Work program of the three concrete chambers on the asphalt pavement in Maxinde V2

WM.06 VRP.01
Seal off the work area,cut and remove the
Seal off the work area,cut and remove the
9-Jun pavement,find the existing pipe,mark it,and
pavement, and find the existing pipe
backfill

10-Jun Excavation of the chamber

Keep excavation of the chamber, and cast the Seal off the work area,remove the pavement,start
11-Jun
concrete bed the excavation of the chamber

Close the water,connect to the existing pipeline


12-Jun Excavation of the chamber
and install the water meter

Keep excavation of the chamber, and cast the


13-Jun Start the reinforcement work
concrete bed

Continue the reinforcement work, then cast the


14-Jun Close the water,install the water meter
baseplate

15-Jun Excute the formwork Start the reinforcement work

Continue the reinforcement work, then cast the


16-Jun Excute the formwork
baseplate

17-Jun Cast the wall and the top plate Excute the formwork

18-Jun Maintain the concrete with water Excute the formwork

Maintain the concrete with water,backfill the


19-Jun Cast the wall and the top plate
trench,minimize the affection to the traffic

20-Jun Maintain the concrete with water Maintain the concrete with water

Maintain the concrete with water,backfill the


21-Jun Maintain the concrete with water
trench,minimize the affection to the traffic

22-Jun Maintain the concrete with water Maintain the concrete with water

23-Jun Maintain the concrete with water Maintain the concrete with water

24-Jun Maintain the concrete with water Maintain the concrete with water

25-Jun Maintain the concrete with water

26-Jun Maintain the concrete with water

27-Jun

28-Jun

1.The contractor will try the best to finish the work as soon as possible, minimizing the affection to the traffic;
2.The asphalt pavement rehabilatation of the chambers and connections to the existing pipe will be executed at the same time.And the date of the
Remark:
action is affected by the supplier.Before it, the contractor will provide temporary access.And if the plan is changed, the contractor will inform the
consult immediately.
1.The contractor will try the best to finish the work as soon as possible, minimizing the affection to the traffic;
2.The asphalt pavement rehabilatation of the chambers and connections to the existing pipe will be executed at the same time.And the date of the
Remark:
action is affected by the supplier.Before it, the contractor will provide temporary access.And if the plan is changed, the contractor will inform the
consult immediately.
he asphalt pavement in Maxinde V2

WM.07
Seal off the work area,cut and remove the
pavement,find the existing pipe,mark it,and
backfill

Seal off the work area,remove the pavement,start


the excavation of the chamber

Excavation of the chamber

Keep excavation of the chamber, and cast the


concrete bed

Close the water,install the water meter

Start the reinforcement work

Continue the reinforcement work, then cast the


baseplate

Excute the formwork

Excute the formwork

Cast the wall and the top plate

Maintain the concrete with water

Maintain the concrete with water,backfill the


trench,minimize the affection to the traffic

Maintain the concrete with water

Maintain the concrete with water

Maintain the concrete with water

Maintain the concrete with water

Maintain the concrete with water

he affection to the traffic;


ing pipe will be executed at the same time.And the date of the
ess.And if the plan is changed, the contractor will inform the
he affection to the traffic;
ing pipe will be executed at the same time.And the date of the
ess.And if the plan is changed, the contractor will inform the