Country GERMANY

Document/Ref SWITCHING SCHEDULE / PROCEDURE

MV 1 20KV INITIAL POWER ENERGISATION


UTILITIES/SYNA-MV1 INCOMER

AMAZON FRA134 FRANKFURT PHASE 1


CONSTRUCTION/COMMISSIONING
CRITICAL PATH EQUIPMENT

 UA RA MORFELDON B SWITCHROOM DISTRIBUTION SYNA 21KV FEEDER CUBICAL J2Q13


 MV1 SWGR 20KV CUBICAL INCOMER MV-1Q1 +AO1
 MV1 SWGR 20KV CUBICAL FEEDER MV-1Q1 +AO4
 TEMPORARY 20KV LOAD BANK SYSTEM
FEEDER
CUBICAL RING
MAIN 1 M2
CUBICAL J2Q13

FEEDER MV-1Q1
+A04

INCOMER
MV1 -1Q1 +A01

LOAD
BANK
440v 4MW
LOAD BANK
TEMP 20KV /440
XFMR
LOAD
BANK
440 4MW

DB 21/03/24 PRIMARY
SIGN Walk of system and all associated appartus to take place prior to commencment of switching to verify as follows
TIME +A12:C53A12:C63C12A12:C61A12:C62A12:C61A12:C59A12:C58A12:C57A12:C55A12:C53A12:C51A12:C50A12:C49A12:C48A12:CA12:C47
Confirm that approved request for energisation is in place
Confirm that approved request for isolation is in place
Confirm that energisation time and date has been agreed and that all necessary parties are aware
Confirm that isolation time and date has been agreed and that all necessary parties are aware
Confirm that a declaration of fitness has been received
Confirm that QAQC documents are approved and signed off
Confirm that equipment has completed L2 Cx.
Confirm that torqueing records are to hand
Confirm that pre-energisation test results are to hand
Confirm that VLF/ Hi-Pot test record sheets are to hand
Equipment owner to confirm that the approved protection settings have been applied to preotection relays
Expected configuration of equipment:
Confirm equipment/ system being energised is clear of personnel and safe to energise
Confirm fire extinguisher is to hand
Confirm equipment/ system being isolated is clear of personnel and safe to energise
Confirm that all warning and safety signage has been posted
Confirm that relevant test equipment is to hand
Confirm all necessary safety PPE is to hand
Confirm that all outgoing circuits have LOTO applied to prevent uncontrolled energisations
Confirm that communication equipment is at hand
Confirm that all necessary parties are available to witness energisation
Confirm that all necessary parties are available to witness isolation
Confirm that this switching plan is approved for use
Confirm system boundaries are attached
Equipment owner to confirm that tap changer settings are correct
Confirm equipment is in good condition and safe to energise
Confirm area being energised has been walked and is ready to energise
Confirm area being energised is secure
Confirm permit system is implemented for energised area and equipment
Confirm that there are no unexpected alarms on systems being worked on
Confirm remote switching is available
Confirm support generator available as required
Confirm cable routes are completed with signage posted
Confirm cabling has sufficient mechanical protection when passing through areas under construction

DB 21/03/24 PRIMARY
Table 1 ARC Flash requirements
Scenario 20kv Utility feed only
Max Cal/Cm^2 52.89
PPE cat 5

ITEM LOCATI APPARATUS OPERATION / RESULT SIGN


ON EQUIPEMENT
1) CONFIRM VCB MV-1Q1 +A06 FEEDER TO RMU 1.1C CB1 IS RACKED
LEVEL 0 MV-1Q1 +A06 OUT IN TEST POSITION AND CIRCUIT EARTH SWITCH IS
MV1 FEEDER TO RMU APPLIED.WITH LOCK NO….4….
SWITCH 1.1C-CB1
CONFIRM MECH FLAG VISIBLE AT VCB WINDOW. AND CASTELL
ROOM KEY 1Q1FB4 IS FIRMLY IN POSITION ON VCB.
M.00.85 ON FLORES HMI CONFIRM INPUT 304 IS INDICATING EARTH
SWITCH CLOSED.

