MCC PROCEDURES

AL AIN SANAIYA PROJECT APPROVAL


Stage 1: MCC ID Request
Once the project is awarded to your company, you will need to request for the MCC ID to proceed with the
installation by sending an email to mp@admcc.ae.
The below format must be followed.
(Email Subject: Al Ain Sanaiya - Entity Name – Entity Trade License No.) with the following documents:

• Award Letter
• Trade License of the Entity
• Project Registration Form
• MCC Evaluation Report

✓ Once the request has been received, MP will reply with “MCC ID”. After receiving the MCC ID,
installation, testing and commissioning can be proceeded.
Stage 2: Final Approval Request
After completing the work, you will need to reply to the same email with the following documents for final
approval:

• Project Registration Form


• Trade License of the Entity
• Site Visit Request Form
• Updated Drawings
• Technical Submittal Part 1
• Technical Submittal Part 2
– Snapshots for all cameras
– Add the EID copy of the signees on the password protection form
Reminders

1. Email subject should always include (Al Ain Sanaiya - Entity Name – Entity Trade License No.)

Example: (Al Ain Sanaiya - Baqala Stoud - CN-123456)

2. Always reply on the same email trail only, do not create a new email.

3. Only Al Ain Sanaiya Project drawing approval requests must be sent to mp@admcc.ae, any emails

not related to Al Ain Sanaiya Project drawing approvals will be automatically disregarded.

4. Incomplete documents will be rejected.

1|Page
Al Ain Sanaiya Project

MCC Compliance Flow Chart

MCC ID Request Final Approval


Installation Site Visit
Request

Send an email to MP (Email Subject: Al Ain


After completing the work, reply on the same email with
Sanaiya - Entity Name –Trade License No.)
the following documents for final approval:
with the following: • Project Registration Form
• Trade License of the Entity
• Award Letter
• Trade License of the Entity • Site Visit Request Form
• Project Registration Form • Updated Drawings
• MCC Evaluation Report • Technical Submittal Part 1
• Technical Submittal Part 2

Rectify the Complying


NO
comments

YES
Request for
Complying
Re-Visit

YES
After rectifying the comments send an email to
mp@admcc.ae and request for the revisit. Attached

Complying
the following if there is any changes on the drawings: Complying
• Updated Drawings
Certificate • Technical Submittal Part 1
Certificate
• Technical Submittal Part 2

2|Page

NOTE: Always reply on the same email trail only, do not create a new email.