Report On 10th March 2024
Report On 10th March 2024
Page 1
I. Supervision work on the site:
1. Main activity.
No Time Contents Notes
Contractor:
th
04 Feb - Making the MV cables terminating at connection
1 From 8AM-4PM box G10 & G20.
Testing:
- Testing HV equipment of Song Quang substation.
Contractor:
- Contractor terminates the control cables at C20, C10
cabinets.
05th Feb - Making the MV cables terminating at connection
2 From 8AM-12AM box G10 & G20.
From 1:30PM-5:30PM Testing:
- Testing HV cabinets at Chau Thon HPP.
- Testing motors.
- Go back to Hanoi
- Solving the issue for cables at the site.
- Modification the correct position of terminal for
WF158,258.
06th Feb Contractor:
3 From 8AM-12AM - Contractor terminates the control cables at C20, C10
From 1:30PM-5:30PM cabinets.
- Making the MV cables terminating at connection
box G10 & G20.
- Terminating the cables at diesel gernerator,
- Checking the cabinets and list out remaining works.
- Find out the matter at the C10 cabinet: missing parts
U05, U31, U32, U33 and report to Ingeteam, Chau
Thon.
07th Feb
Contractor:
4 From 8AM-12AM
- Contractor terminates the control cables at C20, C10
From 1:30PM-5:30PM
cabinets.
- Making the HV cables terminating at Main
transformer bus duct side.
- Terminating the cables at C07.
5 08th Mar - Checking the cabinets and list out remaining works.
Page 2
From 8AM-12AM Contractor:
From 1:30PM-5:30PM - Contractor terminates the control cables at C11
cabinets.
- Making the HV cables terminating at Main
transformer bus duct side.
- Terminating the cables at X10 box.
- Checking the cabinets and list out remaining works.
- Making report and the acceptance minutes for the
supervision job.
- Making the as-built and revised for the drawing and
th
09 Mar cable list.
6 From 8AM-12AM Contractor:
From 1:30PM-5:30PM - Contractor terminates the control cables at C11
cabinets.
- Making the HV cables terminating at Main
transformer bus duct side.
- Terminating the cables at X10 box.
10th Mar
7 - Go back to Hanoi as the requested from Chau Thon
From 8AM-4PM
Page 3
equipment.
+A10 SWITCHGEAR GENERATOR 1 Installed Not yet connected the PE
(10,5kV) cable to the grounding
system, not yet did the
bolting work to the
foundation.
+A11 GROUND SWITCHGEAR Installed Not yet connected the PE
GENERATOR 1 (10,5kV) cable to the grounding
system, not yet did the
bolting work to the
foundation.
+A20 SWITCHGEAR GENERATOR 2 Installed Not yet connected the PE
(10,5kV) cable to the grounding
system, not yet did the
bolting work to the
foundation.
+A21 GROUND SWITCHGEAR Installed Not yet connected the PE
GENERATOR 2 (10,5kV) cable to the grounding
system, not yet did the
bolting work to the
foundation.
+A40 Owner would like to use
SWITCHGEAR_INTAKE&SPILLWAY the existing 35kV system
(35kV)
and would not install this
equipment.
+C01 POWER METER CABINET Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+T01 POWER TRANSFORMER Installed Not yet connected the PE
110/10,5kV cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C02 SUBSTATION CONTROL Installed Not yet connected the PE
CABINET cable to the grounding
system, not yet did the
bolting work to the
Page 4
foundation.
+C05 AUX. SERV. A.C. CABINET Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C06 EMERG. SERV. A.C. CABINET Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C07 AUX. SERV. DC/SAI CABINET Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+D01 DC CHARGER CABINET Installed Not yet connected the PE
cable to the grounding
system.
+C04 COMMUNICATION CABINET Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C03 COMMON CONTROL CABINET Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C10 CONTROL CABINET UNIT 1 Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C11 TURBINE GOVERNOR CABINET Installed Not yet connected the PE
UNIT 1 cable to the grounding
system, not yet did the
bolting work to the
foundation.
