SCENARIO ONE:

· Working at or inspecting infrastructure


which is located on the verge and not
blocking the footpath or roadway.
· Work to be completed in a single shift.
· Speed limit is up to 80km/h.

VERGE (GRASS, CONCRETE, ETC.)


INFRASTRUCTURE BEING
INSPECTED/WORKED UPON

USE THIS SCENARIO WHEN:


· On approach to your site, there is at
least 100m or 2D sight distance,
whichever is greater, for approaching
vehicles in every direction or able to see
the end of the road.
YOUR PARKED VEHICLE WITH A · You can park legally in a place where
VISIBLE FLASHING AMBER LIGHT other cars can still go around your
vehicle without needing to cross into the
opposing traffic lane.
· The entire work area is at least 3m clear
of a moving traffic lane for speeds of 80
km/h or less.
· For speeds of 60 km/h or less, the work
area should not encroach onto a moving
traffic lane (i.e. you can work up to the
kerb). Symbolic worker signs and/or
delineating cones would be required in
this case, as per other scenario cards.

VALUE OF 'D' METRES


TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h

(IF ANY OF THESE CONDITIONS CANNOT BE


MET, DO NOT USE THIS PLAN)

Job Number: ALT211079VIC-DG-0001

(Plan 1 - Sheet 1 of 2)
Prepared By:

FOOTPATH OR UNPAVED PATH


WHICH PEDESTRIANS MIGHT USE

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.

RIIWHS302D Implement traffic management plan.


Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.

RIIWHS302D Implement traffic management plan.


TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 1 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0001 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO TWO:
· Working at or inspecting infrastructure
which is located on the verge and not
VERGE (GRASS, CONCRETE, ETC.) blocking the footpath or roadway.
· Work to be completed in a single shift.
INFRASTRUCTURE BEING · Speed limit is up to 80km/h.
INSPECTED/WORKED UPON

USE THIS SCENARIO WHEN:


WORK AREA MUST BE LOCATED AT LEAST 3.0M
AWAY FROM MOVING TRAFFIC LANE · On approach to your site, there is at
least 100m or 2D sight distance,
YOUR PARKED VEHICLE WITH A
whichever is greater, for approaching
VISIBLE FLASHING AMBER LIGHT
vehicles in every direction or able to see
the end of the road.
· You can park legally along a road with
no lane line-marking.
· The entire work area is at least 3m clear
of a moving traffic lane for speeds of 80
km/h or less.
· For speeds of 60 km/h or less, the work
area should not encroach onto a moving
traffic lane (i.e. you can work up to the
kerb). Symbolic worker signs and/or
delineating cones would be required in
this case, as per other scenario cards.

VALUE OF 'D' METRES


TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h

(IF ANY OF THESE CONDITIONS CANNOT BE


MET, DO NOT USE THIS PLAN)

Job Number: ALT211079VIC-DG-0002

(Plan 2 - Sheet 1 of 2)
Prepared By:

FOOTPATH OR UNPAVED PATH


WHICH PEDESTRIANS MIGHT USE

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.

RIIWHS302D Implement traffic management plan.


Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.

RIIWHS302D Implement traffic management plan.


TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 2 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0002 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO THREE:
· Working at or inspecting infrastructure which
is located on verge and not blocking the
INFRASTRUCTURE BEING INSPECTED WITH footpath or roadway.
APPROPRIATE GUARDING/BARRICADING USED · Work to be completed in a single shift.
VERGE (GRASS, CONCRETE, ETC.) · Speed limit is up to 60km/h.

USE THIS SCENARIO WHEN:


POSITION YOUR VEHICLE TO OFFER PROTECTION TO THE WORK
AREA AND ACHIEVE CLEARANCE TO LIVE TRAFFIC · On approach to your site, there is at least
100m or 2D sight distance, whichever is
greater.
· You can park legally in a place where other
cars can still go around your vehicle without
needing to cross into the opposing traffic lane.
· The speed limit is 60km/h or less and the
PLACE TRAFFIC CONES EVERY 4m FOR
work area does not encroach onto a moving
DELINEATION, WITH AT LEAST 5 BEHIND
traffic lane (i.e. you can work up to the kerb).
THE VEHICLE
Note:
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
FOOTPATH OR UNPAVED PATH '2D' from the work area for approach speeds
WHICH PEDESTRIANS MIGHT USE of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.

VALUE OF 'D' METRES


FOR ADVANCE SIGN TRAFFIC SPEED 'D' VALUE
PLACEMENT REFER 50km/h or LESS 15m
TO NOTE AND TABLE 60km/h 45m
OF "VALUE OF 'D' EQUAL TO SPEED
METRES" 70km/h OR GREATER
OF TRAFFIC IN km/h

· Where possible, the vehicle should be placed


RUN THE CONES TO JUST PAST to offer protection from approaching traffic.
THE WORK AREA FOR SAFETY

MINIMUM OF 3m MUST BE
MAINTAINED FOR PASSING
TRAFFIC AT SPEEDS UP TO 60
KM/H (IF ANY OF THESE CONDITIONS CANNOT BE
MET, DO NOT USE THIS PLAN)

Job Number: ALT211079VIC-DG-0003

(Plan 3 - Sheet 1 of 2)
Prepared By:

FOR ADVANCE SIGN PLACEMENT REFER


TO NOTE AND TABLE OF "VALUE OF 'D'
METRES"
(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
MANHOLE GUARD/COVER
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 3 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0003 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO FOUR:
· Working at or inspecting infrastructure which is
located on verge and not blocking the footpath
or roadway.
· Vehicle parked on the verge.
· Work to be completed in a single shift.
· Speed limit is up to 80km/h.
INFRASTRUCTURE BEING VERGE (GRASS, CONCRETE, ETC.)
INSPECTED/WORKED UPON
USE THIS SCENARIO WHEN:
· On approach to your site, there is at least
100m or 2D sight distance, whichever is
CLEARANCE TO EDGE OF TRAFFIC
LANE AT LEAST 1.2M FOR SPEEDS greater.
ABOVE 60KM/H & UP TO 80 KM/H · The speed limit is 80km/h or less and the
clearance to edge of traffic lane is at least
1.2m.
PLACE TRAFFIC CONES · The speed limit is 60km/h or less and the
EVERY 4m, WITH AT LEAST 2 work area does not encroach onto a moving
BEHIND VEHICLE traffic lane (i.e. you can work up to the kerb).
Note:
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
FOR ADVANCE SIGN PLACEMENT REFER TO NOTE '2D' from the work area for approach speeds
AND TABLE OF "VALUE OF 'D' METRES" of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.
VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h
FOR ADVANCE SIGN
PLACEMENT REFER TO
· Where possible, the vehicle should be placed
NOTE AND TABLE OF
"VALUE OF 'D' METRES" to offer protection from approaching traffic.

