk Factor Guidelines...........................................................................
Figure 5 - R/O Life Cycle Actions........................................................................15
Figure 6 - R/O Terms Definitions.............................................................................
Figure 7 - Risk Identification Details....................................................................18
Figure 8 - Example Risk Analysis Framework.....................................................20
Figure 9 - PID Matrix...........................................................................................21
Figure 10 - Example Opportunity Analysis Framework.......................................22
Figure 11 - Risk Waterfall Chart..............................................................................
1.0 Introduction
1.1 Overview
1.2 Scope
This plan defines the methods and tools used throughout the ROM process to
accomplish the identification of R/Os on the SPEED RACER program. This plan
also identifies roles and responsibilities, process/organizational interfaces, and
guidelines for the identification, assessment, handling, monitoring, escalation,
and closure of risks at the functional level. The plan also illustrates different
documents that can provide different approaches when it comes to planning.
1.3
1.1 Strategy
The SPEED RACER program objectives are to develop the flight test vehicle as
outlined above while ensuring the efficient procurement of COTS subsystems,
and to demonstrate the Air System’s capabilities through two flight tests.
Additional program objectives include minimizing risk and cost by implementing
objective manufacturing technology, in addition to COTS subsystems,
prototyping the digital thread within the 3DX platform, and demonstrating a
foundation for the development of the Compact Multi-Mission Truck (CMMT).
3.0 Risk & Opportunity Management Board
3.1 Overview and Activities
A Risk and Opportunity Management Board (ROMB) occurs biweekly but can
occur more frequently based on program needs. A decision log will be
maintained within the digital thread to capture any actions, changes, or notes
made at each ROMB.
The SPEED RACER ROMB members are required stakeholders in the risk and
change management process. If a required member is unable to participate, a
delegate with decision-making authority must attend on behalf of the missing
participant. Multiple stakeholders may delegate to the same individual. For both
parties, the Program Manager and Chief Engineer hold the ultimate delegation of
authority and can veto other stakeholders at any time.
Risk Manager
Program Manager
Chief Engineer
Air Vehicle IPT Lead
Systems Engineering IPT Lead
Other Subject Matter Experts, as required
3.3 ROMB Roles and Responsibilities
IPT Lead Responsible for representing the IPT within the R/O process. Tasks include:
Accountable for all R/O items within their IPT
Review and assess all R/Os identified within IPT, including
subcontractors
Obtain/assign the necessary resources for R/O handling
Review and approve mitigation/achievement plans before implementation
Support Risk Manager in preparing R /O reports and briefing materials
for all management reviews
Keep customer and subcontractor counterparts informed on all team R/O
items and their status
Conduct internal R/O and watch item reviews within the IPT, as required
Member of CROMB
IPT Member Tasks include:
Table 1 – R/O Management Roles and Responsibilities
Term Definition
Candidate All risks begin as candidates when they are brought up by
anyone on the program. The ROMB can determine that
additional information is required before deciding to
acknowledge/board or reject the risk.
Watch Item/ ROMB determines the risk requires oversight and mitigation
Boarded
Mitigating/ Taking clear, discrete, and unplanned actions to reduce the
Emerging impact on the program
Closed Risk mitigated to an RPN the ROMB deems sufficient to no
longer warrant additional oversight or mitigation
Accepted ROMB has determined not to attempt to mitigate but instead
address any impacts if the risk realizes itself as an issue
Risk A potential undesirable event or threat that could affect the
project’s ability to meet its performance, cost, schedule, or other
objectives. It is an uncertain item, caused by external factors,
which may cause an execution failure in the project. A risk is an
item that has a measurable likelihood of occurrence and a
measurable negative impact on the project’s performance, cost,
schedule, and product delivery. A risk is an item that may occur
in the future and can be mitigated or prevented. Risks can be out
of the scope of control of the project and may require outside
resources to mitigate. Once the likelihood and impact are known
to be quantifiable, the items are then categorized as risks.
Opportunity An opportunity is an item that can either save cost or schedule
or add the capability to the system or program.
Issue An issue is an item with a measurable negative impact on a
project’s schedule, cost, or performance that is certain to occur
or has already occurred. An issue cannot be prevented; rather,
the final negative impact on the project can only be reduced.
