Professional Documents
Culture Documents
Conventional Operations Manual
Conventional Operations Manual
Rig At Location
Operations Manual
Client Name
Rev.0
Date
Aker Marine Contractors, Inc.
Client
Rig
Conventional Mooring At Location
Operations Manual
1.0 INTRODUCTION
3.0 EQUIPMENT
6.0 SCHEDULE
7.0 SAFETY
Aker Marine Contractors, Inc. Revision 0
BP Amoco Project # 7338
Ocean America Preset Mooring At GC-563 Page 4 of 10
Operations Manual April
19, ,1999
1.0 INTRODUCTION
Aker Marine Contractors has developed a conventional mooring system for the Rig to be
moored in Location. The water depth at the well head is approximately W.D. ft and the
water depth over the mooring spread ranges from W.D. ft to W.D. ft.
The Rig will be moored at Location using a conventional mooring system with a rig
heading of Heading° in approximately W.D. ft water depth at the well head, and a water
depth ranging from W.D. ft to W.D. ft. The composition of the mooring legs at this
location is as follows. The mooring will have a Spread Type spread.
Conventional Moorings
Mooring Composition
Table 2.0-1 shows the coordinates for the mooring system at Location. Figure 2.0-1
shows the plan view of the mooring system.
Table 2.0-1
Coordinates for Location Conventional Mooring
Mooring Center Coordinates:
X = X coordinate’ Rig Heading
Heading°
Y = Y coordinate’
Leg Leg Water Anchor Coordinates Horizontal Dist.
Heading Depth Fairlead to
No. (deg) (ft) X (ft) Y (ft) Anchor (ft)
1 xx xx xx xx xx
2 xx xx xx xx xx
3 xx xx xx xx xx
4 xx xx xx xx xx
5 xx xx xx xx xx
6 xx xx xx xx xx
7 xx xx xx xx xx
8 xx xx xx xx xx
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Conventional Mooring At Location Page 6 of 10
Operations Manual
Date
3.0 EQUIPMENT
The equipment necessary to setout the moorings at Location with the Vessel is
summarized in Table 3.0-1.
Table 3.0-1
SETOUT EQUIPMENT LIST (For One AHTS)
Item Quantity Description
The equipment necessary to perform the recovery operations is summarized in Table 3.0-
2.
Table 3.0-2
RECOVERY EQUIPMENT LIST (For One AHTS)
Item Quantity Description
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Conventional Mooring At Location Page 7 of 10
Operations Manual
Date
The following procedures detail the steps to setout the moorings at Location using the
Vessel. The order in which the legs will be setout will be determined on site. Presumably,
the primary legs will be setout first. After the primary legs have been setout the four breast
legs will be setout. A minimum of # towing vessels are needed until four legs are set out.
The order in which the legs will be recovered will be determined on site. Presumably, the
breast legs will be recovered first. After breast legs have been recovered, the four primary
legs will be recovered. The following procedures are for the recovery of the conventional
mooring legs. A minimum of # towing vessels will be needed once four legs are recovered.
6.0 SCHEDULE
It is estimated that it should take estimated time to setout the moorings at location. This
assumes that vessel and vessel will be used on the setout. It is estimated that it should
take estimated time to recover the moorings at location. This assumes that vessel and
vessel will be used on the recovery.
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Conventional Mooring At Location Page 10 of 10
Operations Manual
Date
7.0 SAFETY
All operations shall be performed in a safe manner. Safety has the highest priority of all,
and before any work is started, each department manager (i.e., deck foremen, captains,
etc.) must ensure all operations are performed in a safe manner. The job should always be
organized with safety as the dominant issue. All personnel should be continuously
informed and updated as to possible risks involved in the operations.
A safety meeting will be held aboard each vessel involved in the operation prior to the
commencement of work. In addition a meeting will be held aboard the rig prior to the
hook-up and disconnect operations.
SAFETY BRIEFING
Running Wires
AHTS Heaving and Buoy Heave
Personnel Deck Responsibilities Clearly Defined
Only Designated Personnel Will Give Winch Instructions
Only Designated Personnel Will Communicate Between The Vessels
Be Deliberate Throughout Task Execution - If You Aren’t Sure, Don’t Do It
Inform Deck Foreman Immediately of Anything that Compromises Safety on
Deck
Do Not Attempt to Operate Deck Equipment With Which You Are Unfamiliar
If You Are Not on Shift, Stay Clear of Deck Operations
Be Aware and Observe Specific Safety Instructions Given By Vessel Captains Or
Designated Supervisors
Task Specific Safety Meetings to be Arranged BY ANYONE if Required
Follow Vessel Rules
Be Considerate of Those Off Shift Trying To Rest –
Immediately inform AMC Representative Of Any Incidents. AMC Representative
to further report to Drilling Contractor and Client, both verbally and later, in a
written report.