(IF ANY OF THESE CONDITIONS CANNOT BE


YOUR PARKED VEHICLE WITH A MET, DO NOT USE THIS PLAN)
VISIBLE FLASHING AMBER LIGHT
Job Number: ALT211079VIC-DG-0004

RUN THE CONES TO JUST PAST THE WORK AREA FOR SAFETY (Plan 4 - Sheet 1 of 2)
Prepared By:

FOOTPATH OR UNPAVED PATH


WHICH PEDESTRIANS MIGHT USE

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 4 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0004 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO FIVE:
· Working at or inspecting infrastructure which is
located on the verge and not blocking the
FOR ADVANCE SIGN PLACEMENT REFER footpath or roadway.
TO NOTE AND TABLE OF "VALUE OF 'D' · Work to be completed in a single shift.
METRES" · Speed limit is up to 60km/h (no center line).
VERGE (GRASS, CONCRETE, ETC.)
USE THIS SCENARIO WHEN:
RUN THE CONES TO JUST PAST · On approach to your site, there is at least
THE WORK AREA FOR SAFETY 100m or 2D sight distance, whichever is
INFRASTRUCTURE BEING INSPECTED WITH greater.
APPROPRIATE GUARDING/BARRICADING USED · You can park legally in a place where other
cars can still go around your vehicle.
· The speed limit is 60km/h or less and the
POSITION YOUR VEHICLE TO OFFER work area does not encroach onto a moving
PROTECTION TO THE WORK AREA AND traffic lane (i.e. you can work up to the kerb).
ACHIEVE CLEARANCE TO LIVE TRAFFIC
Note:
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
PLACE TRAFFIC CONES EVERY 4m FOR · The symbolic worker sign shall be placed at
DELINEATION, WITH AT LEAST 5 BEHIND '2D' from the work area for approach speeds
THE VEHICLE of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.

FOOTPATH OR UNPAVED PATH VALUE OF 'D' METRES


WHICH PEDESTRIANS MIGHT USE TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h

· Where possible, the vehicle should be placed


to offer protection from approaching traffic.

(IF ANY OF THESE CONDITIONS


CANNOT BE MET, DO NOT USE THIS
PLAN)

MINIMUM OF 6m MUST BE Job Number: ALT211079VIC-DG-0005


MAINTAINED FOR PASSING
(Plan 5 - Sheet 1 of 2)
TRAFFIC AT SPEEDS UP TO 60
KM/H Prepared By:

FOR ADVANCE SIGN PLACEMENT REFER


TO NOTE AND TABLE OF "VALUE OF 'D'
METRES"
(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods MANHOLE GUARD/COVER

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 5 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0005 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO SIX:
· Working at or inspecting infrastructure which is
located on the verge and not blocking the
footpath or roadway.
· No vehicle on site.
· Work to be completed in a single shift.
· Speed limit is up to 80km/h.

VERGE (GRASS, CONCRETE, ETC.)


USE THIS SCENARIO WHEN:
· On approach to your site, there is at least
100m or 2D sight distance, whichever is
greater.
· The speed limit is 80km/h or less and the
clearance to edge of traffic lane is at least
1.2m.
INFRASTRUCTURE BEING INSPECTED WITH · The speed limit is 60km/h or less and the
APPROPRIATE GUARDING/BARRICADING USED work area does not encroach onto a moving
traffic lane (i.e. you can work up to the kerb).
PLACE TRAFFIC CONES EVERY 4m, WITH AT
LEAST 5 BEFORE THE WORK AREA Note:
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
FOOTPATH OR UNPAVED PATH alone are present and working closer than 3m
WHICH PEDESTRIANS MIGHT USE (1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
'2D' from the work area for approach speeds
of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.

VALUE OF 'D' METRES


TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h

CLEARANCE TO EDGE OF FOR ADVANCE SIGN


TRAFFIC LANE AT LEAST 1.2M PLACEMENT REFER TO
FOR SPEEDS ABOVE 60KM/H & NOTE AND TABLE OF
UP TO 80 KM/H "VALUE OF 'D' METRES"

(IF ANY OF THESE CONDITIONS CANNOT BE


MET, DO NOT USE THIS PLAN)

Job Number: ALT211079VIC-DG-0006

RUN THE CONES TO JUST PAST (Plan 6 - Sheet 1 of 2)


THE WORK AREA FOR SAFETY Prepared By:

FOR ADVANCE SIGN PLACEMENT REFER TO NOTE


AND TABLE OF "VALUE OF 'D' METRES"