2) LEVEL 0 CONFIRM VCB MV-1Q1 +A05 FEEDER TO RMU 2.1C CB1 IS RACKED
MV1 MV-1Q1 +A05 OUT IN TEST POSITION AND CIRCUIT EARTH SWITCH IS APPLIED
SWITCH FEEDER TO RMU WITH LOCK NO….3….
2.1C-CB1
ROOM CONFIRM MECH FLAG IS VISIBLE AT VCB WINDOW. AND
M.00.85 CASTELL KEY 1Q1FB3 IS FIRMLY IN POSITION ON VCB ON
FLORES HMI CONFIRM INPUT 304 IS INDICATING EARTH SWITCH
CLOSED.
LEVEL 0 MV-1Q1 +A04
3) MV1 FEEDER TO RMU CONFIRM VCB MV-1Q1 +A04 FEEDER TO RMU 1.2B CB1 IS RACKED
SWITCH 1.2B-CB1 OUT IN TEST POSITION AND CIRCUIT EARTH SWITCH IS APPLIED
ROOM WITH LOCK NO….2….
M.00.85 CONFIRM MECH FLAG IS VISIBLE AT VCB WINDOW. AND
CASTELL KEY 1Q1FB2 IS FIRMLY IN POSITION ON VCB.ON
FLORES HMI CONFIRM HMI INPUT 304 IS INDICATING EARTH
SWITCH CLOSED.
NOTE THIS IS TEMPORARY FEEDER TO 20KV LOAD
BANK STRING

DB 21/03/24 PRIMARY
4)
CONFIRM VCB MV-1Q1 +A03 FEEDER TO RMU 2.2B CB1 IS RACKED
LEVEL 0 OUT IN TEST POSITION AND CIRCUIT EARTH SWITCH IS
MV1 MV-1Q1 +A03 APPLIEDWITH LOCK NO….1….
SWITCH FEEDER TO RMU
CONFIRM MECH FLAG IS VISIBLE AT VCB WINDOW.AND CASTELL
2.2B-CB1
ROOM KEY 1Q1FB1 IS FIRMLY IN POSITION ON VCB. ON FLORES HMI
M.00.85 CONFIRM HMI INPUT 304 IS INDICATING EARTH SWITCH CLOSED.

LEVEL 0 CONFIRM ON MV-1Q1+A02 MECH FLAG BUS BAR EARTHED IS


5) MV1 MV-1Q1 +A02 OPEN.
SWITCH METERING PANEL WITNESS CASTELL KEY 1Q1BBE IS REMOVED AND LOCATED
ROOM IN CASCADE CASTELL BOX.
M.00.85
LEVEL 0
6) MV1 MV-1Q1 +A02 REMOVE LOTO KEY….16 ….
SWITCH METERING PANEL
PROCEED TO RACK INTO SERVICE POSITION.
ROOM CONFIRM METERING VOLTAGE XFMR ARE IN SERVICE POSITION
M.00.85 RACKED IN ON TULIPS TO OPEN SHUTTERS AND ON BARS

7)
LEVEL 0 CONFIRM VCB MV-1Q1 +A01 INCOMER SUPPLY IS RACKED OUT IN
MV1 MV-1Q1 +A01 TEST POSITION. AND CIRCUIT EARTH SWITCH IS APPLIED WITH
SWITCH INCOMER A LOCK NO….15….
ROOM CONFIRM MECH FLAG IS VISIBLE AT VCB WINDOW.
M.00.85 AND CASTELL KEY 1Q1ES0 IS FIRMLY IN POSITION ON VCB.
ON FLORES HMI CONFIRM HMI INPUT 304 IS SEEING EARTH
SWITCH CLOSED. BOTH MV1 AND UTIITLITIES SUB STATION B
SHOULD BE VERIFIED INDICATION CLOSED PRESENT AT BOTH
LOCATIONS.

8)
LEVEL 0 MV-1Q1 +A01 CONFIRM CONTROL VT. S ARE RACKED OUT AND IN TEST
MV1 INCOMER A POSITION.
SWITCH PROCEED TO RACK CONTROL VT. S INTO SERVICE POSITION ON
PRIMARY SIDE VCB INCOMER ANCILLIARY SERVICE SPOUTS
ROOM
M.00.85

9) SYNA COLABIRATION IS NOW REQUIRED.


LEVEL 0 DEISOLATE AND REMOVE LOCK NO ….15….
MV1 MV-1Q1 +A01
CONFIRMATION AND WITNESS OF THE OPENENING OF EARTH
SWITCH INCOMER A
SWITCH ON VCB MV-1Q1 +A01.
ROOM CROSS CHECK SIGNATURES WILL BE REQUIRED.
M.00.85 COUNTER SIGN AND CONFIRM CIRCUIT EARTH SWITCH HAS
BEEN OPENED. A PREVENTION RECLOSE LOTO SHALL NOW BE
APPLIED TO THE EARTH SWITCH LOCK OUT.
CONFIRM AT VCB CUBICLE MECH OPEN FLAG IS VISIBLE.
VERIFY AT FLORES HMI STATION INPUT 304 IS INDICATING OPEN
STATUS.
VERIFY AT SYNA SUB STATION B CUBICLE J2Q13 SEL 751 IS
INDICATING OPEN EARTH SWITCH STATUS.

MERC SIGN………………………………………………

SYNA SIGN……………………………………………….

