Professional Documents
Culture Documents
Earthmoving Plant
Earthmoving Plant
V, V. Tucker
C.Eng.,M.I.Mech.E., F.I. Plant E., A.M.B.I.M.
WOODHEAD-FAULKNER CAMBRIDGE
Published by W-oodhead-Faulkner Limited
8 Market Passage, Cambridge CB2 3PF
Conditions of sale
All rights reserved. No part of this publication may be reproduced,
stored in a retrieval system or transmitted, in any form or by any
means, electronic, mechanical, photocopying, recording or
otherwise, without the prior permission of the copyright owner.
V.V.T.
NOTES OM UNITS OF MEASUREME
Both Imperial and metric speeds and capacities are used in this book,
the reason being that much British equipment still has instruments
graduated in miles per hour and capacities specified in cubic yards.
Conversion tables for Imperial, metric and US units are provided on
pages 91-92.
Page
Preface iii
Introduction l
Plant selection 72
Task indentification. Preliminary selection. Machine output
estimation. Machine matching. Output costing. Selection in practice.
v
7 Construction plant maintenance
The technical reasons for maintenance. Forms of maintenance.
Inspection. Routine lubrication servicing. Integrated system of
servicing and preventative maintenance.
8 General considerations
Manufacturers' data. Computer facilities. Plant training.
Conclusion.
Index 97
Hundreds of millions of pounds are spent annually by the construction
industry on earthmoving and other forms of construction plant. In
any large civil engineering project up to 25% of the cost of that project
may be associated with the provision of the construction piant, yet the
selection and management of such plant is still given a relatively minor
place in the training curriculum of the average civil engineer.
Even the industry itself has been slow to recognise that the proper
employment of such a large capital asset is as important to the survival
of a company as the efficient management of the construction activity.
The past twenty years have seen a gradual change in the organisation
of construction companies, aimed at focusing management expertise
on plant operation. Contractors with large holdings have formed plant
companies which offer a plant hiring service to all comers and a
priority plant provision service to the parent company, whilst
independent plant hire companies have proliferated, to the extent that
they now form the major portion of the market for new plant in the
United Kingdom. These plant companies have professional tnanagers
who are there to offer advice on plant selection, but for the civil
engineer dependent on these experts for information there is always
the possibility that the advice may be coloured by the fact that certain
plant is available within the plant company rather than by consider-
ations as to the most efficient and economical way of carrying out the
task. In addition, it is possible that the plant manager approached is an
expert in a very limited range of types of plant. Companies tend to
specialise in a certain field, e.g. compaction equipment, or loaders,
and he may therefore not be able to advise authoritatively on other
types of plant.
The proper selection of plant is important for several reasons. The
first and most obvious is that of achieving the lowest cost of carrying
out the construction task. Using a machine not really designed for the
task or of unsuitable capacity can result in a high cost operation. The
safety of men on site and of the machine operator may be put at risk
and a slow operation can keep other staff on site longer than planned,
holding up succeeding operations and delaying the completion of the
whole contract. Too small a machine may suffer frequent breakdowns
from overloading or abuse as the operator tries to obtain high
production. Most construction operations today are built around items
of plant and if the plant stops the job stops. The consequential loss to a
contract due to plant breakdown is always high compared with the
additional cost incurred by use of the correct plant in the beginning
or by carrying out good effective maintenance. Even when an efficient
system of machine replacement is available, production time is lost
and the cost of bringing the machine to site may be appreciable.
The aim of this book is to introduce the subject of earthmoving plant
selection, operation, output estimation, costing and maintenance to
the young civil engineer. It keeps the subject simple and provides
basic instruction which can readily be added to by reference to the
sources of further information mentioned. The book also contains
useful output data and tables.
The earlier chapters cover the basic operational roles of the more
common items of earthmoving plant, namely the loader backacter, the
wheeled and tracked loaders, the bulldozer, the rope and hydraulic
excavators, the scraper and the grader. Subsequent chapters define
the factors that affect the output and give examples of corrections to
the theoretical output which must be made to determine probable out-
put on site. The use of output graphs and additional sources of output
information are mentioned. The simple theory relating to the limit-
ations and advantages of wheels and tracks is then dealt with in some
detail because of its importance in the selection process.
Calculating the cost of owning and operating plant has always
proved difficult because of the several variables involved. All the
elements that combine to form the hourly cost of plant are considered
and methods of their calculation suggested. Examples of the costs
relating to differing periods of ownership are shown and the consider-
ations which affect the decision to hire or buy are mentioned. Any
relation of the cost figures with the actual cost of plant was probably
destroyed by inflation before the printer's ink was dry but the prin-
ciples may be followed safely. The approach to plant selection is dealt
with by considering the basic earthmoving tasks and the advantages
and limitations of conventional machines to carry out these tasks. This
is the preliminary or first stage of the selection process. Having
determined the machines which could carry out the task the second
stage is the estimation of probable outputs. These must be related to
the time available for the task and the cost of completing the task,
thus permitting the selection of the most efficient machine. A chapter
on the importance and method of maintaining plant, followed by an
Appendix of useful tables, completes the book.
It is hoped that the logical progression of the material from the plant
capability to output estimation and selection will make the subject
easy to follow. This book should, as its title suggests, serve as an
introduction to this fairly complex subject and to those keen to extend
their knowledge are recommended the publications of leading plant
manufacturers. In the opinion of the author the books of Caterpillar
Tractor Co. are the best and should be studied first. Other manufactur-
ers are following the lead of this enlightened company and orgaxfisa-
tions such as Massey-Ferguson, John Deere International and, at
home. J. C. Bamford also have information available.
THE BULLDOZER
The bulldozer is a crawler tractor with some form of blade mounted
transversely across the front end. As will be seen in a subsequent
section, the crawler loader can be converted for the bulldozing (or, as
more commonly expressed, dozing) role, but the bulldozer proper is a
machine designed and purpose-built for its role. The blade is usually
raised, lowered and tilted by means of hydraulic rams although
machines with cable-raked and -lowered blades may still be found.
Fig. l. Bulldozer
Over short distances (up to about 100 metres) bulldozing is the cheap-
est way of moving spoil from one place to another on site. The earth is
pushed in front of the blade, and it is rather surprising to find that the
greatest resistance comes not from the weight or mass of earth moved,
but from the high frictional resistance of moving the spoil across the
grouiia.Hence thmkElity of special "U" or bowl blades (Fig. 2).
which keep the material rolling in front of the blade, reducing the
frictional drag and permitting the movement of a greater mass than the
standard straight blade; such blades find application in the movement
of large volumes of light, essentially frictional, materials.
The dozer is also used to speed up scraper bowl loading by pushing
from the rear during the loading operation; push loading is frequently
used for wheeled scrapers but much less frequently for crawler-towed
scrapers.
Stability and safety
The person at greatest risk is the dozer operator: operating too near
the edge of an excavation or downhill dozing over the edge of a bank
may result in the edge crumbling and the machine toppling into the
hole. Operator training is in the main the only real safeguard.
Capacity and outputs
The theoretical output of a bulldozer will depend on the size and type
of blade, on the power of the tractor driving it, and even more on the
dozing technique used. For instance, slot dozing, a technique whereby
many passes are made over the same piece of ground, forming a trench
or slot. improves output by reducing material spillage around the sides
of the blade. Downhill dozing will improve output by using gravitation-
al forces to assist the tractor's own engine power. Where two or three
dozers are to be used, if they operate side-by-side again spillage
around the blades will be reduced, increasing output. A rough
approximation of a dozer blade load under good conditions is the
volume encompassed by the blade at a 1-in-l slope to the ground
from the top edge of the blade, plus 20%.
Manufacturers measure the soil heaped in front of the blades under
various conditions and pr3duce output tables or graphs for specific
machines and specified conditions. These may be regarded as the
optimum or theoretical, to be modified by all the practical factors
which will be enumerated in subsequent chapters. Examples of graphs
and their use are given in Chapter 3.
