Professional Documents
Culture Documents
BFD Asset Integrity Shellvis Rev01
BFD Asset Integrity Shellvis Rev01
1901
RESTRICTED
Basis for Design – Asset integrity Shellvis V-1901 project
Document History
Date Revision Reason for Author Reviewer/ PMF PTE PS Owner
Change
RESTRICTED - 2
Basis for Design – Asset integrity Shellvis V-1901 project
CONTENTS
Document History....................................................................................................................................2
Part I – General Information....................................................................................................................5
1. Introduction.......................................................................................................................6
1.1. Scope of the Document..........................................................................................6
1.2. Project Overview....................................................................................................6
1.3. Location of the Project...........................................................................................6
1.4. Objectives...............................................................................................................6
1.5. Outline of Existing Facilities..................................................................................6
1.6. Scope overview/summary......................................................................................6
1.6.1. General................................................................................................................6
1.6.2. Equipment List....................................................................................................7
1.7. Interfaces................................................................................................................8
1.7.1. Interfaces with Plant Electrical supply................................................................8
1.7.2. Interfaces with Control supply............................................................................8
1.7.3. Interfaces with Other system...............................................................................8
2. Nomenclature/Abbreviations............................................................................................9
3. Project Level Requirements / General Design Considerations.......................................11
3.1. Standardisation Requirements..............................................................................11
3.2. HSSE & SP...........................................................................................................11
3.2.1. Health & Human Factor Engineering (HFE)....................................................11
3.2.2. Process Safety...................................................................................................12
3.3. Key current equipment parameters.......................................................................12
3.4. Material Selection.................................................................................................13
3.5. Operations & Maintenance...................................................................................13
3.5.1. Mode of operations...........................................................................................13
3.5.2. Maintainability..................................................................................................13
4. Site & Engineering Data.................................................................................................14
5. Process system................................................................................................................17
5.1. Process and Instrumentation Diagrams................................................................17
5.2. Design basis..........................................................................................................17
5.3. Main technical risks..............................................................................................18
5.4. Power Generation.................................................................................................18
5.5. Instrument and Tool Air.......................................................................................18
6. Utility systems.................................................................................................................19
RESTRICTED - 3
Basis for Design – Asset integrity Shellvis V-1901 project
7. Interfaces / Tie-ins...........................................................................................................20
8. General/Common Facilities & Systems..........................................................................21
8.1. Facility Layout......................................................................................................21
8.2. Civil/Structural/Architectural...............................................................................22
8.2.1. Structural Improvement....................................................................................22
8.2.2. Civil Works.......................................................................................................22
8.3. Instrumentation & control....................................................................................22
8.3.1. Automation, control, and optimisation..............................................................22
8.3.2. Instruments........................................................................................................22
8.4. Mechanical engineering........................................................................................22
8.4.1. V-1901 Inspection.............................................................................................23
8.4.2. New nozzles in V-1901.....................................................................................23
8.4.3. New in line mixer M-1902................................................................................23
8.4.4. Piping................................................................................................................23
8.4.5. Venting..............................................................................................................24
8.5. Electrical...............................................................................................................24
8.5.1. Frequency converter..........................................................................................24
9. Standards, Codes and Regulations..................................................................................26
9.1. Standards Philosophy...........................................................................................26
9.2. Selection of Engineering Standards......................................................................26
9.3. Selection of Specific Standards for the project....................................................26
10. Further study...................................................................................................................27
Appendix A. P&ID................................................................................................................................28
Appendix B. DRAWINGS....................................................................................................................29
Appendix C. List....................................................................................................................................30
Appendix D. Equipment Data sheet......................................................................................................31
RESTRICTED - 4
Basis for Design – Asset integrity Shellvis V-1901 project
RESTRICTED - 5
Basis for Design – Asset integrity Shellvis V-1901 project
1. Introduction
1.1. Scope of the Document
This document contains the BfD (Basis for Design) reactor revamping to improve control safety
process and warranty operativity on the unit known as Shellvis (V-1901) to be able to keep producing
lube oil in Tarragona LOBP.
The Shellvis unit has been operative for over 30 years, currently works to produce BC SL 2006,
S8551 and LUBAD.
In Tarragona LOBP is the only reactor that complies with the production of these products.
The Shell TARRAGONA LOBP is an existing Lube Oil Blending plant (LOBP) located in the
industrial area of LA CANONJA near the city of Tarragona in Spain.
1.4. Objectives
Provide the basis for design to warranty the operativity of the Shellvis unit and its installations.
Newton Ingenieros is the company involved in the development of the project in Bfd and BDEP
phases.
Tarragona LOBP produces lubricant products with the operation activities including raw material
(base oils, additives, packaging) storage and consumption, blending follows the formulation approved
from Regional Products Management, filling into packed products of different sizes (small pack,
pails, drums and IBC), warehouse and logistic (inbound/out bound).