DB 21/03/24 PRIMARY
10) LEVEL 0 CONFIRM IN COLLABORATION WITH SYNA.
MV1 MV-1Q1 +A01 ALARMS OR LOCKOUT ARE NOT PRESENT ON INCOMER
SWITCH INCOMER A CUBICLES IN MV 1 A01 AND FEEDER CUBICLE SUBSTATION B
J2Q13 RING MAIN FEEDER.
ROOM
M.00.85
MERC SIGN………………………………………………

SYNA SIGN……………………………………………….
LEVEL 0
11) MV1 LEVEL 0 PROCEED TO CLEAR MV1 SWITCHROOM AND LOCK ALL DOORS.
SWITCH MV1 SWITCHROOM SAFETY BARRIERS ARE TO BE ADORNED BOTH ENTRANCES.
M.00.85 AND PERSONNEL TO BE PRESENT TO PREVENT UNAUTHORISED
ROOM ENTRY.
M.00.85

12) SUB-STATION B SYNA NOW TO COMMENCE IN COLLABORATION WITH MERCURY


SUB SYNA THE CLOSURE AND SUPPLY OF 20KV TO INCOMER MV1 CUBICLE
STATION B CUBICAL J2Q13 A01.
RING MAIN FEEDER THIS WILL BE COMMUNICATED WITH A REVERSE COUNTDOWN
VIA RADIO COMUNICATION SO ALL PARTIES ARE FULLY AWARE
AT THE POINT OF VCB CLOSURE.

13) ONCE CLOSURE OF 20KV FROM SUB STATION B CUBICLE J2Q13


LEVEL 0 HAS BEEN CONFIRMED ON FLORES PANEL.
MV1 MV-1Q1 +A01 CONFIRM VOLTAGE PRESENT ON CRT INCOMER IS AVALIBLE
SWITCH INCOMER A AND WITHIN DESIGN TOLERANCE WITHIN
UNDER AND OVER VOLTAGE PROTECTION SETTINGS.
ROOM CONFIRM NO ALARMS OR LOCKOUT PRESENT RECORD KV
M.00.85 AT VDI PERFORM A PHASE ROTATION TESTAT TEST PORTS .

Metering
DEVICE L1 L2 L3
HMI
PQM
VDI

VOLTAGE DETECTOR INDICATION CW CCW


PHASE ROTATION
LEVEL 0
14) MV1 MV-1Q1 +A01 SAP AND BUDDY PERSONEL WILL NOW PROCEED TO ADORN FULL
SWITCH INCOMER A CAT RATED ARC FLASH SUIT AND ENTER MV1 SWITCHROOM.
ROOM
M.00.85

15) LEVEL 0 MV-1Q1 +A01 AT INCOMER MV-1Q1 +A01 PROCEED TO RACK INCOMER VCB TO
MV1 INCOMER A SERVICE POSITION
SWITCH ON CIRCUIT AND BUS BAR
CONFIRM ON SEL 751 REMOTE OPERATION IS INDICATED AS
ROOM AVALIBLE AND ILUMINATED.
M.00.85 CONFIRM NO ALARMS OR LOCKOUTS ARE PRESENT.

MV-1Q1 +A01
16) LEVEL 0 INCOMER A SAP AND BUDDY TO CLEAR THE ROOM
MV1 CONFIRM DOORS RELOCKED AND BARRIERS AND NO ENTRY
SWITCH PERSONNEL ARE PRESENT.
ROOM
M.00.85

DB 21/03/24 PRIMARY
LOCATED AT MV1 CONTROL ROOM AT FLORES PANEL.
17) LEVEL 0 MV-1Q1 +A01 IN COLABRATION WITH ALL PERSONELL.
MV1 INCOMER A CONFIRM NO ALARMS OR LOCKOUTS ON FLORES PANEL ARE
SWITCH PRESENT.
PROCEED TO INITIATE CLOSURE ON HMI OF VCB INCOMER
ROOM MV-1Q1 +A01.
M.00.85 THE VCB SHOULD NOW BE CONFIRMED AS CLOSED ON HMI AND
BUS BAR LIVE.
CROSS CHECK SEL 751 FOR ALARMS OR UNEXPECTED
INDICATIONS.
CONFIRM AT VCB CONTROL SECTION CLOSED ILUMINATION.
AND MECH FLAG CLOSED INDICATOR ARE VISIBLE.
AT CUBICLE MV-1Q1+A04 CONFIRM VCB REMAINS IN TEST
18) LEVEL 0 MV-1Q1 +A04 POSITION.
MV1 FEEDER CONFIRM EARTH SWITCH STILL APPLIED WITH LOCK NO…2…
SWITCH (TEMPORARILY
UTILISED FOR PROCEED TO WITH STT AND DEISOLATE LOCK….2……
ROOM LOAD BANK DISENGAGE FEEDER CIRCUIT EARTH SWITCH TO THE OPEN
M.00.85 STRING) POSITION.
CONFIRM MECH FLAG INDICATES OPEN.
AT FLORES HMI INPUT 304 IS INDICATING CORRECT AS EARTH
SWITCH OPEN.