Table 2 – Risk Definitions
The risk identification process is comprised of activities that highlight potential
R/Os that could increase or decrease the likelihood of meeting cost, schedule,
and/or performance objectives. Any project team member may and should
identify a potential R/O. R/Os are identified through ad-hoc working meetings,
team meetings, and/or one-on-one expert interviews. Potential R/Os are
documented at the IPT level for review and potential elevation to the ROMB. The
identification of R/Os is an iterative process. Potential R/O items are identified
throughout the life of the project through the performance of tasks and R/O
reviews performed at each ROMB meeting.
Risk statements must be worded with both IF and THEN statements: “IF [X
happens] THEN [it will have Y impact on the program].” The IF statement is a
description of a potential future event, while the THEN statement describes the
outcome/impact of the occurrence of that event. If a risk becomes an issue, the
issue retains the wording of a risk. Opportunities should be stated in the same
manner as risks.
The rating methodology used to rate and rank R/Os is outlined in AeroCode AC-
5601 and elaborated in section 6, Tools and Procedures. The Risk Manager will
input data into our selected risk management software that will auto-score the
risk level as determined by the standard scoring matrix. The risk level is
determined by evaluating the Likelihood of occurrence and the Impact of the risk
item. They are both scored from low to high.
The impact scoring criteria are subdivided into cost, schedule, and performance
impacts. The impact component of the risk level assumes the highest ranking of
the cost, schedule, and performance scores.
4.1.2.2 Risk Assessment
Each identified R/O is analyzed to assess the likelihood of occurrence and the
resulting impact. The combination of the likelihood and impact results in a score
that provides a means to rank the severity of R/O items. The use of a scoring
matrix and templates ensure consistency in scoring results. The order in which
the program addresses R/Os will be prioritized based on rating and its position in
the integrated master schedule (IMS).
The Risk Manager will interface with program and management personnel to
develop a Rough Order of Magnitude (ROM) dollar value estimate and schedule
impact assessment for each high and moderate R/O.
4.1.2.2.1 Probability of Occurrence
(2) Minor Schedule Slip 1-2 weeks and/or could impact non-
critical path milestones
No impact on key dates or critical path
These actions are represented in an accompanying risk waterfall chart (Figure 4),
which tracks the R/O mitigation progress. Each risk waterfall should show the
original R/O mitigation plan, the actual progress, and any revisions that have
taken place.
The four basic handling strategies for risk are: Avoid, Mitigate, Transfer, and
Accept.
· Avoid: Seeks to simply eliminate the event leading to the risk. This
option is often used in the proposal phase where diligent planning can
help avoid risk before execution either through contract language or
coordination with the customer.
If the Mitigate strategy is chosen, then handling steps for the risk must be
defined. For all risks that are scored High, regardless of strategy, a fallback plan
must be defined should the primary handling plan fail, or the risk occurs. Fallback
plans are developed with implementation criteria and decision dates to execute
the fallback plan should it become evident that the primary mitigation plan will not
succeed. Mitigation plans may be developed for Low risks but are not required by
this process.
4.1.4.2 Opportunity Handling Strategies
For opportunities, the steps would focus on achieving the benefit. Strategies for
capturing an opportunity can be assessed once the opportunity is adequately
defined. Like a risk, an opportunity has four basic handling strategies Exploit,
Share, Enhance, and Accept.
Speed Racer uses two tools for ROM, 3DX, and GitLab. The R/O register source
of truth is 3DX and is managed by the Risk Manager. Boarded 3DX risks are also
copied to Gitlab. In Gitlab, the risk is linked to related issues. Gitlab intends to
allow for higher participation and visibility among non-board members.
5.1 R/O Life Cycle Actions
Within the context of the SPEED RACER ROM process, an issue is NOT an
event for which there is no opportunity to reduce the cost/schedule/performance
impact or that currently exists within the existing scope of the Performance
Measurement Baseline. Instead, an issue should be outside the scope of
existing baselines and have adequate lead time to allow for the activities
defined within this ROMP. Issue Management is the continuous, reactive
process of identifying and assessing impacts, implementing handling plans to
reduce impacts, and monitoring those plans to completion. “Real-time” issues
that do not fall within the responsibility of the program team should be
communicated to the appropriate parties to support timely action and inclusion
into program baselines.
Like a risk, every opportunity has two components that must be assessed:
1) The probability of occurrence – measuring the likelihood of capturing the
opportunity.
2) The potential benefit – what, performance, schedule, or financial benefits
can be captured.