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
MANHOLE GUARD/COVER
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 6 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0006 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO SEVEN:
· Working at or inspecting infrastructure
which is located on the footpath and
AREA WHERE PEDESTRIANS ARE TO BE DETOURED SHALL BE OF A requires full footpath closure.
SIMILAR QUALITY AND TYPE AS THE EXISTING IF POSSIBLE. AS A · Work to be completed in a single shift.
PLACE TRAFFIC CONES EVERY 4m
GUIDE THE TEMPORARY PATH SHOULD BE:
· Speed limit is up to 80km/h.
· AT LEAST 1.2m WIDE (2.0m WIDE IF IT IS A SHARED PATH)
· A FIRM SURFACE (FOR WHEELCHAIRS AND PRAMS)
· FREE OF WORK EQUIPMENT AND MATERIALS VERGE (GRASS, CONCRETE, ETC.) USE THIS SCENARIO WHEN:
· MORE THAN 1.2m FROM TRAFFIC AT SPEEDS UP TO 60km/h AND · On approach to your site, there is at
MORE THAN 3.0m FROM TRAFFIC AT SPEEDS OF 70-80km/h
least 100m or 2D sight distance,
whichever is greater, for approaching
vehicles in every direction or able to see
PEDESTRIANS DETOUR (T8-2) SIGNS SHALL BE the end of the road.
POSITIONED AT BOTH ENDS OF THE WORK AREA OR · You can park legally in a place where
PROPERLY MOUNTED TO THE WORK BARRIER other cars can still go around your
vehicle without needing to cross into the
opposing traffic lane.
FOOTPATH OR · The entire work area is at least 3m clear
UNPAVED PATH of a moving traffic lane for speeds of 80
WHICH km/h or less.
PEDESTRIANS · For speeds of 60 km/h or less, the work
MIGHT USE area should not encroach onto a moving
traffic lane (i.e. you can work up to the
PED
kerb). Symbolic worker signs and/or
ES
TR
IA NS
delineating cones would be required in
this case, as per other scenario cards.
VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h

(IF ANY OF THESE CONDITIONS CANNOT BE


MET, DO NOT USE THIS PLAN)

Job Number: ALT211079VIC-DG-0007

(Plan 7 - Sheet 1 of 2)
Prepared By:

YOUR PARKED VEHICLE WITH A


INFRASTRUCTURE BEING INSPECTED WITH VISIBLE FLASHING AMBER LIGHT
APPROPRIATE GUARDING/BARRICADING USED
(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
MANHOLE GUARD/COVER
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan. PED
ES
TRIA
RIIWHS205D Control traffic with Stop-Slow bat. NS
1200 x 300 mm T8-2 PEDESTRIANS
(ARROW) SIGN (1x Left and 1x Right)
Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 7 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0007 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO EIGHT:
· Working at or inspecting infrastructure which
is located on the footpath and requires full
AREA WHERE PEDESTRIANS ARE TO BE DETOURED SHALL BE OF A footpath closure.
SIMILAR QUALITY AND TYPE AS THE EXISTING IF POSSIBLE. AS A · Work to be completed in a single shift.
GUIDE THE TEMPORARY PATH SHOULD BE: · Speed limit is up to 60km/h.
· AT LEAST 1.2m WIDE (2.0m WIDE IF IT IS A SHARED VERGE (GRASS, CONCRETE, ETC.)
PATH)
· A FIRM SURFACE (FOR WHEELCHAIRS AND PRAMS)
· FREE OF WORK EQUIPMENT AND MATERIALS PEDESTRIANS DETOUR (T8-2) SIGNS SHALL BE
· MORE THAN 1.2m FROM TRAFFIC AT SPEEDS UP TO POSITIONED AT BOTH ENDS OF THE WORK AREA OR
60km/h PROPERLY MOUNTED TO THE WORK BARRIER
USE THIS SCENARIO WHEN:
· On approach to your site, there is at least
RUN THE CONES TO JUST PAST 100m or 2D sight distance, whichever is
THE WORK AREA FOR SAFETY greater.
FOR ADVANCE SIGN PLACEMENT REFER · You can park legally in a place where other
TO NOTE AND TABLE OF "VALUE OF 'D' cars can still go around your vehicle without
METRES" needing to cross into the opposing traffic lane.
· The speed limit is 60km/h or less and the
work area does not encroach onto a moving
traffic lane (i.e. you can work up to the kerb).

PLACE TRAFFIC CONES EVERY 4m FOR PED


ES
TR
Note:
IAN
DELINEATION, WITH AT LEAST 5 BEFORE S

· A symbolic worker sign shall be displayed


THE WORK AREA when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
'2D' from the work area for approach speeds
of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.
VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
FOR ADVANCE SIGN EQUAL TO SPEED
PLACEMENT REFER TO 70km/h OR GREATER
OF TRAFFIC IN km/h
NOTE AND TABLE OF
"VALUE OF 'D' METRES"
· Where possible, the vehicle should be placed
to offer protection from approaching traffic.

(IF ANY OF THESE CONDITIONS


CANNOT BE MET, DO NOT USE THIS
PLAN)
MINIMUM OF 3m MUST BE
MAINTAINED FOR PASSING Job Number: ALT211079VIC-DG-0008
TRAFFIC AT SPEEDS UP TO 60
KM/H (Plan 8 - Sheet 1 of 2)
Prepared By:

POSITION YOUR VEHICLE TO OFFER


INFRASTRUCTURE BEING INSPECTED WITH PROTECTION TO THE WORK AREA AND
FOOTPATH OR UNPAVED PATH APPROPRIATE GUARDING/BARRICADING USED ACHIEVE CLEARANCE TO LIVE TRAFFIC
WHICH PEDESTRIANS MIGHT USE

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
MANHOLE GUARD/COVER
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan. PED
ES
T
RIIWHS205D Control traffic with Stop-Slow bat. RIA
NS
1200 x 300 mm T8-2 PEDESTRIANS
(ARROW) SIGN (1x Left and 1x Right)
Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 8 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0008 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO NINE:
· Working at or inspecting infrastructure which is
located on a footpath at a T-intersection and
not blocking the footpath or roadway.
· Vehicle parked on the verge.
· Work to be completed in a single shift.
· Speed limit is up to 80km/h.

YOUR PARKED VEHICLE WITH A


VISIBLE FLASHING AMBER LIGHT USE THIS SCENARIO WHEN:

CLEARANCE TO EDGE OF TRAFFIC · On approach to your site, there is at least


LANE AT LEAST 1.2M FOR SPEEDS 100m or 2D sight distance, whichever is
SYMBOLIC WORKER SIGN ABOVE 60KM/H & UP TO 80 KM/H greater.
TO BE PLACED 'D' m PRIOR INFRASTRUCTURE BEING INSPECTED WITH · The speed limit is 80km/h or less and the
TO THE INTERSECTION APPROPRIATE GUARDING/BARRICADING USED clearance to the edge of traffic lane is at least
1.2m.
· The speed limit is 60km/h or less and the
work area does not encroach onto a moving
traffic lane (i.e. you can work up to the kerb).
Note:
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
'2D' from the work area for approach speeds
of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.

