2 Nos Bars 6 mm φ

Each 1400 mm Long

5 Nos Bars 6 mm φ
NH-72A
NH-72A NH-72A Each 375 mm Long

SECTIONAL PLAN Schedule of


Reinforcement when
R.C.C is used

ELEVATION

ELEVATION
ELEVATION FACE-II
FACE-I

SIDE ELEVATION

SECTIONAL PLAN
FRONT ELEVATION SIDE ELEVATION
DETAIL OF KILOMETRE STONE
DETAIL OF 200 METRE STONE
SECTIONAL PLAN

130
RB

G.L

A A

PLAN

ELEVATI0N SECTION A-A


SIDE ELEVATION
DETAIL OF BOUNDARY STONE
DETAIL OF FIFTH KILOMETRE STONE
NOTES -

1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE MENTIONED.


2. THE FIFTH KILMETRE/ KILOMETRE STONE SHALL BE CONSTRUCTED AS PER IRC:8-1980.
3. THE 200 METRE STONE SHALL BE CONSTRUCTED AS PER IRC:26-1967.
4. THE BOUNDARY STONE SHALL BE CONSTRUCTED AS PER IRC:25-1967.

CLIENT: AUTHORITY ENGINEER : EPC CONTRACTOR : PROJECT : CONCESSIONAIRE INDEPENDENT ENGINEER DRAWING TITLE : DRG. NO. CIPL/D1055/HW/DWG/SP/ 002
Checked By Checked By Checked By Approved By
FOUR LANING FROM KM. 100.757 TO KM. 107.350 Resident cum Highway/
GWALIOR SHIVPURI SECTION OF NH-46 PASSING
Construction Manager Project Manager Team Leader/Resident Engineer
KM,BOUNDARY STONE
THROUGH MADHAV NATIONAL PARK IN THE
Bridge/Structural Engineer
AS BUILT DRAWING
STATE OF MADHYA PRADESH ON EPC MODE BASIS
NATIONAL HIGHWAYS
LEA ASSOCIATES SOUTH DATE :
AUTHORITY OF INDIA ASIA PVT. LTD KRC INFRA PROJECTS PVT LTD. SCALE : AS SHOWN PAPER SIZE : A2