Page 5
+C20 CONTROL CABINET UNIT 2 Installed Not yet connected the PE
cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C21 TURBINE GOVERNOR CABINET Installed Not yet connected the PE
UNIT 2 cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C31 POWER METER CABINET Installed
(SONG-QUANG)
+C32 SUBSTATION CONTROL Installed Not yet connected the PE
CABINET (SONG-QUANG) cable to the grounding
system, not yet did the
bolting work to the
foundation.
+C40 AUX SERV. A.C. CABINET Waiting for the
(INTAKE&SPILLWAY) construction works
finished.
+D02 BATTERIES Located Changing the installation
location, not yet fix
equipment, not yet pulled
cables.
+F01 SURGE ARRESTER-1 110kV Installed Not yet connected the PE
cable to the grounding
system.
+F02 SURGE ARRESTER-2 110kV Installed Not yet connected the PE
cable to the grounding
system.
+F31 SURGE ARRESTER 110kV Installed Not yet connected the PE
(SONG-QUANG) cable to the grounding
system.
+G01 DIESEL GENERATOR AUX Installed Not yet connected the PE
cable to the grounding
system.
+G40 DIESEL GENERATOR Waiting for the
(INTAKE&SPILLWAY) construction works
finished.
Page 6
+I01 LINE CIRCUIT BREAKER 110kV Installed Not yet connected the PE
(52L1) cable to the grounding
system.
+I31 CIRCUIT BREAKER 110kV Installed Not yet connected the PE
(SONG-QUANG) cable to the grounding
system.
+S01 DISCONNECTOR 110kV (89L1) Installed Not yet connected the PE
cable to the grounding
system.
+S30 DISCONNECTOR-1 110kV Installed Not yet connected the PE
(89B2) (SONG-QUANG) cable to the grounding
system.
+S31 DISCONNECTOR-2 110kV Installed Not yet connected the PE
(89L2) (SONG-QUANG) cable to the grounding
system.
+T02 VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV cable to the grounding
system.
+T02A VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV Phase A cable to the grounding
system.
+T02B VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV Phase B cable to the grounding
system.
+T02C VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV Phase C cable to the grounding
system.
+T03 CURRENT TRANSFORMER Installed Not yet connected the PE
110kV cable to the grounding
system.
+T03A CURRENT TRANSFORMER Installed Not yet connected the PE
110kV Phase A cable to the grounding
system.
+T03B CURRENT TRANSFORMER Installed Not yet connected the PE
110kV Phase B cable to the grounding
system.
+T03C CURRENT TRANSFORMER Installed Not yet connected the PE
110kV Phase C cable to the grounding
Page 7
system.
+T04 AUX. TRANSFORMER 1 Installed Not yet connected the PE
10,5/0,4kV cable to the grounding
system.
+T05 AUX. TRANSFORMER 2 Owner would like to use
35/0,4kV the existing 35kV system
and would not install this
equipment.
+T32 VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV (SONG-QUANG) cable to the grounding
system.
+T32A VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV Phase A (SONG-QUANG) cable to the grounding
system.
+T32B VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV Phase B (SONG-QUANG) cable to the grounding
system.
+T32C VOLTAGE TRANSFORMER Installed Not yet connected the PE
110kV Phase C (SONG-QUANG) cable to the grounding
system.
+T33 CURRENT TRANSFORMER Installed Not yet connected the PE
110kV (SONG-QUANG) cable to the grounding
system.
+T33A CURRENT TRANSFORMER Installed Not yet connected the PE
110kV Phase A (SONG-QUANG) cable to the grounding
system.
+T33B CURRENT TRANSFORMER Installed Not yet connected the PE
110kV Phase B (SONG-QUANG) cable to the grounding
system.
+T33C CURRENT TRANSFORMER Installed Not yet connected the PE
110kV Phase C (SONG-QUANG) cable to the grounding
system.
+T40 AUX. TRANSFORMER 35/0,4kV Owner would like to use
(INTAKE&SPILLWAY) the existing 35kV system
and would not install this
equipment.
+X01 POWER TRANSFORMER Installed Not yet connected the PE
CONNECTION BOX cable to the grounding
Page 8
system.
+X02 VOLTAGE TRANSFORMERS Installed Not yet connected the PE
110kV CONNECTION BOX cable to the grounding
system.