FOR ADVANCE SIGN VALUE OF 'D' METRES


PLACEMENT REFER TRAFFIC SPEED 'D' VALUE
TO NOTE AND 50km/h or LESS 15m
TABLE OF "VALUE 60km/h 45m
OF 'D' METRES" 70km/h OR GREATER
EQUAL TO SPEED
OF TRAFFIC IN km/h

· Where possible, the vehicle should be placed


RUN THE CONES TO JUST to offer protection from approaching traffic.
PAST THE WORK AREA FOR
SAFETY

FOOTPATH OR UNPAVED PATH (IF ANY OF THESE CONDITIONS


WHICH PEDESTRIANS MIGHT USE CANNOT BE MET, DO NOT USE THIS
PLAN)
VERGE (GRASS,
CONCRETE, ETC.) Job Number: ALT211079VIC-DG-0009

(Plan 9 - Sheet 1 of 2)
FOR ADVANCE SIGN Prepared By:
PLACEMENT REFER PLACE TRAFFIC CONES EVERY 4m FOR
TO NOTE AND DELINEATION.
TABLE OF "VALUE
OF 'D' METRES"

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
MANHOLE GUARD/COVER
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 9 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0009 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO TEN:
· Working at or inspecting infrastructure which is
located on the verge at a T-intersection and
not blocking the footpath or roadway.
· Vehicle parked on the verge.
· Work to be completed in a single shift.
· Speed limit is up to 80km/h.

SYMBOLIC WORKER SIGN


TO BE PLACED 'D' m PRIOR
TO THE INTERSECTION PLACE TRAFFIC CONES USE THIS SCENARIO WHEN:
EVERY 4m, WITH AT LEAST 2 · On approach to your site, there is at least
BEHIND VEHICLE 100m or 2D sight distance, whichever is
RUN THE CONES TO JUST PAST greater.
THE WORK AREA FOR SAFETY · The speed limit is 80km/h or less and the
clearance to edge of traffic lane is at least
1.2m.
· The speed limit is 60km/h or less and the
work area does not encroach onto a moving
traffic lane (i.e. you can work up to the kerb).
Note:
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
'2D' from the work area for approach speeds
of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.
VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
CLEARANCE TO EDGE OF 50km/h or LESS 15m
TRAFFIC LANE AT LEAST 1.2M 60km/h 45m
FOR SPEEDS ABOVE 60KM/H & EQUAL TO SPEED
UP TO 80 KM/H 70km/h OR GREATER
OF TRAFFIC IN km/h
FOR ADVANCE SIGN
PLACEMENT REFER TO
NOTE AND TABLE OF · Where possible, the vehicle should be placed
"VALUE OF 'D' METRES" to offer protection from approaching traffic.

YOUR PARKED VEHICLE WITH 2


VISIBLE FLASHING AMBER LIGHTS

(IF ANY OF THESE CONDITIONS CANNOT BE


MET, DO NOT USE THIS PLAN)
INFRASTRUCTURE BEING
INSPECTED WITH APPROPRIATE Job Number: ALT211079VIC-DG-0010
GUARDING/BARRICADING USED (Plan 10 - Sheet 1 of 2)
FOOTPATH OR UNPAVED PATH
WHICH PEDESTRIANS MIGHT USE Prepared By:

FOR ADVANCE SIGN


PLACEMENT REFER TO
NOTE AND TABLE OF
"VALUE OF 'D' METRES" VERGE (GRASS,
CONCRETE, ETC.)

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
MANHOLE GUARD/COVER
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 10 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0010 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
INFRASTRUCTURE BEING SCENARIO ELEVEN:
INSPECTED/WORKED UPON · Working at or inspecting infrastructure which is
located on the verge and not blocking the
POSITION YOUR VEHICLE TO OFFER footpath or roadway.
PROTECTION TO THE WORK AREA AND · Work to be completed in a single shift.
ACHIEVE CLEARANCE TO LIVE TRAFFIC · Speed limit is up to 60km/h.

PLACE TRAFFIC CONES EVERY 4m FOR USE THIS SCENARIO WHEN:


DELINEATION, WITH AT LEAST 5 BEHIND
THE VEHICLE · On approach to your site, there is at least
100m or 2D sight distance, whichever is
greater.
· You can park legally in a place where other
cars can still go around your vehicle without
FOOTPATH OR UNPAVED PATH needing to cross into the opposing traffic lane.
WHICH PEDESTRIANS MIGHT USE · The speed limit is 60km/h or less and the
work area does not encroach onto a moving
traffic lane (i.e. you can work up to the kerb).
Note:
· When EWP is utilised:
VERGE (GRASS, - Do not elevate the EWP to come within the
CONCRETE, ETC.) legislated exclusion zone. This distance
varies in different states and territories, so you
will need to find out the legal requirement in
your state or territory. (Refer to the State
Code of Practice - Working Near Live Parts).
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
FOR ADVANCE SIGN alone are present and working closer than 3m
PLACEMENT REFER TO (1.2m in SA) to a moving traffic lane.
MINIMUM OF 3m MUST BE NOTE AND TABLE OF
MAINTAINED FOR PASSING · The symbolic worker sign shall be placed at
"VALUE OF 'D' METRES" '2D' from the work area for approach speeds
TRAFFIC AT SPEEDS UP TO 60
KM/H of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.
VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h
· Where possible, the vehicle should be placed
RUN THE CONES TO JUST PAST THE WORK to offer protection from approaching traffic.
AREA FOR SAFETY
(IF ANY OF THESE CONDITIONS
CANNOT BE MET, DO NOT USE THIS
PLAN)

Job Number: ALT211079VIC-DG-0011

(Plan 11 - Sheet 1 of 2)
Prepared By:
FOR ADVANCE SIGN PLACEMENT REFER
TO NOTE AND TABLE OF "VALUE OF 'D'
METRES"

