Siddababa Tunnel Project

Daily Progress Report


Date: Tuesday, June 4, 2024 Day: Sunny/Cloudy/ Rainy
Rainfall: Max. Temp: 34°C Min Temp. : 22°C Humidity: 63%
Working Time from 07:00 AM to 06:00 PM (Day Shift) , 07:00 to 6:00AM(Night Shift)
1.1 Personnel-Technical Staff 1.2 Personnel-Service & Support 1.3 Personnel-Operator
S.N. Description Name Nos S.N. Description Nos S.N. Description Nos
Public Relation Officer (Mr. Mahendra Poudel)
1. Project Manager Mr.Zhou He You 1 11. 1 19. Driver 5

20. Operator 6
Mr.Yan Wei Safety Engineer/ Manager/Officer
2. Procurement Officer 2 12. 1
Mr. Zheng Hongjiang (Mr.Huang Yi Cheng)

13. Translator (Mr. Abhishek Sharma , Mr.Jit Tamang, Mr.


3. Warehouse Manager Mr.Li Jin Lian 1 4
Ranjit Regmi,Mr. Ramesh Pandey)

4. Accountant Mr.Lin Jiang Feng 1 14. Account Helper(Nisha Pandey) 1

5. Geologist Mr.Ganga Ram Maharjan 1 15. IPC engineer(Suman Gautam) 1


Mr. Su Guo Fa , Mr.Liang 16. Cook 5
Hao, Mr. Zhao 17. Cleaner 2
Chen Peng, Mr.Lei Hong 18. Security Guard 6
Jun Mr. Chen Shao
Lin Mr. Li Tang
Pei Mr. Xu Xiao Po
Mr. Yudhisthir Panthi
Mr. Shreejesh Poudel
Mr. Hunag Yichen
6. Tunnel/Site/Civil Engineers Mr.Huang Guiping 18
Mr.Huang Hudi Mo
Mr.Wu Jian Guo
Mr.San jui(shotcrete operator)
Mr. Kaushal Raut
Mr. Deepak Sunar
Mr. Kaushal Raut
Mr.Suresh Ayer

7. Mechanical/Material Engineer Mr.Kshitiz Khanal 1

Mr. Zhang Ze Peng Mr.


Mohan Bohara Mr.
8. Surveyor 3
Harka Bista .

Mr.Zhang Jin Gui


Mr.Aklesh Kr. Sahani,
9. Lab Engineer/Technician Mr.Sandip Kandel 4
Mr.Deepak Bastola

10. QA/QC Engineer Kushal Gautam 1


Total 33 Total 21 Total 11
21. North Portal Site 22. Main Tunnel /South Portal Site

Welder/Carpenter/ Barbender/ Shotcrete


Driller/Shotcrete worker 4 2 Shotcretor/ Mason Skilled/scaffolder 4 Electrician/welder 2
worker/Traffice Controller

11 12
Electrician/operators 0 Shotcretor/ Mason Unskilled Driller 0 Operator 3

Technician/Supervisor 3 Extra technician 2 Technician/ Supervisor 3 Extra technician 0

23. Workshop 24. By-Pass 2

Welder /skilled 1 Electrician Helper Worker 4 Driller

Shotcretor/ Mason
Worker 2 Operators 5 Technical/Supervisior 2 6
Unskilled

Technician/Supervisor 2 Extra Technician Electrician Safety officer

25. Slope Protection MR 1 & Road maintenace work 26. BY-Pass 1and By-pass 3
Driller/Shotcrete worker
7 Worker at road maintenace 10 Worker in By-Pass 3 4 Driller in By-Pass 1 4
in MR-1
Workers/Operators in MR- 23 Technical/Supervisi 12
4 0 Technical/Supervisior in By-Pass 3 2 2
1 or in By-Pass 1
Technician/Supervisor in
2 0 Electrician/welder
MR-1
Grand Total 134

2. Major Equipment at site

Hrs. Down Description Down


S.N. Description Nos Hrs. Down time S.No. Description Nos Down time S.N. Description Nos Hrs. S.No. Nos Hrs.
time time

Concrete High Pressure Double


Excavator 12+12 Pneumatic Jaak Hammer 12X5+3
1. 5 0 7. Transit 3 6+6+6 0 13. 32 0 19. Fluid Grouting Pump 1 0 0
+12 X4
Mixer
Drilling
Hydraulic Pressure Breaker 12+12 6 Concrete Batching Plant Dry Shotcrete machine
2. 3 0 8. Machine 1 0 14. 1 6 0 20. 4 0+0+0+0 0
+0
(ROC)/DTH
10+10 Ground Robotic Shotcrete
3. Hilux / Pickup 5 +10+1 0 9. Concrete 1 0 0 15. Generator (400 KW) 1 0 0 21. 1 6 0
Machine
0+10 Pump

