REPORT

OF ELECTRICAL EQUIPMENT INSTALLATION

PROJECT: CHAU THON HYDROELECTRIC POWER PLANT


REPORT DATE: 21st Jan 2024

Page 1
I. Supervision work on the site:
1. Main activity.
No Time Contents Notes
15th Jan
- Travelling from Ha Noi to the site. Checking the
1 From 8AM-12AM
general condition of the plant.
From 1:30PM-5:30PM
- Meeting with Chau Thon project and discuss about
the plan for supervising of electrical equipment
installation works. Checking the civil work
16th Jan completed at the site. Discuss with Chau Thon and
2 From 8AM-12AM the contractor about some request to modify by
From 1:30PM-5:30PM Chau Thon. Make email to report to Ingeteam Spain
for the approval of the requested from Chau Thon.
- Contractor install cable tray, termination the LV
cable and control cable.
- Continue checking the civil work completed.
Checking drawing and found some difference
17th Jan between design drawing and the actual situation at
3 From 8AM-12AM the site.
From 1:30PM-5:30PM - Checking the diesel generator.
- Contractor install cable tray, termination the LV
cable and control cable.
- Checking drawing and correct the tagname of the
electrical control box in the Song Quang 110kV
substation as the requested from the contractor
18th Jan
because in the design drawing did not show the
4 From 8AM-12AM position of the boxes.
From 1:30PM-5:30PM - Checking the cable pulling;
- Contractor install cable tray, termination the LV
cable and control cable.
- Checking the DC Battery.
- Checking the cable pulling.
19th Jan
- Checking the cabinet installation.
5 From 8AM-12AM
- Checking the condition and information of the
From 1:30PM-5:30PM
temporary transformer at the intake area.
- Contractor terminate the HV cables and LV cables
20th Jan - Checking the cable pulling.
6
From 8AM-12AM - Making the report to Ingeteam.

Page 2
From 1:30PM-5:30PM - Disscussing and give out the solution for the Chau
Thon regards the DC batteries and charger room
changing.
- Contractor cleaning the bus-duct
- Terminating the cables

2. Estimation the schedule of installation.


Currently, the constractor did not submit the installation schedule to Ingeteam. In the owner
progress the project will be energyzing on 30th April 2024.
Status of works at the site:
Content of works Installation Notes
+A01 SWITCHGEAR OUTLET (10,5kV) Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+A02 SWITCHGEAR AUX. SERV. Installed Not yet connected the cable
(10,5kV)
to the grounding system,
not yet did the bolting work
to the foundation.
+A05 SWITCHGEAR_LOCAL GRID Owner would like to use
(35kV) the existing 35kV system
and would not install this
equipment.
+A10 SWITCHGEAR GENERATOR 1 Installed Not yet connected the cable
(10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A11 GROUND SWITCHGEAR Installed Not yet connected the cable
GENERATOR 1 (10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A20 SWITCHGEAR GENERATOR 2 Installed Not yet connected the cable
(10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A21 GROUND SWITCHGEAR Installed Not yet connected the cable
GENERATOR 2 (10,5kV) to the grounding system,
not yet did the bolting work

Page 3
to the foundation.
+A40
SWITCHGEAR_INTAKE&SPILLWAY
(35kV)
+C01 POWER METER CABINET Not in the Ingeteam scope
+T01 POWER TRANSFORMER Installed Not yet connected the cable
110/10,5kV to the grounding system,
not yet did the bolting work
to the foundation.
+C02 SUBSTATION CONTROL Installed Not yet connected the cable
CABINET to the grounding system,
not yet did the bolting work
to the foundation.
+C05 AUX. SERV. A.C. CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C06 EMERG. SERV. A.C. CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C07 AUX. SERV. DC/SAI CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+D01 DC CHARGER CABINET
+C04 COMMUNICATION CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C03 COMMON CONTROL CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C10 CONTROL CABINET UNIT 1 Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+E10 HYDRAULIC OIL UNIT 1 Not in the Ingeteam scope