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 11 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0011 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO TWELVE:
· Working at or inspecting infrastructure which is
located on the verge and not blocking the
footpath or roadway.
· Work to be completed in a single shift.
· Speed limit is up to 60km/h (no center line).
FOR ADVANCE SIGN PLACEMENT REFER
TO NOTE AND TABLE OF "VALUE OF 'D'
METRES"
USE THIS SCENARIO WHEN:
VERGE (GRASS, CONCRETE, ETC.)
· On approach to your site, there is at least
100m or 2D sight distance, whichever is
INFRASTRUCTURE BEING greater.
RUN THE CONES TO JUST PAST
INSPECTED/WORKED UPON THE WORK AREA FOR SAFETY · You can park legally in a place where other
cars can still go around your vehicle.
· The speed limit is 60km/h or less and the
POSITION YOUR VEHICLE TO OFFER work area does not encroach onto a moving
PROTECTION TO THE WORK AREA AND traffic lane (i.e. you can work up to the kerb).
ACHIEVE CLEARANCE TO LIVE TRAFFIC Note:

· When EWP is utilised:


- Do not elevate the EWP to come within the
legislated exclusion zone. This distance
varies in different states and territories, so you
PLACE TRAFFIC CONES EVERY 4m FOR will need to find out the legal requirement in
DELINEATION, WITH AT LEAST 5 BEHIND your state or territory. (Refer to the State
THE VEHICLE Code of Practice - Working Near Live Parts).
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
'2D' from the work area for approach speeds
FOOTPATH OR UNPAVED PATH of 60km/hr or more, or 'D' for approach
WHICH PEDESTRIANS MIGHT USE speeds less than 60km/hr, as per the table
below.
VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h
MINIMUM OF 6m MUST BE
MAINTAINED FOR PASSING · Where possible, the vehicle should be placed
TRAFFIC AT SPEEDS UP TO 60 to offer protection from approaching traffic.
KM/H
(IF ANY OF THESE CONDITIONS
CANNOT BE MET, DO NOT USE THIS
PLAN)

Job Number: ALT211079VIC-DG-0012

(Plan 12 - Sheet 1 of 2)
Prepared By:

FOR ADVANCE SIGN PLACEMENT REFER


TO NOTE AND TABLE OF "VALUE OF 'D'
METRES"

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
RIICOM201D Communicate in the workplace. VEHICLE MOUNTED WARNING DEVICE
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan.
TRAFFIC CONES (AT SPACING
RIICOM201D Communicate in the workplace. SPECIFIED IN NOTES) -
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure. 450-500MM HIGH CONES WHERE
RIIWHS302D Implement traffic management plan. TRAFFIC SPEEDS DO NOT EXCEED
70KM/H.
700MM HIGH CONES WHERE TRAFFIC
RIIWHS302D Implement traffic management plan. SPEEDS EXCEED 70 KM/H.
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.
900 x 600 T1-5 SYMBOLIC WORKER
RIIWHS302D Implement traffic management plan. SIGN
TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 12 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT201079VIC-DG-0012 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO THIRTEEN:
· Working at or inspecting infrastructure which is
PEDESTRIANS DETOUR (T8-2)AND USE located on a footpath and requires full footpath
OTHER FOOTPATH (T8-3) SIGNS SHALL closure.
BE POSITIONED AT BOTH ENDS · Work to be completed in a single shift.
· Speed limit is up to 50km/h.
FOOTPATH OR UNPAVED PATH
WHICH PEDESTRIANS MIGHT USE

USE THIS SCENARIO WHEN:


· On approach to your site, there is at least
100m or 2D sight distance, whichever is
INFRASTRUCTURE BEING INSPECTED WITH
greater.
APPROPRIATE GUARDING/BARRICADING USED · The speed limit is 50km/h or less and the
work area does not encroach onto a moving
PEDESTRIANS DETOUR (T8-2) AND USE traffic lane.
OTHER FOOTPATH (T8-3) SIGNS SHALL
BE POSITIONED AT BOTH ENDS VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h

US
E
FO OTHE
OT
PA R
TH
PE D
ES
TR
IAN
S

VERGE (GRASS,
CONCRETE, ETC.)

PEDESTRIAN (IF ANY OF THESE CONDITIONS


DETOUR PATH
CANNOT BE MET, DO NOT USE THIS
PLAN)
PEDESTRIAN DETOUR SHALL BE INSTALLED AT A
LOCATION WHERE THEY CAN BE CROSSED SAFELY. Job Number: ALT211079VIC-DG-0013
IF THE CROSSING IS NOT SAFE FOR PEDESTRIANS,
TRAFFIC CONTROLLERS MAY BE REQUIRED TO (Plan 13 - Sheet 1 of 2)
ASSIST PEDESTRIANS FOR CROSSING THE ROAD. Prepared By:

THINGS TO LOOK FOR IN A LOCATION INCLUDE


PRAM RAMPS, GOOD SIGHT DISTANCE, AND
EXISTING CROSSING POINTS. IF A SAFE CROSSING
POINT CAN BE LOCATED NEARBY BUT NO RAMPS
ARE PRESENT, CONSIDER INSTALLING TEMPORARY
RAMPS AS PER MANUFACTURERS
RECOMMENDATIONS, SIMILAR TO THE EXAMPLE
SHOWN HERE. (03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
VEHICLE MOUNTED WARNING DEVICE
RIICOM201D Communicate in the workplace.
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. PED
ES
TR
IAN
S
1200 x 300 mm T8-2 PEDESTRIANS
RIICOM201D Communicate in the workplace. (ARROW) SIGN (1x Left and 1x Right)
New South Wales Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. US
E
FO OTHE
OT
PA R
TH 900 x 600 mm T8-3 USE OTHER
RIIWHS302D Implement traffic management plan. FOOTPATH SIGN
Northern Territory Project Compliance Requirements RIIWHS205D Control traffic with Stop-Slow bat.