Air
4. Tripper 11 6X11 0 10. 4 12+0+0+0 0 16. Generator (600 KW) 1 0 0 22. Core cutter 8 0 18
Compressor

Grouting
5. Wheel Loader 3 6+8+6 0 11. Machine 1 2 0 17. Electric Compressor 1 0 0 23. Potable air compressor 1 12 0
(Low

6. Jumbo drill 0 0 0 12. Jet Fan 2 6+4 0

Add: No.15 Sanlihe Road, Haidian District, Beijing, china Post code: 100029 Tel: +86-10-8649 6111/6222 Fax: +86-10-8649 6100 Email: cscec_siddababa@163.com Website: www.cscec.com
Siddababa Tunnel Project
Daily Progress Report
Date: Tuesday, June 4, 2024 Day: Sunny/Cloudy/ Rainy
Rainfall: Max. Temp: 34°C Min Temp. : 22°C Humidity: 63%
Working Time from 07:00 AM to 06:00 PM (Day Shift) , 07:00 to 6:00AM(Night Shift)

Conducted Ref. Description


S.N. Test/Sampling/Inspect Ref. Standard Description (Test code) Test Machine S.N. Test/Sampling/ Inspect Test Machine
No. of Test Standard (Test code)

28 days Compressive strength


test of shotcrete C25/30 at CSCEC-STP-ST-20240507-
1. EN 12390-3 Automatic compressive strength test machine 3.
North main tunnel rib to rib 1
K1+976.2-973.8

7 days Compressive strength


test of first shotcrete C25/30 CSCEC-STP-ST-20240506-
2. EN 12390-3 Automatic compressive strength test machine 3.
at south main 2
tunnel,K0+991.5-997

28 days Compressive
strength test of early strength
CSCEC-STP-EM-20240507-
3. mortar Rockbolt grouting at EN 445 Automatic flexural & compressive strength test machine. 3.
1
North main tunnel,K1+976.2-
973.8

7 days Compressive strength


test of early strength mortar CSCEC-STP-EM-20240528-
4. EN 445 Automatic flexural & compressive strength test machine. 3.
Rockbolt grouting at south 1
main tunnel,K0+911.5-997.0

Particle density & water


absorption test of coarse CSCEC-STP-CA-20240603-
5. EN 1097-6 Pycnometer
aggregate (8/4) mm after 24 1
hrs.

Blasting Material log

S.N Detonator Delay No. Quantity Aviable Quantity Demanded Consumed Quantity Remaining Quantity

1 10424
NED-1 40 85 10339
2 2358
NED-3 40 31 2327
3 3829
NED-5 20 34 3795
4 10279
NED-7 40 70 10209
5 9596
NED-9 47 68 9528
6 13213
NED-11 40 71 13142
7 14040
NED-13 50 96 13944
8 0
NED-15 0 0 0
Emulsion-(Power
9 36911.8 750 737.6 36174.2
Gel)32mm
10 ED 1362 1358
8 4
11

12

Add: No.15 Sanlihe Road, Haidian District, Beijing, china Post code: 100029 Tel: +86-10-8649 6111/6222 Fax: +86-10-8649 6100 Email: cscec_siddababa@163.com Website: www.cscec.com
Siddababa Tunnel Project
Daily Progress Report
Date: Tuesday, June 4, 2024 Day: Sunny/Cloudy/ Rainy
Rainfall: Max. Temp: 34°C Min Temp. : 22°C Humidity: 63%
Working Time from 07:00 AM to 06:00 PM (Day Shift) , 07:00 to 6:00AM(Night Shift)

5. Material available (Permanent works)

Balancce Quantity Up to Quantity Production/ Remain-ing


S.N. Material Unit QA/QC Ref. available Consumption Qty this Day QA/QC Supply Ref Remarks
previous day Supply this day Qty