Dozer blade types and uses
The Straight (S) blade is the most commonly found pattern of blade on
site. It has a high horse power per foot of cutting edge ratio, which
makes it a good general purpose dozing blade with good ground
penetration and load characteristics. If the dozer is fitted with a blade
tilt cylinder, versatility and productivity of the blade may be increased.
Fig 2. Dozer "S" blade Fig. 3. Dozer "U" blade
h
Fig. 7. 4-in-lor melti-purpose bucket
Teeth Cutt~ngEdge
S d e Bit
C ldm
Se~t~on
:,"cf\lde)
Grab
Teeth
Mouidbodrd
Cutting t d g e
Standard bucket - used for loading. Bulk handling bucket -for handling
bnckfilling, site stripping and levelling. lightmaterials such ascoke and coal but
not suitable for digging.
D
, ump sheave (Tipping sheave)
types are perforated to allow water to drain off. The teeth on the bucket
are designed for easy replacement: sharp teeth are essential for high
outputs in relatively hard conditions.
Additional roles
The dragline is one of a small family of plant items with a crawler-
tracked crane base. It is probably the most important and the common
version, but two others have extensive use for earthmoving operations
in the construction industry; these are the face shovel and the clam-
shell or grab.
The face shovel (Fig. 13) is primarily used for the excavation of
high banks, such as are found in quarries. In operation the jib is fixed
and the "dipper arm" carrying the face cutting bucket is racked in or
out to or from the excavation face. Racking towards the face "crowds"
the bucket causing it to bite into the bank, raising the bucket rotates
the "dipper arm" about a point on the jib, forcing the bucket through
the banked material and filling it.
On some shovels the "dipper arm" cannot be racked i n and out,
but rotates about a fixed pivot point on the jib, and because no crowd
E%. 14. Priestman rope-operated
digging grab
action is possible this type cannot dig such hard material. It is,
however, a simpler machine to operate, although its output is less
than the "crowd" version.
The spoil dug must be loaded into haul units because the dumping
radius in this configuration is small. In quarries, shale and blasted
rock may be handled, its cycle time is low, the bucket moving upwards
through the banked material is quickly filled and its output is much
higher than a dragline with equal capacity bucket. Note, however, that
a haul unit must be used (except where a hopper or conveyor is
loaded), whereas the dragline mostly operates without. Large hydrau-
lic face shovels are now in common use, tending to replace the older
rope machine.
The clamshell or grab (Fig. 14) may be fitted to the dragline in place
of the "dipper arm" and bucket. The grab has teeth and is used for
hard materials, the clamshell has no teeth and is used to handle softer
materials, e.g. sand. Both attachments are operated by two ropes from
the dragline boom or jib, a hoist rope for raising or lowering and a
holding rope to hold the grab whilst the hoist rope is lowered off to
open it. A rope from a tagline drum prevents the grab from rotating
during the hoist and lower operations.
Stability and safety
The problem of stability of this equipment in use approximates to that
for the crane role, except that it is derated in the dragline mode to
about 80% of the crane capacity. The essential requirement for
maximum stability is a firm level base; if the ground is soft, the
equipment should stand on timber sleepers or steel mats, not too near
the edge of the excavation. The second requirement is that safe
working loads at the varying radii are not exceeded (the maximum
bucket load for the material dug must be calculated and heeded).
Sudden jerks or stops must be avoided lest the load swings beyond the
radius for stable operation, and finally, ropes must be regularly
inspected for crushing and broken strands, etc. In fact, the require-
ments for the regular inspection of all lifting equipment are clearly
laid down in various regulations and must be strictly complied with.
Capacity and outputs
DRAGLINE
The equipment bucket sizes range from % to 2% cubic yards for tht
smaller commercial machine frequently found on site or in smaller
quarries, up to more than 100 cubic yards for the very large open
mining type of operation.
The length of time needed to fill the bucket depends on the angle
and depth of the dig, on the hardness of the material and, especially,
on the skill of the operator. Tables of outputs for draglines are avail-
able which specify the conditions, usually optimum, under which they
were or could be achieved; the figures in these tables may be used for
the preliminary selection of the machine size for a particular operation,
but they will need to be modified to more realistic levels in accordance
with the factors detailed in Chapter 3. As an example of an output, a
dragline with a 2 cubic yard bucket, digging gravel under optimum dig
conditions, i.e. bucket quickly and easily filled, assuming no delays,
a 90" boom swing angle from dig to dump and all material loaded into
haul units, may achieve an actual hourly output of 280 cubic yards;
- under adverse conditions this figure could be halved.
FACE SHOVEL
Working into a bank the shovel is quickly filled and the time required
is low, hence the theoretical output may be taken as the product of the
bucket size and the number of cycles. As will be seen in Chapter 2,
included in the factors which modify the theoretical outputs is the type
of material dug: the output when digging light sandy soil will be nearly
three times that achievable when digging poorly blasted rock. The
need to move the machine as the face advances, plus the need to
clean up the floor of the excavated area to reduce risk of haul unit
damage, also reduces output.
GRAB/CLAMSHELL
Both of these attachments (rope operated patterns only) rely on their
own weight to provide digging power. The grab interlocking teeth
provide the additional penetrating facility which permits moderately
hard materials to be dug. When handling soft materials in, for
example, an industrial application from barge to hopper, the theoret-
ical output is again the simple product of clamshell capacity and the
number of cycles. On site, however, the operation is likely to be
intermittent, with the grab/clamshell only partially filled and the
depth of dig increasing every few cycles. For these reasons figures for
the output of grab/clamshell are seldom computed or published.
On site grabs/clamshells are normally used for specialist operations
such as deep, small hole excavation or removing spoil from timbered
trenchworks. They are not normally regarded as production tools,
as are the other excavation attachments referred to in this chapter.
THE HYDRAULIC EXCAVATOR
The hydraulic excavator represents the classic application of hydraulic
power to construction tasks. By means of an engine-driven hydraulic
pump, control valve system and double acting rams, the bucket may be
accurately and forcefully positioned to dig and load hard materials.
Special purpose-designed buckets are available for specific tasks
(see Fig. 16) and other attachments such as rock breakers, face
shovels, crane hooks and hydraulic grabs are commonly used.
The hydraulic excavator differs from the wheeled tractor mounted
backhoe previously described in that it is capable of 360" rotation and
is equipped with much larger buckets. In the principle of operation,
however, they are the same.
The basic tasks that may be carried out by the excavator are base-
ment dig, leaving clean interior faces, trench digging, small square-
hole digging for columns and backfilling. Fitted with a grab attach-
ment it has the ability to apply downward pressure to the grab cutting
edges.
From the foregoing it can be seen that the hydraulic excavator is a
very versatile machine which may be used for a wide range of con-
struction activities. As an example, in its normal excavation role it can
Fig. 15. Hydraulic excavator -
Fig. 16. Types of bucket
Ejector Bucket
Parallel or tapered sides ejects sricky soil
by means of an inner blade.
3-in-1 Bucket
For normal trenching, square hole
digging and a face shovel.
tances exceeded 300 metres (one way); then the slow hauling speeds
(approx 10-12 kph) made cycle times excessively long and the
crawler-drawn scrapers began to be superseded by the rubber-tyred
motorised scraper. Haul speeds of 60 kph are possible on good haul
routes for these self propelled rubber-tyred machines. However,
because traction over ground is inferior to the crawler tractor-towed
machine it is usually necessary to provide assistance during the load-
ing operation by pushing with a crawler tractor.