RIIWHS302D Implement traffic management plan. MANHOLE GUARD/COVER


TMR eLearning Programs:
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 13 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0013 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO FOURTEEN:
· Working at or inspecting infrastructure which is
located on the verge and requires full footpath
closure.
AREA WHERE PEDESTRIANS ARE TO BE DETOURED SHALL BE OF A · Vehicle parked on the verge.
SIMILAR QUALITY AND TYPE AS THE EXISTING IF POSSIBLE. AS A
· Work to be completed in a single shift.
GUIDE THE TEMPORARY PATH SHOULD BE:
· Speed limit is up to 80km/h.
· AT LEAST 1.2m WIDE (2.0m WIDE IF IT IS A SHARED PATH)
· A FIRM SURFACE (FOR WHEELCHAIRS AND PRAMS)
· FREE OF WORK EQUIPMENT AND MATERIALS
USE THIS SCENARIO WHEN:
· On approach to your site, there is at least
100m or 2D sight distance, whichever is
PEDESTRIANS DETOUR (T8-2) SIGNS SHALL BE greater, for approaching vehicles in every
POSITIONED AT BOTH ENDS OF THE WORK AREA OR direction or able to see the end of the road.
PROPERLY MOUNTED TO THE WORK BARRIER · The speed limit is 80km/h or less and the
clearance to edge of traffic lane is at least
1.2m.
· The speed limit is 60km/h or less and the
work area does not encroach onto a moving
traffic lane (i.e. you can work up to the kerb).
· Pedestrians can still move around the work
area.
Note:
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
FOOTPATH OR UNPAVED PATH alone are present and working closer than 3m
WHICH PEDESTRIANS MIGHT USE (1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
PED
ES
TR
IAN
S
'2D' from the work area for approach speeds
of 60km/hr or more, or 'D' for approach
speeds less than 60km/hr, as per the table
below.

FOR ADVANCE SIGN VALUE OF 'D' METRES


PLACEMENT REFER TRAFFIC SPEED 'D' VALUE
TO NOTE AND 50km/h or LESS 15m
TABLE OF "VALUE 60km/h 45m
CLEARANCE TO EDGE OF TRAFFIC OF 'D' METRES" 70km/h OR GREATER
EQUAL TO SPEED
LANE AT LEAST 1.2M FOR SPEEDS OF TRAFFIC IN km/h
ABOVE 60KM/H & UP TO 80 KM/H
· Where possible, the vehicle should be placed
to offer protection from approaching traffic.
RUN THE CONES TO JUST PAST
THE WORK AREA FOR SAFETY

WORK AREA TO BE CONTAINED USING TAPE, (IF ANY OF THESE CONDITIONS CANNOT BE
PEDESTRIAN MESH OR SIMILAR IF AN MET, DO NOT USE THIS PLAN)
EXCAVATION OF UP TO 500mm DEEP IS
REQUIRED Job Number: ALT211079VIC-DG-0014
FOR ADVANCE SIGN (Plan 14 - Sheet 1 of 2)
PLACEMENT REFER
TO NOTE AND Prepared By:

TABLE OF "VALUE VERGE (GRASS, CONCRETE, ETC.)


OF 'D' METRES"

(03) 9248 4224

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
VEHICLE MOUNTED WARNING DEVICE
RIICOM201D Communicate in the workplace.
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. TRAFFIC CONES (AT SPACING
SPECIFIED IN NOTES) -
RIICOM201D Communicate in the workplace. 450-500MM HIGH CONES WHERE
Project Compliance Requirements TRAFFIC SPEEDS DO NOT EXCEED
New South Wales RIIWHS201D Work safely and follow WHS policies and procedure. 70KM/H.
RIIWHS302D Implement traffic management plan. 700MM HIGH CONES WHERE TRAFFIC
PED
SPEEDS EXCEED 70 KM/H.
ES
TR
RIIWHS302D Implement traffic management plan. IAN
S
Northern Territory Project Compliance Requirements 1200 x 300 mm T8-2 PEDESTRIANS
RIIWHS205D Control traffic with Stop-Slow bat. (ARROW) SIGN (1x Left and 1x Right)

RIIWHS302D Implement traffic management plan.


TMR eLearning Programs:
Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1 PEDESTRIAN CONTAINMENT AND
Queensland GUIDANCE EQUIPMENT
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods
900 x 600 T1-5 SYMBOLIC WORKER
South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan. SIGN
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 14 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0014 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SCENARIO FIFTEEN:
· Working at or inspecting infrastructure which is
located on the verge and requires full footpath
AREA WHERE PEDESTRIANS ARE TO BE DETOURED SHALL BE OF A closure.
SIMILAR QUALITY AND TYPE AS THE EXISTING IF POSSIBLE. AS A · Vehicle parked on the verge.
GUIDE THE TEMPORARY PATH SHOULD BE: PEDESTRIANS DETOUR (T8-2) SIGNS SHALL BE · Work to be completed in a single shift.
POSITIONED AT BOTH ENDS OF THE WORK AREA OR · Speed limit is up to 80km/h.
· AT LEAST 1.2m WIDE (2.0m WIDE IF IT IS A SHARED PATH) PROPERLY MOUNTED TO THE WORK BARRIER
· A FIRM SURFACE (FOR WHEELCHAIRS AND PRAMS)
USE THIS SCENARIO WHEN:
· FREE OF WORK EQUIPMENT AND MATERIALS VERGE (GRASS, CONCRETE, ETC.)
· MORE THAN 1.2m FROM TRAFFIC AT SPEEDS UP TO 60km/h AND · On approach to your site, there is at least
MORE THAN 3.0m FROM TRAFFIC AT SPEEDS OF 70-80km/h 100m or 2D sight distance, whichever is
greater, for approaching vehicles in every
direction or able to see the end of the road.
· The speed limit is 80km/h or less and the
clearance to edge of traffic lane is at least
1.2m.
· The speed limit is 60km/h or less and the
work area does not encroach onto a moving
traffic lane (i.e. you can work up to the kerb).
· Pedestrians can still move around the work
area.
PED
ES
TRIA
NS
Note:
FOOTPATH OR UNPAVED PATH
· A symbolic worker sign shall be displayed
WHICH PEDESTRIANS MIGHT USE when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
FOR ADVANCE SIGN '2D' from the work area for approach speeds
PLACEMENT REFER of 60km/hr or more, or 'D' for approach
TO NOTE AND TABLE speeds less than 60km/hr, as per the table
OF "VALUE OF 'D' below.
METRES"
VALUE OF 'D' METRES
TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
RUN THE CONES TO JUST PAST
60km/h 45m
THE WORK AREA FOR SAFETY
EQUAL TO SPEED
70km/h OR GREATER
CLEARANCE TO EDGE OF OF TRAFFIC IN km/h
TRAFFIC LANE AT LEAST 1.2M INFRASTRUCTURE BEING INSPECTED
FOR SPEEDS ABOVE 60KM/H & · Where possible, the vehicle should be placed
WITH APPROPRIATE FENCING USED to offer protection from approaching traffic.
UP TO 80 KM/H