All operation process and quality follow Shell Lubricant Quality System and HSSE management
system to ensure all operation activities are safe for people and environment.
Packed products are stored in the warehouse according to pack-sizes and dispatch per customer
orders. facilities that the project ties-into.
The Equipment called Shellvis (V-1901) is currently used as a reactor for the production of BC SL
2006, S8551 and LUBAD at the CPDL plant in Tarragona.
RESTRICTED - 6
Basis for Design – Asset integrity Shellvis V-1901 project
The purpose of this project and document is to describe the necessary actions to ensure the integrity of
the equipment, as assets, to guarantee its long-term operability and security, within the production and
operation lines of the CPDL and introduce those improvements identified and feasible.
This document describes the Basis for Design for the future phase of BDEP engineering and
execution for the total integrity of the asset.
Description of current facilities:
The current operation of the reactor is manually, through local operation using panel CP-1901, located
in the Shellvis building.
1.6.1. General
Associated equipment:
o Replace in-line mixer
o Verify integrity in tank mixer
RESTRICTED - 7
Basis for Design – Asset integrity Shellvis V-1901 project
Piping:
o Apply pipping modifications to replace flow meter and the in-line mixer.
o Replace steam and condensate lines and install new flow meter in steam line.
o Replace vent duct.
Civil works
o Adequation of foundation for new in-inline mixer.
o New grating floor in underground level.
o Replace grating floor in stairs to underground level and improve handrail.
Electrical:
o New wiring for existing and new elements.
o Installation of frequency converter.
1.7. Interfaces
1.7.1. Interfaces with Plant Electrical supply
To ensure safety during execution of electrical works the electrical supply of the Shellvis area must be
secure.
The Adasoft system must be stopped to integrate the new process system associated with the
modifications in the Shellvis area.
Other potential interfaces to be considered are the connection to general utilities system such as
steam and air, the Shellvis area can be isolated without causing interference with other plant process.
The interference to consider then is the installation of the proper shut-off valve in each system.
The connection of Shellvis system with the storage facilities must be mechanically and from operation
perspective isolated and planned.
All elements include in the load of raw material, additives and recipe must be disconnected.
All elements included in the transfer of finished production to storage facilities must be also isolated.
RESTRICTED - 8
Basis for Design – Asset integrity Shellvis V-1901 project
These operations will be planned accordingly with plant operation and productions.
As stated previously, all isolation t¡of the Shellvis equipment and auxiliars must be planned and
executed in accordance to plant’s production and operation management.
RESTRICTED - 9
Basis for Design – Asset integrity Shellvis V-1901 project
2. Nomenclature/Abbreviations
DN Diameter Nominal. The DN prefix indicates the nominal diameter of a piping system
component in millimetres
DP Design Pressure
DT Design Temperature
HAZOP Hazard and Operability Study
HEMP Hazards and Effects Management Process
HSSE Health, Safety, Security and Environment
PRS Portfolio Requirements Specification
RESTRICTED - 10
Basis for Design – Asset integrity Shellvis V-1901 project
RESTRICTED - 11
Basis for Design – Asset integrity Shellvis V-1901 project
1.1 Operability
The layout of the facility or equipment shall allow for efficient and safe access during the operation thereof
under all normal, upset/emergency, and weather conditions.
The placement and orientation of all valves, controls and displays/instruments, including local control
panels, shall be appropriate to ensure safe and effective viewing, reach, and operation by personnel.
1.2 Maintainability
Equipment requiring maintenance shall be able to be worked on efficiently and safely without removal of
many other items such as piping, motors, etc., by providing adequate space and lay down areas for all
anticipated activities.
Doors, gates and access hatches shall be provided and configured to facilitate ease of maintenance.
1.3 Emergency Egress
All areas of the facility and equipment requiring access shall be able to be evacuated from safely under
normal and emergency conditions.
1.3.1 Walkways on packaged units or on vessel access platforms (e.g., tanks and pressure vessels)
between the vessel piping or other obstruction and guardrail shall be 700 mm (28 in) minimum in width.
1.3.2 Walkways other than on packaged units or vessel access platforms shall be 900 mm (36 in)
minimum in width with additional width required for operating aisles or stretcher accessible routes from
any location in or on a structure or building.
1.4 Manual Materials Handling
RESTRICTED - 12
Basis for Design – Asset integrity Shellvis V-1901 project
Manual lifting, pulling, pushing, and carrying of equipment, with respect to the biomechanical and
physiological capabilities and limitations of the personnel shall be addressed during design.
Associated needs include the availability of mechanical lifting aids for assisted lifting and appropriate
storage or placement of lifting aids for safe reach and effective operation.