A compromise machine, i.e., one which has high overground speeds
yet possesses an ability to load light soils unaided is the elevating
scraper. This form (Fig. 19) is a self-propelled, rubber-tyred unit with
a motor-driven multi-bladed elevator passing over the cutting edge;
when the scraper is loading the elevator by working towards the rear
of the bow it continuously removes the cut spoil from the cutting edge,
reducing the loading effort required. Hence easy and moderate dig
materials may be loaded in reasonably economic times without
recourse to a crawler pusher. With more difficult-to-dig materials the
3
E
-
E
X 1 1 l4 --L
;
-2E
6 -
E l / . / 1 I
I j l ,
! l
+E 4
I ( ' 1
1 V
/
JlP++
0 I0 20 30 40 50 60 70 80 V0 100 110
l
170
'4 of tot41 CrlP.7CltV
It may be seen from the graph in Fig. 20 that about 0.6 minutes is
needed to 86% fill the bowl, approximately a further 0.2 minutes is
required to fill it to 99% capacity; i.e. the last 13% of bowl space to
be filled takes more than twice as long to fill as 13% of bowl space
during the earlier part of the load cycle. On a short excavate, haul and
dump cycle it could prove more productive to load the bowl to only
85% of its capacity, the shorter loading time permitting more cycle:
in a given time offsetting the lost production per load. Additionally, the
excessive tractive effort required to fill the last 10-15% of bow!
capacity strains scraper motive unit and pusher tractor. This mal
damage transmission, tyres, etc. and will certainly precipitate
breakdowns.
The total cycle time may for all practical purposes be considesec
to be composed of a "fixed" and a "variable" part. The "fixed'
cycle time consisting of the load, manoeuvre and dump/spread time
the "variable" cycle time consisting of the haul to dump and thc
return to load times. Typical load and dump times for wheeled scraper:
are
Load Manoeuvre anc
Spread/Dump
Wheeled self loading 0.9 minutes 0.7 minutes
Wheeled push loaded 0.6 minutes 0.7 minutes
The variable cycle time will depend on haul distance, haul roac
gradients, haul road condition, type and size of scraper, load, operatol
ability and machine condition. Two principal methods of determining
the haul time will be detailed in subsequent sections. The sum of thc
fixed and variable cycle times gives the total cycle time.
Theoretical output = Bowl capacity X Time allowed for the ooeratior
Cycle time
Example A tandem-powered scraper of 450 h.p., with a 15 cubi
metres heaped bowl capacity, excavates for l minute then travel
1000 metres over a good level haul route to spread-dump the load
Manoeuvre and spread time averages 0.7 minutes. Given that th
average haul speed is 40 kilometres per hour, what is the output ii
loose cubic metres (LCM) per 60-minute working hour?
Fixed cycle time = 1-4-0.7 =1.7minutes
2
= -hours
40
= 3 minutes
Total cycle time = 1.7+3
= 4.7 minutes
Number of cycles per hour = 60
4.7
= 12.8
Theoretical output per hour = 15 X 12.$
= 192 LCM
Fig. 21. Time/distance graph [scraper]
The pusher cycle covers the load assist time, the return to the begin-
ning of the cut for the next assist and the manoeuvring time at each
end of its travel. An average time for this cycle is l .S minutes: hence,
if the sctaper cycle time is 9 minutes, the number of scrapers one
pusher can serve is 9 = 6
l .S
THE GRADER
The grader is an item of earthmoving plant designed specificall
for a particular task. That task is the blade dressing of ground to fin1
limits. The blade which displaces or dozes the soil is wider but not a
deep as the conventional dozer blade: it may be adjusted througl
an angle of about 300' in the horizontal plane and it may be angled tl
the horizontal for bank finishing to 90' or more. The blade may bl
offset from the centre line of the machine and it may be reversed tl
work when the machine is reversed. This latter feature is useful whe~
working close to banks or buildings.
Machines are commonly six-wheeled: the four wheels under thc
engine unit are driven while the two front wheels steer and may bl
tilted from the vertical to counter the side thrust when the grader i
working around bends or corners. Four-wheel steering versions arc
available, facilitating operation in confined or small sites.
The method of operation differs from that of the straight-bladec
dozer in that the grader blade is set at an angle to the direction o
travel and the displaced spoil rolls along the blade forming a windrov
at the end; subsequent passes can displace the windrow laterall:
sideways or spread and wheel-compact it. When spreading, the bladc
is set at right angles to the centre line of the machine, the bladc
height being controlled by the operator.
The importance of haul road maintenance, particularly with scrape
fleets, has been mentioned and, as an indication of the economic
advantage of using graders, a 10% increase in speed of rubber tyre(
scrapers in a l000 metre haul will cover the cost of the use of a grader
any further increase is a bonus.
Activities carried out in addition to the above include:
(a) Ditching: the first cut is made by the toe of the blade which i!
set deeper as the work progresses, the spoil leaving the heel of tht
blade set to spill off inside the track of the rear wheels.
(b) Bank cutting: blade offset and angled to the horizontal, tht
wheels nearest the bank in a ditch at the foot. The windrov
formed at the foot of the bank must be cleared frequently, e.g
on alternative passes.
(C) Scarifying: scarifying rakes may be fitted in front of the blade:
facilitating the break-up of hard ground.
Blacktop mixing and snow-ploughing may also be carried out. Bucket
and dozer blades may be fitted to the front of some models but suc
attachments have very limited outputs.
Stability and safety
The grader as a finishing "light work" tool is an inherently safe an1
stable machine; the greatest risk to site staff is its high ground speed
which may reach 50 kph.
Capacity and output
Grader output is a direct function of its overground speed in general.
First gear or low range is used in heavy going conditions, working on
inclines and for fine grading.
Second gear or medium range is used for heavy grading, ditching,
bank work and scarifying.
Third gear or high range is used for maintenance grading, windrow
spreading and blacktop mixing.
Speeds in gears or different ranges depend on the model but average
figures would be 6 kph in first gear, l 5 kph in second and 40 kph in
third.
To calculate the time required for a grading operation the number of
passes required must be known or estimated and the speed of the first
and subsequent passes known.
2 FACTORS AFFECTING THE
OUTPUT F EARTHM G PLANT
The factors that affect the performance of earthmoving plant are easy
to identify but difficult to quantify. In Chapter 1 the calculation of the
theoretical output was described and the statement made that the
actual output on site may be 50% or less of the theoretical. In this
section it is proposed to describe the reasons for the lost production
and to attempt to put a value on the production loss. It will b e apprec-
iated that the figures given are approximate and provide a guide only
to the probable output. There are many occasions, however, when such
calculations are necessary to enable an estimate of the cost of the
earthmoving aspects of a project to be made.
For ease of reading, the output modifying factors will be considered
under the following headings: soil swell; operating conditions; terrain
formation; machine condition; operator efficiency and job efficiency.
SOIL SWELL
Soil dug from a bank breaks up as the bucket disturbs it and in the
bucket it consists of irregular clods, stones, etc., and voids. The
volume it occupies in the bucket or in front of a dozer blade is greater
than its original bank volume. The increase in volume is greater for
some materials than for others. It will be obvious that sands and small
aggregates will swell little because of their resistance, by virtue of
small size, to the formation of voids. Clays on the other hand break up
into large clods and in consequence have a higher swell factor. Dry
clay swells approximately 40%, i.e. 1 cubic metre of dry clay before
digging becomes 1.4 cubic metres after. Earthmoving operations are
usually priced on bank metredyards, hence the need to take account of
the swell factor when estimating the capacity and number of haul
units required and the time the operation will take. Conversely, it
is sometimes required to convert from loose or dug cubic metres to
bank cubic metres, which is effected by dividing the loose cubic metres
(LCM) by 1 + Swell factor. For example, 150 LCM dry clay would
become 150 + (1 4- 0.4) = 107 bank cubic metres (BCM).
Swell factors vary with moisture, the degree of compaction, in-
clusions such as rocks or roots and material particle size. The only
truly accurate method of determining the swell factor is by testing the
material to be dug. One London contractor lost a considerable sum of
money through underestimating the swell of "blue" clay: the contract-
or was in error in failing to consider the possibility that the swell
factor could be different for different classifications of clays.
A table of approximate swell factors and weights of common
materials may be found in the data section at the end of this book.
OPERATING CONDITIONS
In the construction world the weather is more than just a topic of
conversation. Prolonged rain can speedily convert a profitable job into
a loss-making operation. The possibility of this happening may be
reduced by getting a detailed report from the meteorological office
of conditions that have obtained in that locale, for the proposed period
of operation, in previous years. They will also produce for a modest
charge a forecast of conditions likely to occur and armed with this
information the estimation of the earthmoving task has at least a
chance of being a little more accurate.