WORK AREA TO BE CONTAINED USING TAPE,


PEDESTRIAN MESH OR SIMILAR IF AN
FOR ADVANCE SIGN EXCAVATION OF UP TO 500mm DEEP IS
(IF ANY OF THESE CONDITIONS
PLACEMENT REFER REQUIRED CANNOT BE MET, DO NOT USE THIS
TO NOTE AND TABLE PLAN)
OF "VALUE OF 'D'
METRES"
Job Number: ALT211079VIC-DG-0015
PLACE TRAFFIC CONES EVERY 4m, WITH AT LEAST 5
BEFORE THE WORK AREA (Plan 15 - Sheet 1 of 2)
Prepared By:

(03) 9248 4224


CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
VEHICLE MOUNTED WARNING DEVICE
RIICOM201D Communicate in the workplace.
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. TRAFFIC CONES (AT SPACING
SPECIFIED IN NOTES) -
RIICOM201D Communicate in the workplace. 450-500MM HIGH CONES WHERE
Project Compliance Requirements TRAFFIC SPEEDS DO NOT EXCEED
New South Wales RIIWHS201D Work safely and follow WHS policies and procedure. 70KM/H.
RIIWHS302D Implement traffic management plan. 700MM HIGH CONES WHERE TRAFFIC
PED
SPEEDS EXCEED 70 KM/H.
ES
TR
RIIWHS302D Implement traffic management plan. IAN
S
Northern Territory Project Compliance Requirements 1200 x 300 mm T8-2 PEDESTRIANS
RIIWHS205D Control traffic with Stop-Slow bat. (ARROW) SIGN (1x Left and 1x Right)

RIIWHS302D Implement traffic management plan.


TMR eLearning Programs:
Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1 PEDESTRIAN CONTAINMENT AND
Queensland GUIDANCE EQUIPMENT
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods
900 x 600 T1-5 SYMBOLIC WORKER
South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan. SIGN
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.


MANHOLE GUARD/COVER
Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 15 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0015 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
FOOTPATH OR UNPAVED PATH SCENARIO SIXTEEN:
WHICH PEDESTRIANS MIGHT USE · Working at or inspecting infrastructure which is
AREA WHERE PEDESTRIANS ARE TO BE DETOURED SHALL BE OF A PEDESTRIANS DETOUR (T8-2) SIGNS SHALL located on the verge at a cross-intersection
SIMILAR QUALITY AND TYPE AS THE EXISTING IF POSSIBLE. AS A BE POSITIONED AT BOTH ENDS OF THE and requires full footpath closure.
GUIDE THE TEMPORARY PATH SHOULD BE: RUN THE CONES TO
WORK AREA OR PROPERLY MOUNTED TO JUST PAST THE WORK · Work to be completed in a single shift.
· AT LEAST 1.2m WIDE (2.0m WIDE IF IT IS A SHARED PATH) THE WORK BARRIER AREA FOR SAFETY · Speed limit is up to 60km/h.
· A FIRM SURFACE (FOR WHEELCHAIRS AND PRAMS)
· FREE OF WORK EQUIPMENT AND MATERIALS
· MORE THAN 1.2m FROM TRAFFIC AT SPEEDS UP TO 60km/h USE THIS SCENARIO WHEN:
· On approach to your site, there is at least
100m or 2D sight distance, whichever is
greater, for approaching vehicles in every
direction or able to see the end of the road.
SYMBOLIC WORKER SIGN MINIMUM OF 3m · The speed limit is 60km/h or less and the
TO BE PLACED 'D' m PRIOR MUST BE work area does not encroach onto a moving
TO THE INTERSECTION MAINTAINED FOR traffic lane (i.e. you can work up to the kerb).
PASSING TRAFFIC · You can park legally in a place where other
AT SPEEDS UP TO
60 KM/H cars can still go around your vehicle.
· Pedestrians can still move around the work
area.
Note:
PE
DES
TR
· When EWP is utilised:
IANS
- Do not elevate the EWP to come within the
legislated exclusion zone. This distance
varies in different states and territories, so you
will need to find out the legal requirement in
your state or territory. (Refer to the State
Code of Practice - Working Near Live Parts).
· A symbolic worker sign shall be displayed
when either workers on foot or plant items
alone are present and working closer than 3m
(1.2m in SA) to a moving traffic lane.
· The symbolic worker sign shall be placed at
'2D' from the work area for approach speeds
FOR ADVANCE SIGN of 60km/hr or more, or 'D' for approach
PLACEMENT REFER TO NOTE speeds less than 60km/hr, as per the table
AND TABLE OF "VALUE OF 'D' below.
WORK AREA TO BE CONTAINED METRES"
USING TAPE, PEDESTRIAN MESH OR VALUE OF 'D' METRES
SIMILAR TRAFFIC SPEED 'D' VALUE
50km/h or LESS 15m
60km/h 45m
EQUAL TO SPEED
70km/h OR GREATER
OF TRAFFIC IN km/h
VERGE (GRASS,
CONCRETE, ETC.) · Where possible, the vehicle should be placed
to offer protection from approaching traffic.
(IF ANY OF THESE CONDITIONS CANNOT BE
MET, DO NOT USE THIS PLAN)

Job Number: ALT211079VIC-DG-0016

(Plan 16 - Sheet 1 of 2)
Prepared By:

PLACE TRAFFIC CONES EVERY 4m, WITH AT LEAST 5


BEFORE THE WORK AREA

FOR ADVANCE SIGN PLACEMENT REFER


TO NOTE AND TABLE OF "VALUE OF 'D' SYMBOLIC WORKER SIGN
METRES" TO BE PLACED 'D' m PRIOR
TO THE INTERSECTION (03) 9248 4224
CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021
SERVICE STREAM SHORT-TERM LOW IMPACT SCENARIO CARDS
THIS SET OF PLANS HAS BEEN DESIGNED TO COMPLY WITH SECTION 4.4.4 OF AS1742.3-2009 (SHORT TERM LOW IMPACT WORKS-BUILT-UP AREA) AND ATTEMPT TO MEET THE
REQUIREMENTS OF THE RELEVANT STATE TRAFFIC MANAGEMENT CODES.

ALL TRAFFIC MANAGEMENT ACTIVITIES MUST BE IMPLEMENTED INSIDE THE SPECIFIC ROAD RULES AND STATE TRAFFIC MANAGEMENT CODES WHICH THE WORK IS BEING
CARRIED OUT AND WITHIN THE QUALIFIED OPERATOR'S SCOPE OF TRAINING (E.G. DIFFERENCES IN SYMBOLIC WORKER SIGNS IN NSW, ETC.).

SINCE THIS SETUP COULD BE SEEN AS A PARTIAL RELAXATION OF SAFETY STANDARDS, IT IS VITAL THAT A RISK ASSESSMENT BE MADE OF THE PROPOSED ADOPTION OF Prepared By:
THESE TREATMENTS IN PARTICULAR ENVIRONMENTS TAKING PARTICULAR ACCOUNT OF FACTORS SUCH AS TRAFFIC VOLUME AND SPEED, ROAD GEOMETRY AND WIDTH, AND
GENERAL BEHAVIOUR OF ROAD USERS. IF THEY CANNOT BE TOLERATED, A FULLY PROTECTED STATIC WORK SITE OR MOBILE WORKS CONVOY WILL BE REQUIRED.

PLEASE NOTE THAT IN VICTORIA TEMPORARY SPEED LIMIT SHOULD BE CONSIDERED FOR WORKS WITHIN 3M OF TRAFFIC LANE UNLESS WORKSITE HAZARD ASSESSMENT
INDICATES OTHERWISE, IN THAT CASE ENGAGE A QUALIFIED TRAFFIC MANAGEMENT COMPANY.

YOU CAN WORK ON THIS SITE IF YOU ARE WEARING APPROPRIATE CLOTHING INCLUDING A HIGH VISIBILITY VEST, AND ANY OTHER SAFETY EQUIPMENT IDENTIFIED AS BEING
REQUIRED.

THE MINIMUM TRAINING REQUIREMENTS FOR ALL PERSONNEL WHO IMPLEMENT ANY TRAFFIC MANAGEMENT PLAN HAS BEEN LISTED IN THE TABLE BELOW AND COURSE
NAMES/NUMBERS ARE CURRENT AT THE TIME OF DOCUMENT ISSUE.

FOR WORK UNDERTAKEN IN QLD, PLEASE REFER TO THE RISK ASSESSMENT PROVIDED WITH THIS SET OF PLANS REGARDING THE USE OF DELINEATING DEVICES.

TRAINING KEY:

STATE MINIMUM REQUIRED FOR ALL PERSONNEL ONSITE MINIMUM REQUIRED FOR PERSON IMPLEMENTING PLAN SIGNS AND EQUIPMENT:
VEHICLE MOUNTED WARNING DEVICE
RIICOM201D Communicate in the workplace.
Australian Capital Territory Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. TRAFFIC CONES (AT SPACING
SPECIFIED IN NOTES) -
RIICOM201D Communicate in the workplace. 450-500MM HIGH CONES WHERE
Project Compliance Requirements TRAFFIC SPEEDS DO NOT EXCEED
New South Wales RIIWHS201D Work safely and follow WHS policies and procedure. 70KM/H.
RIIWHS302D Implement traffic management plan. 700MM HIGH CONES WHERE TRAFFIC
PED
SPEEDS EXCEED 70 KM/H.
ES
TR
RIIWHS302D Implement traffic management plan. IAN
S
Northern Territory Project Compliance Requirements 1200 x 300 mm T8-2 PEDESTRIANS
RIIWHS205D Control traffic with Stop-Slow bat. (ARROW) SIGN (1x Left and 1x Right)

RIIWHS302D Implement traffic management plan.


TMR eLearning Programs: PEDESTRIAN CONTAINMENT AND
Queensland Project Compliance Requirements · Working in Proximity to Traffic - Awareness Part 1 GUIDANCE EQUIPMENT
· Working in Proximity to Traffic - Awareness Part 2 Works
Protection Methods

South Australia Project Compliance Requirements RIIWHS302D Implement traffic management plan.
RIIWHS205D Control traffic with Stop-Slow bat.

Tasmania Project Compliance Requirements RIIWHS302D Implement traffic management plan.

Victoria Project Compliance Requirements RIIWHS302D Implement traffic management plan.

RIICOM201D Communicate in the workplace.


Western Australia Project Compliance Requirements RIIWHS201D Work safely and follow WHS policies and procedure.
RIIWHS302D Implement traffic management plan. (Plan 16 - Sheet 2 of 2)

Date Revision Description of change Organisation Drawing Number Sheet Number

12/05/21 0 Issued for Information Altus Traffic ALT211079VIC-DG-0016 Sheet 2 of 2

Author Reviewer (VIC/NSW/TAS) Reviewer (SA) Reviewer (QLD) Reviewer (WA) Review Date
Tony Togany Negin Vaez Jay Byrne Daniel McEwan Lara Lambrucchi 12/05/22

NSW Card # 0051756319 173-510 AWTM 17-1573-01

CCD-C-PLN-0261 | Generic Short-Term Low-Impact Traffic Guidance Scenario Plans | Rev 4 | 12/05/2021

You might also like