I. Supervision work on the site:
1. Main activity.
No Time Contents Notes
26th Feb
1 From 8AM-4PM - Travel from Ha Noi to the site.
Page 2
From 8AM-12AM - Fixing cables.
From 1:30PM-5:30PM - Contractor terminates the control cables at C20, C10
cabinets.
- Making the MV cables terminating at connection
box G10 & G20.
Testing:
- Testing HV equipment of Chau Thon substation.
- Testing HV cabinets at Chau Thon HPP.
Page 3
+A21 GROUND SWITCHGEAR Installed Not yet connected the cable
GENERATOR 2 (10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A40
SWITCHGEAR_INTAKE&SPILLWAY
(35kV)
+C01 POWER METER CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+T01 POWER TRANSFORMER Installed Not yet connected the cable
110/10,5kV to the grounding system,
not yet did the bolting work
to the foundation.
+C02 SUBSTATION CONTROL Installed Not yet connected the cable
CABINET to the grounding system,
not yet did the bolting work
to the foundation.
+C05 AUX. SERV. A.C. CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C06 EMERG. SERV. A.C. CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C07 AUX. SERV. DC/SAI CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+D01 DC CHARGER CABINET Installed Not yet connected the cable
to the grounding system.
+C04 COMMUNICATION CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C03 COMMON CONTROL CABINET Installed Not yet connected the cable
to the grounding system,
Page 4
not yet did the bolting work
to the foundation.
+C10 CONTROL CABINET UNIT 1 Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C11 TURBINE GOVERNOR CABINET Installed Not yet connected the cable
UNIT 1 to the grounding system,
not yet did the bolting work
to the foundation.
+C20 CONTROL CABINET UNIT 2 Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C21 TURBINE GOVERNOR CABINET Installed Not yet connected the cable
UNIT 2 to the grounding system,
not yet did the bolting work
to the foundation.
+C31 POWER METER CABINET Installed Not in the Ingeteam scope
(SONG-QUANG)
+C32 SUBSTATION CONTROL Installed Not yet connected the cable
CABINET (SONG-QUANG)
to the grounding system,
not yet did the bolting work
to the foundation.
+C40 AUX SERV. A.C. CABINET
(INTAKE&SPILLWAY)
+D02 BATTERIES Located Changing the installation
location
+H10 COOLING SYSTEM UNIT 1
+F01 SURGE ARRESTER-1 110kV Installed Not yet connected the cable
to the grounding system.
+F02 SURGE ARRESTER-2 110kV Installed Not yet connected the cable
to the grounding system.
+F31 SURGE ARRESTER 110kV Installed Not yet connected the cable
(SONG-QUANG)
to the grounding system.
+G01 DIESEL GENERATOR AUX Installed Not yet connected the cable
to the grounding system.
+G40 DIESEL GENERATOR
Page 5
(INTAKE&SPILLWAY)
+I01 LINE CIRCUIT BREAKER 110kV Installed Not yet connected the cable
(52L1) to the grounding system.
+I31 CIRCUIT BREAKER 110kV Installed Not yet connected the cable
(SONG-QUANG) to the grounding system.
+S01 DISCONNECTOR 110kV (89L1) Installed Not yet connected the cable
to the grounding system.
+S30 DISCONNECTOR-1 110kV Installed Not yet connected the cable
(89B2) (SONG-QUANG) to the grounding system.
+S31 DISCONNECTOR-2 110kV Installed Not yet connected the cable
(89L2) (SONG-QUANG) to the grounding system.
+T02 VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV to the grounding system.
+T02A VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase A to the grounding system.
+T02B VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase B to the grounding system.
+T02C VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase C to the grounding system.
+T03 CURRENT TRANSFORMER Installed Not yet connected the cable
110kV to the grounding system.
+T03A CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase A to the grounding system.
+T03B CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase B to the grounding system.
+T03C CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase C to the grounding system.
+T04 AUX. TRANSFORMER 1 Installed Not yet connected the cable
10,5/0,4kV
to the grounding system.
+T05 AUX. TRANSFORMER 2 Owner would like to use
35/0,4kV the existing 35kV system
and would not install this
equipment.
+T32 VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV (SONG-QUANG) to the grounding system.
+T32A VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase A (SONG-QUANG) to the grounding system.