The SPEED RACER R/O approach places a primary focus on the identification
and management of situations that may cause potentially undesirable program
effects before they impact the health of the overall project. The process is
implemented continuously through the development lifecycle while regularly
updating and refining risk management data.
5.4 Planning
The planning step of R/O Management consists of all the activities resulting in
the creation of the R/O Management Plan (ROMP) following the requirements of
AC-5601.
When identifying R/Os, it is important to consider all possible sources that may
affect program performance baselines.
At the initial identification of a R/O, the details, source, and point(s) of contact
are entered into the SPEED RACER Risk Register within the digital thread.
The risk register is intended to capture details while the R/O is further
investigated and developed.
Candidate R/Os specifically proposed for ROMB review shall contain the
content outlined in Figure 3 - Risk Identification Details. Before a formal
CCRMB evaluation, R/Os will be entered into the risk management tool as an
“Emerging R/O” or “Watch Item” until sufficient information is available to fully
define it as a risk or opportunity. Emerging risks, opportunities, and watch
items are not active items and as such are not included in any risk metrics.
Realizing R/Os may be very complex and/or span many organizations. Each
captured item should be specific to a single root cause and able to be
addressed by a focused handling plan.
Field Description
The ROMB will review risk candidates for formalization. The SPEED RACER risk
manager will work with the board-designated risk owners to develop the required
inputs to the risk scoring tool. This includes a risk statement in the IF…THEN
format (“IF (undesirable event occurs) THEN (plan will change as a
consequence)” leading to the estimated impacts to cost, schedule, and
performance. The RMIS scoring template (found on the scoring tab) is used to
assess the likelihood and impact of the “IF” event on the program/project. It is
also used to assess the impact or consequence to schedule, cost, and
performance or other impact areas if needed. See Figure 8 - Example Risk
Analysis Framework for details of the risk analysis scoring template.
Opportunity Title
Opportunity Description
Likelihood of Success
Estimated ROM EAC Impact if Opportunity Achieved
Estimated Cost of Achieving Opportunity (cost of handling plan steps)
Opportunity Level
Opportunity Owner
The consequence is evaluated by answering the following question: “If the R/O is
realized, what will be the magnitude of the impact or benefit?” There are five
qualitative options used to classify the consequence of risk: Low, Minor,
Moderate, Significant, or High.
Quantitative data shall be considered when developing the handling plan and
includes:
R/Os approved as “program level” shall be elevated and handled per the SPEED
RACER ROMP and “Portfolio level” shall be elevated and handled per ISR &
UAS’s risk charter. Approved SPEED RACER program R/Os must have a
handling plan developed. The Systems Engineering IPT shall ensure that R/O
Owners create and sufficiently detail the handing plan and are submitted for
timely review and approval.
5.6 R/O Escalation
The SPEED RACER ROMB may approve a R/O for escalation to the associated
program or Aero’s BA leadership team based upon the level of potential impact,
need for a program or BA-level resources, and/or the appropriate level of
management to properly handle. Additionally, R/O initiators/owners are permitted
to elevate an item to the respective program in parallel (i.e. without prior SPEED
RACER CCRMB) if the scope of the risk is solely applicable to a singular
program and no advanced functional business area review is determined to be
warranted.
When elevated, the R/O Initiator / Owner shall formally coordinate this escalation
per each unique program or BA-level risk/opportunity management process. For
escalated R/Os, the functional area may provide recommendations for general
handling strategies but will not fully quantify the R/O or develop detailed handling
plans unless delegated to by the associated program(s) or BA-level leadership.
Upon elevation, a R/O will generally receive one of three dispositions and
corresponding action:
Approved as Program or BA-level Risk – The R/O is approved for the
program or BA-level ownership and managed in accordance with the
program's unique ROM process requirements. The Systems Engineering
IPT will retain a formal ‘Watch Item’ within the 3DX platform and capture
any business area-owned steps from within the approved handling plan for
tracking purposes.
Disapproved – The R/O is not approved by the program. Contingent upon
agreement by the SPEED RACER CCRMB, the originating IPT will
manage the risk in accordance with the CCRMB’s disposition and, as
appropriate, manage the handling plan.
Error: Reference source not found depicts the process flow for R/Os from
identification through the closure and the decision gate for when R/Os are
escalated or transferred to the functional, program, or Aero BA level. Error:
Reference source not found describes the elements of the CCRMB decision
gate.
5.7 R/O Metrics & Reports