Page 4
+G10 GENERATOR 1 Not in the Ingeteam scope
+C11 TURBINE GOVERNOR CABINET Not in the Ingeteam scope
UNIT 1
+C20 CONTROL CABINET UNIT 2 Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+E20 HYDRAULIC OIL UNIT 2 Not in the Ingeteam scope
+G20 GENERATOR 2 Not in the Ingeteam scope
+C21 TURBINE GOVERNOR CABINET Not in the Ingeteam scope
UNIT 2
+C31 POWER METER CABINET Not in the Ingeteam scope
(SONG-QUANG)
+C32 SUBSTATION CONTROL Installed Not yet connected the cable
CABINET (SONG-QUANG) to the grounding system,
not yet did the bolting work
to the foundation.
+C40 AUX SERV. A.C. CABINET
(INTAKE&SPILLWAY)
+D02 BATTERIES Changing the installation
location
+H10 COOLING SYSTEM UNIT 1
+F01 SURGE ARRESTER-1 110kV Installed Not yet connected the cable
to the grounding system,
not yet poured the grouting
for the structure
foundation.
+F02 SURGE ARRESTER-2 110kV Installed Not yet connected the cable
to the grounding system,
not yet poured the grouting
for the structure
foundation.
+F31 SURGE ARRESTER 110kV Installed Not yet connected the cable
(SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+G01 DIESEL GENERATOR AUX Installed Not yet connected the cable

Page 5
to the grounding system,
not yet did the bolting work
to the foundation.
+G40 DIESEL GENERATOR
(INTAKE&SPILLWAY)
+I01 LINE CIRCUIT BREAKER 110kV Installed Not yet connected the cable
(52L1) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+I31 CIRCUIT BREAKER 110kV
(SONG-QUANG)
+S01 DISCONNECTOR 110kV (89L1) Installed Not yet connected the cable
to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S30 DISCONNECTOR-1 110kV Installed
(89B2) (SONG-QUANG)
+S31 DISCONNECTOR-2 110kV Installed
(89L2) (SONG-QUANG)
+T02 VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T02A VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase A
to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T02B VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase B to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T02C VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase C to the grounding system,
not yet poured the grouting

Page 6
for the structure
foundation.
+T03 CURRENT TRANSFORMER Installed Not yet connected the cable
110kV to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T03A CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase A to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T03B CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase B to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T03C CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase C to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T04 AUX. TRANSFORMER 1 Installed Not yet connected the cable
10,5/0,4kV to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T05 AUX. TRANSFORMER 2 Owner would like to use
35/0,4kV the existing 35kV system
and would not install this
equipment.
+T32 VOLTAGE TRANSFORMER
110kV (SONG-QUANG)
+T32A VOLTAGE TRANSFORMER
110kV Phase A (SONG-QUANG)
+T32B VOLTAGE TRANSFORMER
110kV Phase B (SONG-QUANG)
+T32C VOLTAGE TRANSFORMER
110kV Phase C (SONG-QUANG)

Page 7
+T33 CURRENT TRANSFORMER
110kV (SONG-QUANG)
+T33A CURRENT TRANSFORMER
110kV Phase A (SONG-QUANG)
+T33B CURRENT TRANSFORMER
110kV Phase B (SONG-QUANG)
+T33C CURRENT TRANSFORMER
110kV Phase C (SONG-QUANG)
+T40 AUX. TRANSFORMER 35/0,4kV
(INTAKE&SPILLWAY)
+X01 POWER TRANSFORMER Installed Not yet connected the cable
CONNECTION BOX to the grounding system.
+X02 VOLTAGE TRANSFORMERS Installed Not yet connected the cable
110kV CONNECTION BOX to the grounding system.
+X03 CURRENT TRANSFORMERS Installed Not yet connected the cable
110kV CONNECTION BOX
to the grounding system.
+X10 TERMINAL BOX1 GENERATOR Not in the Ingeteam scope
U1 (ACB0)
+X10A TERMINAL BOX2 GENERATOR Not in the Ingeteam scope
U1 (ACB2)
+X10B TERMINAL BOX3 GENERATOR Not in the Ingeteam scope
U1 (ACBH)
+X11 TERMINAL BOX TURBINE U1 Not in the Ingeteam scope
+X11A TERMINAL BOX 1 TURBINE Not in the Ingeteam scope
U1
+X11B TERMINAL BOX 2 TURBINE Not in the Ingeteam scope
U1
+X11C TERMINAL BOX 3 TURBINE Not in the Ingeteam scope
U1
+X11D TERMINAL BOX 4 TURBINE Not in the Ingeteam scope
U1
+X11E TERMINAL BOX 5 TURBINE U1 Not in the Ingeteam scope
+X11F TERMINAL BOX 6 TURBINE U1 Not in the Ingeteam scope
+X12 TERMINAL BOX HYDRAULIC Not in the Ingeteam scope
OIL UNIT 1
+X13 TERMINAL BOX VALVES UNIT 1 Not in the Ingeteam scope
+X14 TERMINAL BOX COOLING Not in the Ingeteam scope
SYSTEM UNIT 1