CSCEC-STP-CA-
1. Aggregates(8 mm) MT -7,358.21 -36.00 -7,394.21
20231004-1

CSCEC-STP-CA-
2. Aggregates(16mm) MT 30.05 30.05
20231004-2

CSCEC-STP-CA-
3. Aggregates(22.4mm) MT 108.57 108.57
20231005-1

CSCEC-STP-FA-
4. Sand MT -934.08 -50.98 -985.06
20231009-1

CSCEC-STP-C-20231008-
5. Cement MT -29.87 -21.840 -51.71
1

CSCEC-STP-R-20231014-
6. Rebar 6mm(500 D) Kg 381.74 -984.00 -602.26
1

CSCEC-STP-R-20231014-
7. Rebar 8mm Fe500D Kg 6,418.00 6,418.00
2

CSCEC-STP-R-20231013-
8. Rebar 12mm Fe500D Kg -2,073.58 -2,073.58
1

CSCEC-STP-R-20231013-
9. Rebar 20mm Fe500D Kg 5,051.19 5,051.19
3

CSCEC-STP-R-20231013-
10. Rebar 25mm Fe500D Kg -26,740.83 -418.27 -27,159.10
4

11. Plate 3.60mm-4.00 4X16 Kg 40,922.10 40,922.10

12. BL Pipe 6.00'' (H) m -84.00 -84.00

13. BL Pipe 8.00'' (H) m 21.20 21.20

CSCEC-STP-SA-
2. I-Beam (100 by 180) Kg 42,860.69 42,860.69
20231014-1

Chemicals-PCA-1
15. Kg -5,571.83 4572/079/080 -5,571.83
Admixture

233 Pcs of DCP Gewi bar CSCEC-STP-ANC-


16. pcs 54.00 54.00
with complete accessories 20231216-1

17. Plate 12mm x4x8 kg 5,800.00 5,800.00

6. Material available (Temporary works)

Balancce Quantity Up Quantity Production/ Remain-ing Remark


S.N. Material Unit QA/QC Ref. available Consumption Qty This Day QA/QC Supply Ref
to previous day Supply this Day Qty s

1. Cement MT 0.00 0.00

2. Sand MT 4.83 4.83

3. Aggregates(8 mm) MT 48.98 48.98

4. Aggregates(16mm) MT 0.00 0.00

5. Aggregates(22.4mm) MT 49.35 49.35

6. Rebar 6mm(500 D) kg

7. Rebar 20mm(500 D) kg

Add: No.15 Sanlihe Road, Haidian District, Beijing, china Post code: 100029 Tel: +86-10-8649 6111/6222 Fax: +86-10-8649 6100 Email: cscec_siddababa@163.com Website: www.cscec.com
Siddababa Tunnel Project
Daily Progress Report
Date: Tuesday, June 4, 2024 Day: Sunny/Cloudy/ Rainy
Rainfall: Max. Temp: 34°C Min Temp. : 22°C Humidity: 63%
Working Time from 07:00 AM to 06:00 PM (Day Shift) , 07:00 to 6:00AM(Night Shift)

7. Work Progress for General Works

S.N.
Description of
Ref. Map or Layout Codes in Lay Out Work Description Unit L B H Quantity Remarks
Item

Main Tunnel(south)
Blasting work South main tunnel at 4:19
kg 275.00
PM
K1+013.8 South main tunnel pull length 3.7m
i. DD-MT-19-A1 Sheet 1 of 2 Mucking work m3 280.00
Spraying of first layer of shotcrete
K1+010-K1+013.8 m3 18.00
C25/30
ii DD-SP-03-A2 South Slope protection work

Bypass
Blasting work at 8:32 AM kg 87.6
iii. DD-BP-04-A3 Sheet 1 of 1 L1K0+024.6 By-Pass 1
Mucking work m3 18.0

Excavation work by using core cutting


iv. DD-BP-05-A2 Sheet 1 of 1 L2K0+017 nos. 0 By-Pass 2
machine

Blasting work By-Pass 3(4:18PM) kg 100.00


v. DD-BP-06-A2 Sheet 1 of 1 L3K0+019.3 By-Pass 3 pull length 2m
Mucking work m3 30.00

MR-1
Sheet no.
vii. DD-RA-10-A1 K0+816-800 Installing 25mm dia rockbolt at H7.5-5.5 nos. 16
8,9,10,11,12,13 of 51

Main Tunnel North

Blasting work at 8:10 AM kg 275


K1+949.6 North main tunnel pull length 3.4m
Mucking work m3 205

viii. DD-MT-19-A1 Sheet 1 of 2 Installation of MS-III-A support system cycle 4

Installation of 25mm dia. Rockbolt of 3m


K1+962.7-1+957.9 nos. 40
length at 10-10-10-10-10-10 pattern

C25/30 shotcrete m3 30

9. RFI Note:

10. Social Issues If any:

11. Photos

Photo No. 1: MS-III-A support system installation work at North Main tunnel Photo No. 2: Face drilling work using explosives at South main tunnel

Photo No. 3:By-Pass-1 after using explosive Photo No. 4: North main tunnel after using explosives