On well drained sites, moderate rainfall poses little problem to the
work task, but on badly drained sites and on cohesive soils, e.g. clays,
output will be reduced and work may eventually cease. Under such
conditions only tracked machines can operate; wheeled machines
simply do not have the traction in wet conditions. Even crawler tractor
performance is materially reduced, speed over ground is slower,
buckets pick up water as well as the material under excavation,
visibility is reduced and accurate placing of bucket or blade more
difficult, and, last but not least, operator morale may be badly
affected.
In the absence of rain, weather can still affect the operation adverse-
ly; cold frosty weather makes the ground hard and difficult to dig.
Quantitively, the difference between an easy dig in good conditions
and a reduced output dig because of bad operational conditions can
amount to a loss in output (theoretical or optimum) of at least 15%.
It must be a matter for subjective judgement as to the loss estimate
for particular conditions, rating severe as a 15% loss and moderately
severe perhaps as 10% loss, difficult, e.g. moderate frost or heavy
intermittent rain, at 7%-8%, and good, at zero lost output.
TERRAIN FORMATION
The terrain of the site area should be considered as early as possible to
determine the most effective way of using ground slopes and features
to assist the plant operation. Dozing should always be carried out
downhill: the gravitational force available assists the engine to produce
a greater dozing effort and it helps also to keep the load rolling once
started, reducing the dozing effort required.
Haul road routes should be selected so that slopes are ascended by
empty trucks, scrapers, etc. and descended laden. Haul routes should
be kept in good condition to enable maximum haul speeds to be
maintained. A high average haul speed keeps cycle times down,
maximising output.
It is possible to quantify the additional output from downhill working
by use of output graphs or, less commonly, by calculating the increase
in ground speed due to the force acting down the slope and relating
this to the shorter cycle time.
OPERATOR EFFICIENCY
An operator who persistently fails to fill his bucket, who moves thc
boom or bucket further than the job demands, who wastefully cut:
with his dozer blade longer than is productive, whose co-ordination o-
controls is poor, who travels in a lower gear than conditions demanc
or who badly positions his machine in relation to the haul unit will no1
produce maximum output. It is possible to measure the loss in outpul
attributable to bad operating by using different operators on the same
machine and same task in succession. The output difference will be
measurable in terms of haul unit loads counted. If the bad operators
are employed by the contracting company, replacing them may be the
simplest way to improve production; unfortunately with the currenl
practice of hiring machine and operators, control over quality is
difficult to exercise. Hence it may be necessary to include in the
estimation of output a factor for probable operator efficiency (perhaps
better expressed as inefficiency).
The loss of output for a bad operator could easily reach, and may
even exceed, 20% of the theoretical output. Taking 20% as a sensible
maximum loss for a bad operator, then an average operator may be
reckoned to produce 10% below the best possible achievement figure.
No modifying factor is used for a highly competent and efficient
operator.
MACHINE CONDITION
Low engine output, worn or blunt teeth or tool points, inadequate
lubrication and maintenance (including maladjusted clutches, etc.)
will reduce output. The increase in internal friction due to dry bearings
or mating surfaces can increase the machine operating cycle by
many seconds, producing a corresponding reduction in output. No
output modifying factor is included in the output estimation for
machine condition because losses from this cause are unacceptable;
it is referred to here because a basic requirement of any earthmoving
operation is sound eqliipment in a good state of maintenance. Machine
breakdown, of course, results in periods of zero output. The possibility
of breakdown can be reduced by planned/preventative maintenance.
JOB EFFICIENCY
A further factor compounded of many smaller constraints is the job
efficiency factor. No machine on site works continuously 60 minutes
every hour, hour after hour. Stops will be required for job discussion,
marking out, work checking, operator needs, machine adjustments
or minor repair, attachment changes, repositioning, waits for haul
units, etc. For this reason a so-called "job efficiency factor" is intro-
duced into output considerations and it simply assumes that for every
elapsed hour on site the machine works for 50 minutes. When delays
are likely to be frequent then a 40 minute work hour should be used.
When delays are very frequent then a 30 minute work hour may be
all that can be achieved.
For example, if the output of a machine is calculated at 120 cubic
metres per hour for 60 minute working, the estimated output on site
allowing for the job efficiency factor is only
50
120 X - minutes
60
= 100 cubic metres per hour.
MACHINE MATCHING
As a matter of theoretical reasoning the maximum output from a
machine/haul unit combination ought to be when machine and haul
unit capacity ratio is 1 to 2, for example, a crawler loader with a
2 cubic yard bucket filling a 4 cubic yard haul unit. In practice such a
combination is unworkable. Dumping 2 cubic yards as one load into
a relatively small (4 cubic yards) haul unit is likely to damage the
suspension or bodywork of the unit and accurate placement of the load
without excessive spillage is difficult. The optimum ratio proved in
practice is l to 4 or l to 3. A greater ratio than this requires too many
machine cycles to fill the haul unit resulting in a high loading time and
a poor production rate.
On this same theme, machine matching means that the loader
should easily be able to fill the tipper or truck, e.g. the truck should not
be so high-sided that filling is difficult. It also assumes that the
excavating plant never waits for a truck, dumper or tipper.
SUMMARY OF FACTORS
As has been shown, the theoretical output of an item of earthmoving
plant, which at its simplest is the product of the maximum possible
output per cycle and the number of cycles, must be modified by:
soil swell, which reduces the bank cubic yarddcubic metres dug
or dozed;
operating conditions, which at worst stop production but more
normally may reduce it by up to 15%;
terrain formation, which may, thanks to gravity, better the
theoretical output;
(d) operator efficiency, when the modifying factor for an excellet
operator is 0%, but for a poor performer may reach 20% or eve
higher;
(e) machine condition, which could further reduce output, but shoul
not, because it is to a large measure controllable;
(f) job efficiency, which reduces t h e theoretical timing of one hot
to an actual period of 30 to 50 minutes according to the variablc
involved;
( g ) machine matching, which gives the ratio of loader to haul un
capacities as 1 to 4 or 1 to 3 ?or optimum efficiency.
In the next chapter probable outputs will be calculated for variol
machines and the use of time/distance and output graphs demo.
strated.
The best source of information for estimating machine outputs for any
g i ~ - l ntask and conditions are records of previous tasks or studies.
In the absence of these the second best source is the data published
by the machine manufacturers. Caterpillar, through their UK dealers,
provide tables and graphs for their extensive range of machines.
Some of the material which follows was taken from Caterpillar
publications.
ULLDBZEW OUTPUT
Use should be made of the output graphs, an example of which is
shown in Fig. 23.
Fig. 23. Bulldozer output graph
l5 3(1 -15 60 75 90 105 I20 135 150 165 180 195 Metres
1000
1200 900
800
1000
700
g 800 603 ;
.
>. 1
500
h(l(l 5
400
400 300
200
7011
100
0
100 2W 300 400 500
Average Dozmg Dlstdnce
If in the above example the operation had been carried out down a
15% grade the output would have been greater because of the
assistance afforded by the gravitational force acting down the slope.
From the gradient fador graph (Fig. 24), the multiplying factor is
1.19, the probable output would then become 131 X 1.19 = 156
approx. BCM per hour.
Fig. 24. Gradient
factor graph
' i Grade
Note In the event that dozing has to be carried out uphill then the
unfavourable section of the graph has to be used and the effect of
the adverse gradient would be to reduce the output.
CRAWLER LOADER OUTPUT
The theoretical output of the crawler loader is the material loaded per
cycle multiplied by the number of cycles in a specified time, e.g. 60
minutes.
(a) the fixed cycle time, consisting of the time for the loader to move
forward into the bank or stockpile, to fill the loading shovel, to
reverse turning to face the haul unit or dump location; to dump
and to return to the start position for the cycle, and
(b) the travel cycle time, when the dump site or haul vehicle is at a
distance from the digging location.