+X03 CURRENT TRANSFORMERS Installed Not yet connected the PE
110kV CONNECTION BOX cable to the grounding
system.
+X32 JUNCTION BOX VOLTAGE Installed Not yet connected the PE
TRANSFORMER (SONG-QUANG) cable to the grounding
system.
+X33 JUNCTION BOX CURRENT Installed Not yet connected the PE
TRANSFORMER (SONG-QUANG) cable to the grounding
system.
+S01A DISCONNECTOR 110kV (89L1- Installed Not yet connected the PE
G-1) cable to the grounding
system.
+S01B DISCONNECTOR 110kV (89L1- Installed Not yet connected the PE
G-2) cable to the grounding
system.
+S31A DISCONNECTOR 110kV (89L2- Installed Not yet connected the PE
G-1) cable to the grounding
system.
+S31B DISCONNECTOR 110kV (89L2- Installed Not yet connected the PE
G-2) cable to the grounding
system.
+S30A DISCONNECTOR 110kV Installed Not yet connected the PE
(89B2-G-1) cable to the grounding
system.
Grounding system The under ground system The resistance of earthing
had finished system when Testing
company measured is 0.94
Ohm, need to reduce this
value.
Cable tray installation Finished
Cable pulling On going
Cable connection On going
Equipment testing On going
Page 9
Progress Table:
Content of works Percentage Total percentage
Cabinet (Take 60% of 95% 57%
works)
Pulling and terminating 89% 27%
cable (Take 30% of works)
Testing (Take 10% of 20% 2%
works)
Total progress 86%
Estimated time to complete all the remaining works: 2 weeks at least (not including the
intake area where have to wait for the construction works).
3. Reason of delay schedule.
No comment.
4. Comment about the quality of installation.
Ingeteam has requested contractor and Chau Thon to connect the grounding cables for
installed cabinets to the grounding system, currently the measured value for the grounding
system’s resistance is 0.94 Ohms as the result of testing company tested at the site; it’s
exceed the allowable value of the Vietnamese standard for resistance of 110kV station. So
need to add more grounding electrodes of find the way to reduce the earthing system
resistance.
5. HSE.
No comment.
6. Conclusion.
Up to now, the installation schedule for the Ingeteam’s equipment and cables is OK.
Chau Thon, 9th Mar 2024
Page 10
PICTURES OF CHECKING/INSPECTION ON
THE SITE
Page 11
Picture 1: Making the MV cables terminating at connection box G10 & G20
Page 12
Picture 2: Testing HV equipment of Song Quang substation
Page 13
Picture 3: Testing HV cabinets at Chau Thon HPP
Page 14
Picture 4: Contractor terminates the control cables at C20, C10 cabinets
Page 15
Picture 5: Testing motors
Page 16
Picture 6: Testing motors
Page 17
Picture 7: Correct the terminal connecting for cables WF158,258
Page 18
Picture 8: Find out the missing parts U05, U31, U32, U33 at the C10 cabinet
Page 19
Picture 9: Making the HV cables terminating at Main transformer bus duct side
Page 20
Picture 10: Terminating the cables at C07
Page 21
Picture 11: Contractor terminates the control cables at C11 cabinets
Page 22
Picture 12: Terminating the cables at X10 box
Page 23
AS-BUITL DRAWING AND MODIFICATION AT SITE
Page 24
1. Cable No. WF158:
In the design drawing:
Infact, at the cabinet don’t have connection point 22,23. After checking and measuring the
continuity from the CB to find the correct position I found need to change to 20,21 as bellows:
Page 25
3. Cable No. WC 110:
Need to modify as follows
Page 26
In fact: Connect to FPRM
Page 27
5. Cable No. WF092
In the design drawing:
Page 28
In fact: Connect to CB for charging battery of DG.
Page 29
At this connecting point:
Page 30
Modified:
Page 31
7. Cable No. WC015
In the design drawing:
Page 32
Page 33
8. Cable No. WF075
In the design drawing:
Page 34
Infact do not have terminal X01, must to modify:
Page 35
Must connect to XT1-20 and XT1-21
Page 36
Page 37