Work Program of The Three Concrete Chanmbers On The Asphalt Pavement in Maxinde
Work Program of The Three Concrete Chanmbers On The Asphalt Pavement in Maxinde
WM.06 VRP.01
Seal off the work area,cut and remove the
Seal off the work area,cut and remove the
9-Jun pavement,find the existing pipe,mark it,and
pavement, and find the existing pipe
backfill
Keep excavation of the chamber, and cast the Seal off the work area,remove the pavement,start
11-Jun
concrete bed the excavation of the chamber
17-Jun Cast the wall and the top plate Excute the formwork
20-Jun Maintain the concrete with water Maintain the concrete with water
22-Jun Maintain the concrete with water Maintain the concrete with water
23-Jun Maintain the concrete with water Maintain the concrete with water
24-Jun Maintain the concrete with water Maintain the concrete with water
27-Jun
28-Jun
1.The contractor will try the best to finish the work as soon as possible, minimizing the affection to the traffic;
2.The asphalt pavement rehabilatation of the chambers and connections to the existing pipe will be executed at the same time.And the date of the
Remark:
action is affected by the supplier.Before it, the contractor will provide temporary access.And if the plan is changed, the contractor will inform the
consult immediately.
1.The contractor will try the best to finish the work as soon as possible, minimizing the affection to the traffic;
2.The asphalt pavement rehabilatation of the chambers and connections to the existing pipe will be executed at the same time.And the date of the
Remark:
action is affected by the supplier.Before it, the contractor will provide temporary access.And if the plan is changed, the contractor will inform the
consult immediately.
he asphalt pavement in Maxinde V2
WM.07
Seal off the work area,cut and remove the
pavement,find the existing pipe,mark it,and
backfill