Note The term "fixed" is a convenience term and must not be taken
literally; for all practical purposes the variations in the time taken by
any particular machine for the activities specified under this heading
may be ignored and the average time regarded as a "fixed" time.
Fixed cycle time
Digging from a bank or stockpile there is a positional relationship of
digging location, loader and haul unit (as shown in Fig. 25) for
optimum efficiency.
For the set-up shown, the times for a complete dig and loading cycle
for the loaders commonly found on UK sites are fairly uniform and
consistent. Typical figures are:
If, as is more usually the case, the haul unit has to be located at a
distance from the digging area, then in addition to the manoeuvring
time of the fixed cycle the time to travel from the site to the truck or
tipper must be calculated. The fixed cycle and travel times (both ways)
must be added together to yield the complete cycle time for the
operation. Two methods of determining this time are commonly used:
CHART METHOD
The simplest method of obtaining this figure is to use the time/
distance travel charts supplied by machine manufacturers. An
example of such a chart is shown in Fig. 26.
Note the difference in speeds when travelling forward or in reverse.
Fig. 26. Travel time estimating chart [crawler loader]
8 15 23 30 38 46 53 60 Metres
(Min) 1.0
0.8
0.6
0.4
0.2
Speed in reverse gear is invariably faster over short distances from dig
to dump. It may therefore be quicker to reverse laden for half the travel
distance, turning and driving forward to dump, in which case forward
and reverse graphs must be used to find the total time.
Gear selection
The reader with an enquiring mind might now be tempted to ask how
is it possible to assess whether the track loader can be driven in third
or second gear. From Fig. 26 it can be seen that over a distance of,
say, 50 metres the travel time in second gear is 12 seconds longer than
in third gear, making a difference of 24 seconds on the whole cycle
time, an appreciable loss of output over a day's operation. This
question of gear selection, fundamental to output estimation, is
governed by engine output and frictional/rolling resistances , etc.,
which are covered in Chapter 4.
Output calculation
The above data has covered the estimation of cycle time and now
the probable amount which will be in the bucket for each of these
cycles must be estimated.
The relevant output modifying factors are:
(a) The fixed cycle time covers the time for the loader to move for-
ward into the bank or stockpile, to fill the loading shovel, to
reverse turning to face the haul unit or dump location, to dump
and to return to the start position for another cycle.
(b) The travel cycle time applies when the dump site or haul vehicle
is more than, say, l 5 metres from the digging/stockpile area.
Consider first the fixed cycle time, usually given as 0.4 minutes for
a four-wheel drive loader with a bucket capacity of l to 2 cubic metres.
This time is very easy to measure for company plant, with company
operators on company earthmoving tasks. A number of times can be
taken, averaged (ignoring the obviously wild or exceptional figures)
and recorded for the soil, weather and machine conditions and
particular operators. In this way accurate information will be obtained,
allowing accurate forecasts of probable outputs in future to be made.
These comments about the value of studying and timing "on-going"
plant operations apply to all plant operated, particularly to all the
mobile plant mentioned in this book although reference to this has not
been made for each item considered, to avoid repetition.
Consider now the travel cycle time: first the probable speed over the
prevailing ground conditions, i.e, rolling and gradient resistance
(or assistance), must be determined (see Chapter 4). Having establish-
ed the speed then the cycle time may be calculated as for the track
loader; if, however, the information available has only allowed the
travel gear to be determined, then further reference to the manufact-
urer's travel/time graphs of the following type will be necessary to
establish the probable variable cycle time (see Fig. 27). Thus in one
way or another the probable average total cycle time is determined.
Fig. 27. Travel time estimating chart [wheeled loader]
I I I I I I I
0 S0 100 150 200 250 300 Metres
Haul or Return Detance
Bucket selection:
Moistloamor 130 160 195 220 245 265 305 350 390 465 505 540 610
Sandy clay (99.5) (122.4) (149) (168) (187) (203) (233) (268) (298) (356) (386) (413) (467)
Sandandgravel 125 155 185 210 235 255 295 340 380 455 495 530 600
(96) (119) (142) (161) (180) (195) (226) (260) (291) (348) (379) (405) (459)
Good,common 105 135 165 190 210 230 265 305 340 375 410 445 510
earth (80) (103) (126) (145) (161) (176) (203) (233) (260) (287) (314) (340) (390)
Clay,hardand 90 110 135 160 180 195 230 270 305 340 375 410 475
tough (69) (84) (103) (122) (134) (149) (176) (207) (233) (260) (237) (314) (363)
Clay, wet and 55 75 95 110 130 145 175 210 240 270 300 330 385
sticky (42) (57) (73) (85) (99) (111) (134) (161) (184) (207) (230) (262) (295)
DRAGLINE OUTPUT
Table 2 gives the optimum output for draglines in bank yards (metres)
assuming an effective depth of cut, no delays, 90" angle swing, all
material loaded into haul units and bucket fill factor included. The
figures in this table require modifying according to the nature of the
material dug, the angle through which the boom swings from dig to
dump, the optimum depth of cut and the overall efficiency of the job.
The depth at which the excavator bucket digs is critical to the bucket
loading time and the angle through which the boom swings to the cycle
time. Tables 3 and 4 give the optimum depth of cut for maximum
output and the correction factors that must be applied to the hourly
production, according to the relationship of the actual digging depth
with the optimum, and the actual swing with the 90" angle on which
the production figures are based.
Material 3/4 f 1% 1% 1% 2 2%
(S7) (.76) (.96) (1.15) (1.34) (1.53) (1.91)
Light moist clay or 6.0 6.6 7.0 7.4 7.7 8.0 8.5
loam (1.83) (2.0) (2.14) (2.26) (2.34) (2.44) (2.59)
Wet, sticky clay 8.7 9.3 10.0 10.7 11.3 11.8 12.3
(2.65) (2.84) (3.0) (3.26) (3.45) (3.6) (3.75)
Dragline output:
Optimum output from table = 265 cubic yards (203 cubic metres)
14 ft (4.3 metres) as a percentage of optimum = 14 x 100 = 133%
10.5
From table (by interpolation) 133% at 60' swing correction factor
is 1.07.
Output using job efficiency factor of 67%, i.e. a 40 minute work hour
to allow for job difficulty, delays, etc. = 284 X 67% = 190 cubic
yards (146 cubic metres).
Slew angle
The angle through which the bucket slews from dig to dump should,
for maximum output, be kept as low as possible. A study of the
operation of a 0.7 cubic yard hydraulic excavator showed an average
cycle time of 0.34 minutes yielding an output (excluding stoppages) of
126 cubic yards per hour. When the slew angle was increased from
55" to 130' the cycle time increased by 4.8 seconds (0.08 minutes).
The possible loss in output due to the increase in slew angle is,
0.08-0.34 X 126 = 30 cubic yards per hour, i.e. approximately a
25% loss.
Method of employment
Bucket choice
Operator fatigue
Measured outputs
Concluding observations
The starting point to determine outputs must be the results and
analyses of previous tasks or manufacturers' theoretical or quoted
site production figures. Hourly output of the machine, allowing for
job and operator efficiency factors, is unlikely to exceed half of the
theoretical - in fact it may well be less.
SCRAPER OUTPUT
In Chapter 1 the basic considerations involved when determining
scraper outputs were detailed. In practice, the calculation is far more
complex: different machine manufacturers use differing approaches to
this problem and invariably data and tables are available for the
particular make and type of machine considered. Essentially there are
two approaches to the task of output estimation. The first, the easier
to understand and use, is a table of outputs for different haul
distances for specific machines : such information gives a rapid
indication of the size of machine required for any particular task. Its
shortcomings as a guide to the probable output for any other cir-
cumstances and conditions (gradients, etc.) are obvious.
The second approach is lengthy and rather tedious; it involves the
following activities.
(a) Identify haul and return routes from dig to dump sites.
(b) Draw profiles of these routes marking level stretches, favourable
and adverse gradients.
(C) Identify going conditions and calculate rolling resistance, laden
and unladen.
(d) Calculate gradient resistances.