1.5 Communication/Labelling
There shall be clear communication of information and equipment identification, including effective
viewing, reading, and understanding of instructions, signs, labels, and operations and maintenance manuals.
1.6 Work Environment
Environmental factors under the control of the project regarding noise, lighting, vibration, and proximity to
hot, cold, hazardous, and contaminated equipment or areas shall be addressed.
2. Standards
Where there are no specific local regulations pertaining to walking and working surfaces or
means of access to machinery, the following ISO standards shall apply.
In order to avoid risks and damages in the process of executing the actions described, the HSSE Study
is developed. The HSSE study is a document that identifies the risks existing at the time of carrying
out the work, analyses them and proposes measures to avoid, mitigate and/or eliminate them.
Thos document also includes all internal safety rules and recommendations of the CPDL.
RESTRICTED - 13
Basis for Design – Asset integrity Shellvis V-1901 project
The set points must be established during BDEP development and taken in considerations in order to
design the new process control.
Carbon steel is the standard material for existing equipment and piping in Tarragona LOBP.
Currently the Shellvis is operated and controlled locally, from its own control system.
Through this project, it is planned to design and implement the necessary improvements to:
1- Maintain local control, thus allowing total control and operability in the local.
RESTRICTED - 14
Basis for Design – Asset integrity Shellvis V-1901 project
2- Integrate the Shellvis into the control system of the plant, thus allowing the control and operability
of the Shellvis from the main control system of the CPDL.
To achieve this objective, the following has been planned: replacement of instrumentation. laying of
new cabling and peripheral elements for communications. Expansion and integration into a
centralized control system.
3.5.2. Maintainability
The aim of the project is to improve the operability and functionality of the Shellvis, and to extend its
useful life.
To this end, provision has been made for the replacement of the weakest elements, the reinforcement
of existing elements and the repair and/or total replacement of elements with wear or damage.
All the elements will be easy to maintain and access, isolables if necessary with the appropriate
isolation and safety measures
RESTRICTED - 15
Basis for Design – Asset integrity Shellvis V-1901 project
CPDL Shell Tarragona is in moderate climatic and seismic data area. Especial attention to seismic
data for this project.
In order to perform design and calculations (thermal stress of pipes, mechanical design and
calculation of supports etc) some data must be considered:
The filtration skid and complete hardware scope will be located inside. (Ambient conditions).
Temperature
Very high temperature: > 35ºC
Sumer temperature > 30ºC
Winter temperature > 5ºC
Very cold temperature < 0ºC (MDMT* at -10 degC C conservative for outdoor
equipment and piping)
Rain
High rain 50-100 mm/day
Normal rain data 5-10 mm/day 10% of days.
RESTRICTED - 16
Basis for Design – Asset integrity Shellvis V-1901 project
Wind
Normal wind 12 km/h
High wind 60km/h
Maximum wind for calculations purposes is 120 km/h
Seismic
For civil works foundations, category V of seismic activity must be considered.
RESTRICTED - 17
Basis for Design – Asset integrity Shellvis V-1901 project
RESTRICTED - 18
Basis for Design – Asset integrity Shellvis V-1901 project
5. Process system
This section describes the existing utility services on-site and the changes required as part of this
project.
P&IDs
These can be found attached:
In the P&ID are represented the equipment, lines, and instrumentation to be replace, installed as new
and to kept.
For the V-1901, it is to be inspected to check its mechanical integrity. In addition, new nozzles to be
implemented to improve process control.
Rotating equipment:
RESTRICTED - 19
Basis for Design – Asset integrity Shellvis V-1901 project
Power Comments
Pump P-1901 11kW Existing, to add frequency
converter
In-line Mixer M-1902 15kW Replace, with frequency
converter
In-line Mixer M-1903 45kW Existing, with frequency
converter
For the rotating equipment, frequency converter needs to be installed to optimize the equipment
operation.
In addition, the in-line mixer must be replaced due to equipment performance reduction. The new
equipment is in the plant warehouse.
Currently the power comes form an existing cabinet that is part of the existing power distribution and
control network.
Main change is the installation of three new frequency converters in the MCC and from there new
electrical cable to feed the rotating equipment.
There is already instrument air in the area to give supply to new pneumatic valves.
RESTRICTED - 20
Basis for Design – Asset integrity Shellvis V-1901 project
RESTRICTED - 21
Basis for Design – Asset integrity Shellvis V-1901 project
6. Utility systems
RESTRICTED - 22
Basis for Design – Asset integrity Shellvis V-1901 project
7. Interfaces / Tie-ins
RESTRICTED - 23
Basis for Design – Asset integrity Shellvis V-1901 project
Lay-out basis and separation distances must follow the Human Factor Engineering requirements:
HFE Requirements for the PRS
3. The following HFE design principles shall be met.
3.1 Operability
The layout of the facility or equipment shall allow for efficient and safe access during the operation thereof
under all normal, upset/emergency, and weather conditions.