Page 6
+T32B VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase B (SONG-QUANG) to the grounding system.
+T32C VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase C (SONG-QUANG) to the grounding system.
+T33 CURRENT TRANSFORMER Installed Not yet connected the cable
110kV (SONG-QUANG) to the grounding system.
+T33A CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase A (SONG-QUANG) to the grounding system.
+T33B CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase B (SONG-QUANG) to the grounding system.
+T33C CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase C (SONG-QUANG) to the grounding system.
+T40 AUX. TRANSFORMER 35/0,4kV
(INTAKE&SPILLWAY)
+X01 POWER TRANSFORMER Installed Not yet connected the cable
CONNECTION BOX to the grounding system.
+X02 VOLTAGE TRANSFORMERS Installed Not yet connected the cable
110kV CONNECTION BOX to the grounding system.
+X03 CURRENT TRANSFORMERS Installed Not yet connected the cable
110kV CONNECTION BOX to the grounding system.
+X32 JUNCTION BOX VOLTAGE Installed Not yet connected the cable
TRANSFORMER (SONG-QUANG)
to the grounding system.
+X33 JUNCTION BOX CURRENT Installed Not yet connected the cable
TRANSFORMER (SONG-QUANG) to the grounding system.
+S01A DISCONNECTOR 110kV (89L1- Installed Not yet connected the cable
G-1) to the grounding system.
+S01B DISCONNECTOR 110kV (89L1- Installed Not yet connected the cable
G-2) to the grounding system.
+S31A DISCONNECTOR 110kV (89L2- Installed Not yet connected the cable
G-1) to the grounding system.
+S31B DISCONNECTOR 110kV (89L2- Installed Not yet connected the cable
G-2) to the grounding system.
+S30A DISCONNECTOR 110kV Installed Not yet connected the cable
(89B2-G-1) to the grounding system.
Grounding system The under ground system
had finished
Cable tray installation Finished
Page 7
Cable pulling On going
Cable connection On going
Cable testing On going
Progress Table:
Content of works Percentage Total percentage
Cabinet (Take 60% of 95% 57%
works)
Pulling and terminating 84% 25%
cable (Take 30% of works)
Testing (Take 10% of 10% 1%
works)
Total progress 83%
Estimated time to complete all the remaining works: 3 weeks at least.
3. Reason of delay schedule.
No comment.
4. Comment about the quality of installation.
Ingeteam has requested contractor and Chau Thon to connect the grounding cables for
installed cabinets to the grounding system, currently the measured value for the grounding
system’s resistance is 0.94 Ohms as the result of testing company tested at the site; it’s
exceed the allowable value of the Vietnamese standard for resistance of 110kV station. So
need to add more grounding electrodes of find the way to reduce the earthing system
resistance.
5. HSE.
No comment.
6. Conclusion.
Up to now, the installation schedule for the Ingeteam’s equipment and cables is OK.
Chau Thon, 2nd Mar 2024
Page 8
PICTURES OF CHECKING/INSPECTION ON
THE SITE
Page 9
Picture 1: Contractor drilling the holes for bus bar of the generator electrical connection box
Page 10
Picture 2: After drilling the additional holes for MV cables connection at G10, G20 connection box
Page 11
Picture 3: Fabricating and installing the support for MV cables to the generator connection box
(G10, G20)
Page 12
Picture 4: Installing the turbine govenor control unit 1 & 2 (C11, C21)
Page 13
Picture 5: Pulling control cables
Page 14
Picture 6: Testing Company arrived to the site to start testing job
Page 15
Picture 7: Pulling and fixing control cables
Page 16
Picture 8: Testing company test the resistance of the grounding system
Page 17
Picture 9: The earthing system resitance value while testing
Page 18
Picture 10: Control cables pulling
Page 19
Picture 11: Testing HV equipment of Chau Thon substation
Page 20
Picture 12: Fabricating & installing the cable ladder to X10 and X20
Page 21
Picture 13: Contractor terminates the control cables at C20, C10 cabinets
Page 22
Picture 14: Testing HV equipment of Chau Thon substation
Page 23
Picture 15: Testing HV equipment of Chau Thon HPP
Page 24
Picture 16: Making the MV cables terminating at connection box G10 & G20
Page 25
Picture 17: Testing main transformer
Page 26
Picture 18: Testing MV cabinets
Page 27