(e) From manufacturers' graphs, determine overground speed
for the haul and return journey using calculated resistance
figures.
(0 Calculate variable cycle time.
Fixed cycle time estimate
(a) Determine from manufacturers' data optimum load time, i.e.
the best relationship between cycle time and percentage of bowl to
be filled in the loading operation (see page 23).
(b) Assess advantage or need for pusher to assist loading.
(C) Assess dump/spread time.
(d) Assess time waiting for pusher, if any.
(e) Arrive at fixed cycle time.
Output estimation
Having calculated the average cycle time, i.e. fixed plus variable,
one may estimate the probable output by applying the output factors,
i.e. swell, operator and job efficiency making allowance for the
percentage of the bowl that will be filled in the loading time selected.
As before, the output is simply: Load per cycle X number of cycles.
Operational efficiency
The calculation of the variable cycle times may be made for altern-
ative haul routes and the route offering the shortest cycle time may be
thus selected.
The importance of haul route maintenance cannot be over-
emphasised: the reader may care to calculate the probable output loss
arising from a 10% increase in the variable cycle time because of poor
haul route maintenance. Such calculations will quickly show the
economic advantage of retaining a grader on site for haul route main-
tenance.
The use of a ripper tooth on the rear of a crawler tractor may permit
the use of scrapers for excavations normally thought of as too hard for
scraper loading.
4 TRACKS Q WHEELS - SOME
PRACTICAL CONSIDERATIQNS
SOIL CLASSIFICATION
The simplest method of classifying soils is into frictional or cohesive
groups. The frictional are the small-particle, stony, sandy soils and
the cohesive are the thin plate-like particles such as clays. Identifying
soils by their primary classifications is important when considering
the use of wheeled or tracked plant. Traction over ground is dependent
on the shear strength of the ground in contact with the tracks or
wheels. In the case of frictional materials, pressure on the ground
increases the shear strength, thus reducing the risk of wheel or track
slippage through shear failure. Cohesive soils, particularly when water
is p r e s x t , have low shear strength; the small flakes or plate-like
particles readily slide over one another and increasing the pressure on
cohesive soils only marginally improves the shear value. Hence
caution should be exercised before deciding to use wheeled machines
on soils which are essentially clays when there is a possibility of heavy
rainfall. The maxim is: when in doubt, use tracks.
WHEELED PLANT
Rolling resistance
This is the property of wheeled plant which impedes its overground
motion. This resistance is compounded of tyre flexion, internal friction
of wheel and drive shaft bearings and the effort needed to climb out of
the depression in the ground which it has itself created due to the load
on it.
On a hard concrete road where there is no visible depression under
the wheel, the rolling resistance (RR) measured as a pull or push is
2% of the vehicle weight, i.e. 40 lb (20 kg) per metric tonne (2200 lb)
weight. For other purposes where there is some penetration by the
tyre this value increases and a table of rolling resistance values for
wheeled planthehicles on different soils is given below (Table 6).
Snow, packed
Snow, loose
Grade resistance
= 1540 kg
= 2200 kg
53
is best understood by looking at a manufacturer's table of gears,
speeds and power at the wheel rim (rimpull) both rated and maximum
for a particular equipment.
Table 7 gives these relationships for a wheeled motorised scraper.
Pounds rimpull
Tracked plant differs from the wheeled versions in that it lays its own
road wherever it goes and its available power is defined as the pull
exerted at the drawbar (drawbar pull). The figure for drawbar pull
takes care of the internal friction and the rolling resistance which are
reasonably consistent whatever surface the machine traverses. Grade
resistance, as has been stated, applies to tracked plant exactly as for
wheeled.
When considering the RR of a crawler tractor-towed scraper, for
example, the tractor may be ignored and only the weight on the
scraper wheels considered as before. The tractor must be taken into
account when calculating the GR.
TRACTION
Traction Factors
Rubber
tyres Tracks
Concrete
Clay loam, dry
Clay loam, wet
Rutted clay loam
Wet sand
Quarry pit
Gravel road (loose, not hard)
Packed snow
Ice
Firm earth
Loose earth
Coal, stockpiled
Rimpull = 9000 kg
POWER LOSS [ALTITUDE]
When relating drawbar or rimpull to the rolling or grade resistance to
be overcome, it is necessary to make one further adjustment if the
equipment is operating at more than 3000 feet above sea level. The
air at greater heights is less dense and thus the weight of air that
enters the engine on each aspiration stroke is less. The oxygen
available for combustion is proportionately reduced, resulting in a
lower output per power cycle. For any given speed the effect of this
power reduction is to reduce the drawbar pull or rimpull.
An approximation, adequate for purposes of simple earthmoving
calculations, is: reduce pull available from plant by 3% for each IQ99
feet of altitude above 3000 feet.
Note Further reading on this subject of altitude power reduction and
its effect on plant output is recommended for a complete understand-
ing of all the implications.
T COSTING
PUNDANdENTAL CONSIDERATIONS
The cost of owning and operating construction plant may be calculated
in many ways; because of the several variable costs involved there is
no single simple common method, although all methods involve the
same basic elements. Variables include, for example, the method of
depreciating the plant, the maintenance costs which vary with machine
age and usage and machine administrative costs, which may be
apportioned over the plant fleet in different ways. It is the inter-
dependence of such variables which causes the engineer most
difficulty when he is trying to establish the costs to his company or
purchasing and operating one or more items of plant compared with,
say, the cost of hiring similar plant.
Perhaps the simplest approach is to appreciate that the cost per
hour, for example, of owning and operating plant is made up of a
number of cost elements. These elements may be identified and
considered separately, then quantified and Walled to give the hourly
cost.
The elements may be grouped under two headings, fixed costs and
variable costs. The elements grouped under the heading fixed costs
are not fixed absolutely, but they may sensibly be considered as fixed
for any particular period (usually one year) over which costs are being
assessed, without affecting to any significant degree the final figures
calculated. By doing this the calculations are very much simplified.
The variable costs cover, as might be expected, those costs which
vary with age or usage, etc.
Depreciation Insurance
Interest on capital employed Administrative overheads.
Variable costs are:
FIXED COSTS
Depreciation
If an item of plant is purchased new on 1 January, stored under cover
for a year and then sold, the price realised would normally be less than
the purchase price. The difference in price, the loss to the purchaser is
the depreciation cost; this would of course have been greater if the
plant had been used during the year considered. Depreciation of plant,
industrial equipment and buildings, etc., is a subject about which
complete books have been written, but in the plant world it is
necessary to consider only two methods of depreciation to obtain cost
analysis results comparable in accuracy with the data available.
The two methods of depreciation are straight line and reappraisal.
STRAIGHT LINE METHOD
The plant item is given a life, say 5 years. The capital expended over
these years is catculated by taking the salvage value of the machine at
the end of this period from the original cost of the machine and
dividing this sum by the "life" in years chosen, e.g.:
Reappraised value:
% of original cost 65 % 50 % 35 70 25 % 20 %
Residual or
reappraised value E6500 E5000 E3500 E2500 E2000
Plotting these values in a graph we get the result shown in Fig. 29.
Fig. 28. Depreciation Fig. 29. Depreciation
[straight line method] graph [reappraisal method] graph
Difference in
estimated value £1900 E1800 E1700 Ell00
Superimposing the two graphs of depreciation on to one diagram,
the tabulated differences are shown diagramatically in Fig. 30.
Fig. 30. Graphic compankon of straight
line and reappraisal methods of depreciation
I 2 3 4 5
Yeersot Ownersh~p
IMPLICATIONS
The difference in depreciated value at the early period of ownership is
considerable, as much as f1900 after one year, and it is still f 1700 after
three years.
If a company uses the straight line method of depreciation when
calculating hire rate, fixing the period for the calculation at say six
years, then sells the machine at market value after say three years of
operation, then it could easily incur a sizeable loss. The true deprecia-
tion for the three-year period will not have been used for calculating
the hourly/weekly rate which should have been recovered.
