Professional Documents
Culture Documents
Preset Operations Manual
Preset Operations Manual
Rig At Location
Operations Manual
Client Name
Rev.0
Date
Aker Marine Contractors, Inc.
Client
Rig
Preset Mooring At Location
Operations Manual
1.0 INTRODUCTION
3.0 EQUIPMENT
8.0 SCHEDULE
9.0 SAFETY
Aker Marine Contractors, Inc. Revision 0
BP Amoco Project # 7338
Ocean America Preset Mooring At GC-563 Page 4 of 13
Operations Manual April
19, ,1999
1.0 INTRODUCTION
Aker Marine Contractors has developed a preset mooring system for the Rig to be installed
in Location. The water depth at the well head is approximately W.D. ft and the water
depth over the mooring spread ranges from W.D. ft to W.D. ft.
The Rig will be moored at Location using a preset mooring system with a rig heading of
Heading° in approximately W.D. ft water depth at the well head, and a water depth
ranging from W.D. ft to W.D. ft. The composition of the mooring legs at this location is
as follows. The mooring will have a Spread Type spread.
Preset Moorings
Mooring Composition
Table 2.0-1 shows the coordinates for the mooring system at Location. Figure 2.0-1
shows the plan view of the mooring system when connected and when buoyed off.
Table 2.0-1
Coordinates for Location Preset Mooring
Mooring Center Coordinates:
X = X coordinate’ Rig Heading
Heading°
Y = Y coordinate’
Leg Leg Water Anchor Coordinates Horizontal Dist.
Heading Depth Fairlead to
No. (deg) (ft) X (ft) Y (ft) Anchor (ft)
1 xx xx xx xx xx
2 xx xx xx xx xx
3 xx xx xx xx xx
4 xx xx xx xx xx
5 xx xx xx xx xx
6 xx xx xx xx xx
7 xx xx xx xx xx
8 xx xx xx xx xx
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Preset Mooring At Location Page 6 of 13
Operations Manual
Date
3.0 EQUIPMENT
The equipment necessary to preset the moorings at Location with the Vessel is
summarized in Table 3.0-1.
Table 3.0-1
PRESET MOORING EQUIPMENT LIST
Item Quantity Description
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Preset Mooring At Location Page 7 of 13
Operations Manual
Date
Table 3.0-2
HOOK-UP EQUIPMENT LIST (For One AHTS)
Item Quantity Description
Table 3.0-3
DISCONNECT EQUIPMENT LIST (For One AHTS)
Item Quantity Description
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Preset Mooring At Location Page 8 of 13
Operations Manual
Date
The following procedures detail the steps to install the mooring system at Location using
the Vessel.
The order in which the legs will be hooked up will be determined on site. Presumably, the
primary legs will be hooked-up first. After the primary legs have been connected, the four
breast legs will be connected. The following procedures are for the hook up of the steel
catenary mooring legs. A minimum of # towing vessels are needed until four legs are
hooked up.
1. The AHTS will deck the surface buoy and connect the workwire to the pendant
wire;
2. The AHTS will pull toward the MODU Once the catenary is formed the J-lock
will slip off and AHTS heaves it in (Figure XX);
3. The AHTS will back up to the required fairlead;
4. The MODU will pass the rig chain to the AHTS, which will secure it in a pelican
hook or 2nd deck stopper (Figure XX);
5. The MODU will pay out rig chain as the AHTS heaves in the pendant wire
(Figure XX);
6. The AHTS will secure the end of the mooring wire in the shark’s jaw (Figure
XX);
7. The mooring wire will be connected to the rig chain (Figure XX);
8. The J-lock chaser will be connected to the rig chain and will take the load;
9. Both the pelican hook and the shark jaw’s will be released;
10. The AHTS will lower the J-lock while the rig heaves in chain (Figure XX);
11. Once the catenary is formed the J-lock will slip off and AHTS heaves it in.
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Preset Mooring At Location Page 10 of 13
Operations Manual
Date
1. Vessel rigs J-lock chaser on work wire and maneuvers close to MODU.
2. Rig heaves in chain as directed by AMC Rig Coordinator.
3. AHTS lowers J-lock chaser and maneuvers into position (as directed by the AMC
Field Engineer) to engage chain;
4. AHTS engages chain with J-lock chaser approximately 200 ft from the chain/wire
connection (Figure XX);
5. Once the AHTS informs the MODU the chaser is at the proper location, the MODU
begins to pay out chain until there is ~ 2,500 – 3,000 ft of chain outboard;
6. After the rig pays out all of the chain, the AHTS recovers the J-lock chaser. The J-
lock chaser is recovered on deck (Figure XX);
7. The AHTS will walk chain on deck as necessary until the catenary wire can be placed
in the shark’s jaw. Attach a pelican hook (or 2nd shark jaws) to the rig chain and
release the J-lock chaser (Figure XX);
8. Break the connecting link between the chain and wire and connect the pendant wire
to the catenary mooring wire (Figure XX);
9. AHTS pays out pendant while the MODU heaves in chain (Figure XX);
10. When the MODU has ~200 ft of chain out the AHTS will pass the end of the chain
back to rig (Figure XX)
11. AHTS moves away from the rig, connects buoy to the pendant wire, and overboards
buoy.
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Preset Mooring At Location Page 11 of 13
Operations Manual
Date
The procedures for recovering the moorings at location are summarized below.
8.0 SCHEDULE
It is estimated that it should take estimated time to set the preset moorings at location.
This assumes that # systems are moved at a time on the vessel. Hook-up and disconnect
should take estimated time hours for each operation (assuming vessels utilized).
Aker Marine Contractors, Inc. Rev
Client Project #
Rig Preset Mooring At Location Page 13 of 13
Operations Manual
Date
9.0 SAFETY
All operations shall be performed in a safe manner. Safety has the highest priority of all,
and before any work is started, each department manager (i.e., deck foremen, captains,
etc.) must ensure all operations are performed in a safe manner. The job should always be
organized with safety as the dominant issue. All personnel should be continuously
informed and updated as to possible risks involved in the operations.
A safety meeting will be held aboard each vessel involved in the operation prior to the
commencement of work. In addition a meeting will be held aboard the rig prior to the
hook-up and disconnect operations.
SAFETY BRIEFING
Running Wires
AHTS Heaving and Buoy Heave
Personnel Deck Responsibilities Clearly Defined
Only Designated Personnel Will Give Winch Instructions
Only Designated Personnel Will Communicate Between The Vessels
Be Deliberate Throughout Task Execution - If You Aren’t Sure, Don’t Do It
Inform Deck Foreman Immediately of Anything that Compromises Safety on
Deck
Do Not Attempt to Operate Deck Equipment With Which You Are Unfamiliar
If You Are Not on Shift, Stay Clear of Deck Operations
Be Aware and Observe Specific Safety Instructions Given By Vessel Captains Or
Designated Supervisors
Task Specific Safety Meetings to be Arranged BY ANYONE if Required
Follow Vessel Rules
Be Considerate of Those Off Shift Trying To Rest –
Immediately inform AMC Representative Of Any Incidents. AMC Representative
to further report to Drilling Contractor and Client, both verbally and later, in a
written report.