The placement and orientation of all valves, controls and displays/instruments, including local control
panels, shall be appropriate to ensure safe and effective viewing, reach, and operation by personnel.
3.2 Maintainability
Equipment requiring maintenance shall be able to be worked on efficiently and safely without removal of
many other items such as piping, motors, etc., by providing adequate space and lay down areas for all
anticipated activities.
Doors, gates and access hatches shall be provided and configured to facilitate ease of maintenance.
3.3 Emergency Egress
All areas of the facility and equipment requiring access shall be able to be evacuated from safely under
normal and emergency conditions.
1.3.1 Walkways on packaged units or on vessel access platforms (e.g., tanks and pressure vessels)
between the vessel piping or other obstruction and guardrail shall be 700 mm (28 in) minimum in width.
1.3.2 Walkways other than on packaged units or vessel access platforms shall be 900 mm (36 in)
minimum in width with additional width required for operating aisles or stretcher accessible routes from
any location in or on a structure or building.
3.4 Manual Materials Handling
Manual lifting, pulling, pushing, and carrying of equipment, with respect to the biomechanical and
physiological capabilities and limitations of the personnel shall be addressed during design.
Associated needs include the availability of mechanical lifting aids for assisted lifting and appropriate
storage or placement of lifting aids for safe reach and effective operation.
3.5 Communication/Labelling
There shall be clear communication of information and equipment identification, including effective
viewing, reading, and understanding of instructions, signs, labels, and operations and maintenance manuals.
3.6 Work Environment
Environmental factors under the control of the project regarding noise, lighting, vibration, and proximity to
hot, cold, hazardous, and contaminated equipment or areas shall be addressed.
4. Standards
Where there is no specific local regulations pertaining to walking and working surfaces or
means of access to machinery, the following ISO standards shall apply.
RESTRICTED - 24
Basis for Design – Asset integrity Shellvis V-1901 project
8.2. Civil/Structural/Architectural
8.2.1. Structural Improvement
A grating floor must be built to improve safety in the underground level, and the stair steps are to be
replaced as well as the handrail update. All these changes are proposed for safety of the operators
working in the area.
Local control for the new elements will be installed during this project. FEED contractor will develop
the Automation and control architecture. Basis will be semi-automated line up of the Shellvis process
(no manual valves, except for maintenance and isolation). This philosophy is selected, that increased
automation and integrate with a more central plant control system.
8.3.2. Instruments
A draft list of elements has been development with elements to be replace and new ones to be added,
to improve process control.
The Shellvis V-1901 shall be inspected by NDT test. According to the report result the vessel shall be
repair or could continue operations.
For this work the thermal insulation must be removed and replaced for new one.
RESTRICTED - 25
Basis for Design – Asset integrity Shellvis V-1901 project
To improve process control new nozzles temperature and radar level are to be built to the equipment.
A new in line mixer is already in the plant warehouse, the scope includes the installation of the new
equipment, including piping modifications and civil works.
8.4.4. Piping
All valves (manual and automatic) are to be replaced for new ones. For lines to be modified heat
insulation to be replaced.
Recirculation line
To replace the existing in line mixer the recirculation must be modify.
Storage lines
Manual valves to be replaced for automatic.
RESTRICTED - 26
Basis for Design – Asset integrity Shellvis V-1901 project
8.4.5. Venting
The venting duct, connected to the air extraction motor of the V-1901, it is to be replaced due to bad
condition.
8.5. Electrical
RESTRICTED - 27
Basis for Design – Asset integrity Shellvis V-1901 project
RESTRICTED - 28
Basis for Design – Asset integrity Shellvis V-1901 project
Local and national legislation will prevail, then the PRS. International standards and best practices
will prevail above other Shell standards (DEPs).
PRS 30.09.00.01, February 2018, requirement will be followed as engineering standards. FEED
Contractor must validate and indicate if other Engineering standards are applicable to this project.
RESTRICTED - 29
Basis for Design – Asset integrity Shellvis V-1901 project
None.
RESTRICTED - 30
Basis for Design – Asset integrity Shellvis V-1901 project
Appendix A. P&ID
RESTRICTED - 31
Basis for Design – Asset integrity Shellvis V-1901 project
Appendix B. DRAWINGS
Plant Lay outs
Mechanical drawing
RESTRICTED - 32
Basis for Design – Asset integrity Shellvis V-1901 project
Appendix C. List
Instrumentation List
Signal List
Other
RESTRICTED - 33
Basis for Design – Asset integrity Shellvis V-1901 project
RESTRICTED - 34