PROVISION COST RATE
The effect of these different methods on the depreciation elements of
Depreciation element to be
recovered for each
operating hour £4.00 £2.50 E2.00 £1.87 £1.60
Table 13. Depreciation costs for 3000 hours peryear operation.
Depreciation element to be
recovered for each
operating hour £1.66 £1.00 £0.77 £0.66 £0.56
The element to be charged per hour for the use of capital in the
above example assuming a 1500-hour utilisation would be:
Insurance
Insurance costs are normally related to the current value of the plant
and are therefore dependent on natural age and working life. Normally
insurance costs are of the order of 1 % of machine current value and in
the example chosen would be 1%o f £10000, i.e. f l00 for the first year.
Administrative cost
VARIABLE COSTS
Fuels and lubricants
Under this cost heading may also be included filters, gaskets, etc.
-in fact, all consumable stores. These costs in the larger machines are
significant enough to be included as an element of the hourly provision
cost. They are obviously variable costs, because the greater the
machine usage the greater the cost of consumables. It is usual to
apportion these costs over the estimate of budgeted hours' utilisation
at a flat rate. In the case of our example of mobile plant this could
amount to £0.90 per hour. It is possible to cost all consumables against
overheads but the cost control system is that much cruder and there-
fore less accurate.
Maintenance
The costs of maintenance are directly dependent upon the working life
of the plant. These costs will vary in relation to:
(a) the type of work on which the plant is used;
(b) the designed reliability of the plant;
(c) the output achieved by the user;
(d) the operator's ability, attitude and knowledge;
(e) the quality of the maintenance effected.
There is, however, an inevitable tendency for plant maintenance to
increase with working life. Within organisations normal maintenance
costs for particular items of plant can be averaged and these are often
expressed for convenience as a percentage of the original purchase
price. For certain types of plant the cost of maintenance can exceed
100% of the original purchase price over 10000 hours. A typical break-
down of maintenance costs is shown in Table 15.
Table 15. Typicalmaintenance costs for a smallitem of mobile plant
Any figures given here would be out of date before the book was
published; readers are therefore cornmended the Contractors' Plant
Association's analyses of operator costs published as a supplement to
its periodic studies into machine operating costs. Operator costs are
an "on" or additional cost which are simply included in the provision
cost. The fact that operators employed by a company continue to be
paid when not actively operating plant is an obvious disadvantage of
ownership compared with hire.
Once plant has been purchased it is too late to consider the probable
cost of owning and operating it; better that the probable cost be
calculated for the likely variables of hours' utilisation per year and
period of ownership before any purchase is made. At worst, such an
exercise allows an immediate examination of the economic implica-
tions of hiring rather than buying.
The simplest method is to construct a table in the form illustrated in
Table 16 using the methods described in the preceding pages. By
constructing tables for different probable annual hours' utilisation the
complete picture is presented and such decisions as minimum viable
period of ownership and minimum annual hours' usage, which would
justify purchase, established.
Table 16. Sample provision cost table [small mobile machine, original cost
£lOOOO]
Depreciation:
Reappraised value
Depreciation each year
Cumulative depreciation cost
Depreciation cost element per hour
Incurancc cost:
Adniinistrative costs:
Maintenance costs:
To cover:
Depreciation
Capital Investment
Insurance
Administrati~e
Maintenance
Accommodating inflation
In all the calculations made to determine the various cost elements
that make the hourly rate it has been assumed that when cost forecasts
are made for future years account will have been taken of the inevit-
able increases that will occur, for example, wages, rent or rates,
heating costs, fuel, etc. The normal projections allow for a rate of
increase proportionally more than the rate for the preceding year.
In the case of a construction company that hires out its plant as a
source of income it will need to adjust its hire rate to include an
element to cover the inevitable increased cost of replacing the item of
plant producing the hire income.
Low cost plant
Certain items of plant are invariably owned by the construction
company, e.g. small dumpers, compaction equipment, etc. Such items
have negligible resale value and are usually written off over a period of
three or four years. The method of calculating the cost to be charged to
site or a contract for this type of plant is as follows:
Purchase price (say) £2000
Working life 3 years
Anticipated utilisation 40 weeks per year
Cost calculation for three-year period:
Depreciation cost E2000
Maintenance cost (estimated at 50% purchase price) El 000
Administrative costs E400
Insurance 3% of f l000 (half of new cost), site only E30
Finance cost 20% of f l000 for three years f 600
GENERAL NOTE
Costs in any particular case will depend on the type of plant, the
requirement for that plant, the area and type of operation and the
current financial climate. For example, lack of availability of a partic-
ular plant item, coinciding with a high demand for that item, can result
in machine appreciation, not depreciation as would normally occur.
This emphasises the need to base all cost studies on local facts, situa-
tions and experience, and not on the figures in the examples to this
chapter. The latter are given to illustrate the methods of costing, which
are, of course, universally applicable.
The selection of an item or items of construction plant for a contract
or series of contracts is a fairly lengthy and complex process. The
larger companies retain specialists in this field and these acquire a
mass of useful data culled from previous contracts on which future
plant selection decisions can largely be based. For smaller companies
without access to this information, however, a logical and cost effective
approach to plant selection is still possible, and the results of such a
process are certain to be much better than an inspired guess and at
worst will provide a method of determining the effects on cost and
output of selecting a particular machine. One of the dangers of any
analytical or selective process is that the effort involved in its employ-
ment may not be justified by the end result and a very objective
view must be taken at the outset to ensure that the construction
project warrants detailed consideration of the alternative machines
available.
The selection process conveniently divides into six stages:
TASK IDENTIFICATION
PRELIMINARY SELECTION
Stripping topsoil
DOZER D4 OR LARGER
Haul distance up to 100 metres.
SCRAPER TOWED
Haul distance up to 400 metres, preferable to dozer when contamin-
ation of the topsoil by the sub-soil is to be avoided.
SCRAPER MOTORISED (INCLUDING SELF-LOADING)
Haul distance up to about 3000 metres. (Note No scraper can travel
laden on public road.)
LOADING SHOVEL
Normally in Britain the tracked version is used, the topsoil be in^
loaded into haul units for transporting to tip. Wheeled loading shovels
may be used on primarily frictional soils, and in dry conditions may
achieve up to 25% better output with the same capacity bucket. May
strip and transport over short distances. Some operational advantage
may be gained by using a 4-in-l bucket but this benefit may be offset
by a reduction in the weight capacity of the bucket, since the 4-in-1
version is heavier than the standard pattern.
Mass excavation
DOZER
The bull/angle dozer yields the lowest cost method of digging and
moving materials over short distances. The angle dozer has a lower
output than the equivalent bulldozer but it is more suited to sidelong
cuts into hillsides.
Dozers may be used in conjunction with belt conveyors. They are
suitable for spreading loose fill. Both machines handle most materials,
including blasted rock.
SCRAPER
Crawler tractor towed Haul distance up to about 400 metres.
GRADER
The best machine for this task.
DOZER
Angle blade should be used.
SCRAPER
May be used if grader or dozer is not available.
Trenching
MULTI-BUCKET TRENCHER
Continuous in operation, specialised in design and application only
justifiable economically for long continuous trenches for water or
electric mains, etc.
EXCAVATOR BACKHOE
180" or 360' models, wheeled or tracked, these are versatile machines
in that they may be used in other roles, e.g. craneage, when not dig-
ging. Selection will depend on volume to be moved per hour, restrict-
ions improved by timbering method of soil disposal but in view of the
time the machine is likely to stand idle, the smallest machine meeting
the requirements should be selected.
MACHINE OUTPUT ESTIMATION
The task in terms of material volume, swell factor, weight per cubic
metre, the tip area in terms of location, route and route condition,
configuration and accessibility, the start/finish times and time avail-
able having been clearly defined. The machines which could, following
a study of the preliminary selection criteria, carry out the task having
been identified, the next stage is the determination of the output
required of the machine selected to complete the task in the time
available. Bank cubic metres (BCM) should be converted using the
swell factor into loose cubic metres (LCM) and divided by the working
hours planned for the operation allowing in the calculation at some
stage a time reserve for unforeseen contingencies, e.g. breakdown,
abnormal weather conditions, etc. Thus the LCM per hour required to
be excavated and tipped may be established.