19)
LEVEL 0 MV-1Q1 +A04
MV1 FEEDER SAP AND BUDDY PERSONEL TO PROCEED TO ADORN FULL CAT
SWITCH (TEMPORARILY RATED ARC FLASH SUIT AND ENTER MV1 SWITCHROOM
UTILISED FOR
ROOM LOAD BANK
M.00.85 STRING)

20)
MV-1Q1 +A04 AT MV-1Q1+A04 SAP AND BUDDY PERSONNEL PROCEED TO RACK
LEVEL 0 FEEDER VCB A04 TO SERVICE POSITION.
MV1 (TEMPORARILY CONFIRM ON VCB CONTROL SEL 751 IS INDICATION VCB IN
SWITCH UTILISED FOR SERVICE.
LOAD BANK CONFIRM ON SEL 751 REMOTE CONTROL IS INDICATED.
ROOM STRING) AT FLORES HMI CONFIRM SERVICE POSITION IS INDICATED AND
M.00.85 VISIBLE.

21) LEVEL 0 EXTERNAL


MV1 WALKDOWN PERSONNEL ARE TO COMPLETE AN EXTERNAL LOAD BANK
SWITCH PRE-LOAD BANK STRING WALKDOWN PRE CLOSURE CHECK OF MV-1Q1+A04
ENERGISATION
ROOM CHECKS
M.00.85

22) AT LOAD BANK START AUX GEN POWER.


AT MDU SWITCH MCCB POWER TO LOAD BANKS.
LOAD LOAD BANK AUX ONCE CONFIRMED AUX POWER PRESENT AT CONTROL LOAD
BANK GEN BANK INTERNAL HOUSING.
AREA CLEAR AREA AND RETURN TO MV1 CONTROL ROOM.
STANDBY PERSONNEL SHOULD BE PRESENT AT LOAD BANK
AREA.
THIS IS REQUIRED TO PREVENT UNATHORISED ACCESS.

23) WITH COLABIRATION OF ALL PERSONNEL.


LEVEL 0 CONFIRM NO ALARMS OR LOCKOUTS ARE PRESENT ON FLORES
MV1 MV1 CONTROL HMI.
SWITCH FLORES STATION PROCEED TO INITIATE A CLOSURE OF VCB MV1Q1+A04.
HMI
ROOM TEMPORARY FEEDER FOR 20Kv/440V 8MW LOAD BANK STRING IS

DB 21/03/24 PRIMARY
M.00.85 NOW LIVE.

24) AT FLORES HMI PANEL CONFIRM CLOSURE OF VCB A04 INPUT


HAS BEEN RECEVIED.
LEVEL 0 MV-1Q1 +A04 PROCEED TO CONFIRM CLOSURE ON VCB CONTROL SECTION IS
MV1 FEEDER ILUMINATED.
SWITCH (TEMPORARILY CONFIRM MECH FLAG CLOSED FLAG IS VISIBLE.
UTILISED FOR CONFIRM NO ALARMS HAVE INITIATED.
ROOM LOAD BANK RECORD FEEDER CIRCUIT KV FROM SEL 751
M.00.85 STRING)
L1……………………. L2…………………. L3

25) AT LOAD BANK CONFIRM CORRECT VOLTS FROM SECONDARY


SIDE OF LOAD BANK XFMR.
LOAD LOAD BANK IF PRESENT AND CORRECT PROCEED WITH LOAD SIMULATION.
BANK EQUIPEMENT FOLLOW UTILITYS AND AMAZON REQUIREMENTS STEPS FOR
LAYDOWN LOAD SIMULATION.
AREA RECORD LV VOLTS AT NO LOAD
L1.…………………L2….……………….
L3……………………. N…………………….

DB 21/03/24 PRIMARY
DB 21/03/24 PRIMARY
DB 21/03/24 PRIMARY
DB 21/03/24 PRIMARY
DB 21/03/24 PRIMARY
Person in charge - Procedure / work-scope COMPLETED:

Name………………………………………………………….

Signature …………………………………………………… Date ……………….

Authorised and reviewed by Amazon global commissioning

Name………………………………………………………….
Signature …………………………………………………… Date …………………………………

Please provide any comments, follow up actions, etc.

…………………………………………………………………………………………………………………………

………………………………………………………………………………………………………………………….

…………………………………………………………………………………………………………………………

………………………………………………………………………………………………………………………...

DB 21/03/24 PRIMARY