Professional Documents
Culture Documents
CHAPTER 2 CP TR Gen
CHAPTER 2 CP TR Gen
Chapter 2:
❖ The typical level of correction that is requested is 0.85, 0.90, or 0.95. The
0.95 is very high but it is requested more recently.
Where:
𝑄𝐿 : Reactive power before compensate
𝑄𝑛𝑒𝑡 : Reactive power after compensated
Example
❖ For a 480Y/277V double ended unit substation with 4000A busses operating
an uncorrected 0.7 power factor, what size of capacitor will be needed for
correction to 0.85, 0.90 and 0.95 power factor?
Connection of capacitor
❖ There are two type for capacitor connection
▪ Delta connection
▪ Y connection
❖ Under-sizing
▪ A reduced efficiency when fully loaded
▪ On long-term overload, serious consequences for:
• resulting in failure of insulation and loss of the transformer
• overheating of the transformer causes protective relays to trip the
controlling circuit-breaker
Number of Transformer
❖ Surface of building or site
❖ Total power of the installed loads
❖ Power Interruption Sensitivity
❖ Disturbance Sensitivity
❖ Installation Scalability
Size Transformer
We can calculate by:
S
STr =
or K OL N
STr =ke S
N : Number of Transformer
S : Total Apparent Power
STr : Apparent Power of Transformer
KOL : Overload Capability Factor
Ke : Extension Factor
Generator Sizing
❖ The importance of maintaining a continuous supply raises the question of the
use of standby-power plant.
❖ Main characteristics to consider for the implementation of a LV back-up
generator:
▪ Site activity
▪ Total power of the installed loads
▪ Sensitive load to Power interruption
▪ Availability of the public distribution network