Page 8
+X20 TERMINAL BOX GENERATOR Not in the Ingeteam scope
U2 (ACB0)
+X20A TERMINAL BOX2 GENERATOR Not in the Ingeteam scope
U2 (ACB2)
+X20B TERMINAL BOX3 GENERATOR Not in the Ingeteam scope
U2 (ACBH)
+X21 TERMINAL BOX1 TURBINE U2 Not in the Ingeteam scope
+X22 TERMINAL BOX HYDRAULIC Not in the Ingeteam scope
OIL UNIT 2
+X21A TERMINAL BOX 1 TURBINE Not in the Ingeteam scope
U2
+X21B TERMINAL BOX 2 TURBINE Not in the Ingeteam scope
U2
+X21C TERMINAL BOX 3 TURBINE Not in the Ingeteam scope
U2
+X21D TERMINAL BOX 4 TURBINE Not in the Ingeteam scope
U2
+X21E TERMINAL BOX 5 TURBINE U2 Not in the Ingeteam scope
+X21F TERMINAL BOX 6 TURBINE U2 Not in the Ingeteam scope
+X23 TERMINAL BOX VALVES UNIT 2 Not in the Ingeteam scope
+X24 TERMINAL BOX COOLING Not in the Ingeteam scope
SYSTEM UNIT 2
+X32 JUNCTION BOX VOLTAGE
TRANSFORMER (SONG-QUANG)
+X33 JUNCTION BOX CURRENT
TRANSFORMER (SONG-QUANG)
+S01A DISCONNECTOR 110kV (89L1- Installed Not yet connected the cable
G-1) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S01B DISCONNECTOR 110kV (89L1- Installed Not yet connected the cable
G-2) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S31A DISCONNECTOR 110kV (89L2- Installed Not yet connected the cable
G-1) to the grounding system,

Page 9
not yet poured the grouting
for the structure
foundation.
+S31B DISCONNECTOR 110kV (89L2- Installed Not yet connected the cable
G-2) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S30A DISCONNECTOR 110kV Installed Not yet connected the cable
(89B2-G-1) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+H20 COOLING SYSTEM UNIT 2 Not in the Ingeteam scope
Grounding system The under ground system
had finished
Cable tray installation On going
Cable pulling On going
Cable connection On going
Cable testing Not yet started

Progress Table:
Content of works Percentage Total percentage
Cabinet (Take 60% of 62% 37%
works)
Pulling and terminating 51% 15%
cable (Take 30% of works)
Testing (Take 10% of 0% 0%
works)
Total progress 53%
Estimated time to complete all the remaining works: 5 weeks at least not including lunar
New Year holidays.
3. Reason of delay schedule.
No comment.
4. Comment about the quality of installation.

Page 10
Ingeteam has requested contractor and Chau Thon to connect the grounding cables for
installed cabinets to the grounding system, and measured the grounding system’s resistance
to ensure the safety.
5. HSE.
No comment.
6. Conclusion.
Up to now, the installation schedule for the Ingeteam’s equipment and cables is OK.
Chau Thon, 21st Jan 2024

Nguyen Manh Hung

Page 11
PICTURES OF CHECKING/INSPECTION ON
THE SITE

Page 12
Picture 1: Checking the condition at Chau Thon substation site on 15th Jan, 2024

Picture 2: Checking the Song Quang substation

Page 13
Picture 3: Control room at the Chau Thon HPP

Picture 4: Cable terminating

Page 14
Picture 5: Checking the civil dimension

Page 15
Picture 6: Solving the problem with cable terminating for cabinet C05

Page 16
Picture 7: Cheking the Diesel Generator

Page 17
Picture 8: HV Cable terminating

Page 18
Picture 9: Cable tray installing

Page 19
Picture 10: Checking the DC batteries

Page 20
Picture 11: Cable connecting

Page 21
Picture 12: Checking the cabinet installation

Page 22
Picture 13: Checking the temporary transformer at intake area

Page 23