The plant items or combinations of items which may carry out the
operation, always with the fact in mind that within limits, the larger
the capacity of the plant which can be used the lower the cost of the
operation is likely to be, may then be considered for their probable
output in the conditions prevailing. This estimation must take account
of all the factors that may affect the output particularly the operating
conditions, terrain formation, operator efficiency and the job efficiency
(or inefficiency). The machine outputs estimated must then be com-
pared with that required to complete the task in time.
MACHINE MATCHING
OUTPUT COSTING
Having determined the machines or machine groups that could
adequately and safely carry out the task, the hourly owning/operating
cost or hire cost for each equipment or equipment group should be
divided by the estimated hourly output, for example given a hire cost
of £10 and an output of l00 cubic metres per hour, then the cost per
metre moved is
£10.00
loo = lop per cubic metre.
77
SELECTION IN PRACTICE
I
0L l l I
200 400 600 800
Metres -one way haul distance
FORMS OF MAINTENANCE
Two descriptions or titles are commonly given to maintenance
systems: these are preventative maintenance and planned mainten-
ance, but before defining these terms it is necessary to state that a
truly effective maintenance system must combine the features of both.
Preventative maintenance
Preventative maintenance originated in the aircraft industry where, to
reduce the risk of mechanical failure in flight, components or assem-
blies were replaced at predetermined intervals, e.g. an engine with a
declared flight life of 1000 hours would be replaced after 1000 hours
flying time and then overhauled, tested and held in store for future
installation. The life of components or assemblies selected for replace-
ment would be based initially on bench tests or previous performance
and increased as experience in service was gained. It can be seen that
this expensive form of maintenance, i.e. replacing before failure has
occurred, has greatly reduced the risk of failure in flight.
The consequences of component or assembly failure in construction
plant are unlikely to be anywhere near as catastrophic as a failure in an
aircraft, hence a full preventative maintenance system whereby com-
ponents or assemblies are changed after a fixed life is very rarely used
in the construction industry. One known example, however, is that
where the transmission unit of a large batching plant is changed after
18 months' service because experience has shown that after this period
the risks of sudden failure are high.
The term preventative maintenance in the construction industry
is usually applied to those inspection, adjustment or tightening
routines which experience has taught need to be done at prescribed
intervals if a premature failure is to be prevented. Examples could
include clutch adjustments, brake adjustments, wheel-nut tightening,
track tensioning and rope inspection. It is in this form that preventative
routines are normally used in construction plant maintenance. The
classic example of preventative maintenance practised by most
motorists is the changing of spark plugs after 10000 vehicle miles.
By making this change even though the engine is running perfectly
the risk of engine failure is appreciably reduced and the expenditure
therefore justified.
Planned maintenance
INSPECTION
An essential component of any maintenance scheme is regular inspect-
ion. Such inspection should be carried out not less than monthly,
preferably by a full-time trained inspector and the results of the
inspection reported back to the depot manager. The report should be
written and follow a prescribed format covering the following:
I Inspection reports
Notes Symbots
Schedule to be drawn up at least X Indicates major or monthly X2 Figwe by theside of X notes
'monthly in advance and more service due. Detail of service specialservice needed, e.g. new
usually six-monthly when contracts contained in appropriate engine service, compressor oil
or hire period allows. schedule. and filter change.
@ Circle round cross indicates X Blacked out indicates machine
inspecnonlmamrenance carried in depot.
out.
Rationalisation of lubricants
Provision of filters
COMPUTER FACILITIES
It is difficult today to find people who are content to spend long periods
maintaining and analysing records. In the smaller companies cash
availability usually precludes the full-time employment of a clerk for
this task and the volume of work involved is not really likely t~ justify
it. Recently, greater use has been made of computers to carry out a
good deal of the more routine drudgery associated with record-
keeping. At least one computer bureau is offering a packaged deal
which covers the adaptation of a standard programme to a company's
particular needs and then sells computer time for the production of
detailed analyses of the records. The advantages of such a system are
very obvious. Analyses can be made extremely quickly and the results
presented in a tidy, easily readable, permanent form. Monthly totals
of plant utilisation and costs can be had a week after the month's end.
Clerical effort is still required to transfer the information from various
sources on to the computer input sheets, but the master file of equip-
ment held, which covers all the original information, can be amended
and reprinted extremely quickly and simply.
The following reports may be rapidly provided using a computer:
PLANT TRAINING
The Industrial Training Act 1964 highlighted the need for a major
improvement in the quantity and quality of training in the major
industries. In spite of a somewhat shaky start, boards have been
established in the major industries and the Construction Industry
Training Board is the one specifically charged with the task of
improving training within the construction industry.
So far as training connected with construction plant is concerned,
the major developments have been:
(a) the formalisation and improvement of mechanic training;
(b) the establishment of courses for plant technicians;
(c) the establishment of a plant operator school;
(d) the development of plant management courses.
CONCLUSION
If this book has opened the door to a better understanding of the
selection, use, control and costing of earthmoving plant and encour-
aged the reader to seek further information about specific areas, then
its aim will have been achieved.
APPENDIX: SO E USEFUL TA
AND DATA
Earth, loam:
dry
wet
Iron ore:
magnetite
pyrite
hematite
Limestone
Sand:
dry, loose
wet, packed
Sandstone
Trap rock
CONVERSION OF METRIC AND US WEIGHTS AND MEASURES
Measurements of length
Kilometres Miles
Kilometres Yards
Kilometres Feet
Metres Yards,
Metres Feet
Metres Inches
Centimetres Inches
Millimetres Inches
Measurements of area
Sq Kilometres X 0.3861 -
- Sq Miles
Sq Kilometres X 247.11 - Acres
Hectares X 2.471 Acres
Sq Metres X 1.196 - Sq Yards
Sq Metres X 10.764 - Sq Feet
Sq Centimetres X 0.155 - Sq Inches
Sq Millimetres X 0.00155 - Sq Inches
Measurements of volume
Liquid measure
US Gals X 0.833 -
- Imp Gals
Imp Gals X 1.2009 - US Gals
3.785 -
- Litres
Gallons X
Qts X 0.946 Litres
-
Litres X 0.2642 - Gals
Litres l .OS7
-
- Qts
X
Measures of weight
-
Pounds X 0.453 - Kilograms
-
Kilograms X 2.2046 - Pounds
TRAVEL TIME IN MINUTES/TRAVEL DISTANCE IN FEET
Speed Time (mins)
(m.p.h.)
1.136 2.275
0.568 1.136
0..779 0.758
0.284 0.568
0.227 0.454
0.189 0.3'8
0.162 0.324
0.142 0.284
0.126 0.252
0.114 0.227
0.103 0.206
0.095 0.189
0.087 0.174
0.081 0.162
0.076 0.152
0.065 0.129
0.057 0.1 l 3
0.050 0.101
0.045 0.090
Example To estimate time required to travel 550 feet at 6.0 m.p.h. first
establish time for 500 ft at 6.0 m.p.h. = 0.95
50 ft = % of time for 100 ft at 6.0 m.p.h. = 0.09
Total = 1.04 minutes
Angle of repose
Height
(ft) 20' 25' 30' 35' 45'
APPROXIMATE WEIGHTS OF MATERIALS
Note These weights are given in pounds per cubic yard and are only approx-
imate, varying with moisture content, chemical composition and source.
Loose In-place
weight weight
Material (lb/cu yd) (Ib/cu yd)
Feldspar
Gneiss
Granite
Gypsum
Ice
Iron ore (Hermatite)
Limonite
Magnetite
Pyrites
Taconite
Kaolinite
Limestone
Marble
Mar1
Mud
Phosphate rock
Porphyry
Potash
Pumice
Riprap rock-average
Rock salt
Sandstone
Shale
Slag:
Furnace
Ground (?hin.)
Crushed
Snow
Sulphur
Talc
Trap rock
INDEX