En Asymmetry As A Basic of Design

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

engineers newsletter providing insights for today’s

hvac system designer

chilled water plants and…


Asymmetry as a Basis of Design
from the editor… require detailed evaluations to selecting unlike chillers—provides an
The Engineers Newsletter regularly determine “the best leaving chilled opportunity to satisfy multiple, often
features articles on chilled water plant water temperature” or “the optimum conflicting, design goals. The “swing-
design. For the most part, these articles cooling-tower flow rate.” Still others, chiller” system (see inset, page 2) is a
examine the “science” of design: they like plant capacity, are quantifications. familiar example of an asymmetrical
offer practical advice for implementing Each solution contributes to the split in plant capacity. In this design, a
control strategies and optimizing success of the final design. large chiller provides daytime cooling
system performance. This issue and a small chiller satisfies evening and
promotes asymmetry as a One aspect of chilled water plant weekend requirements; both chillers
“philosophy” of design. We hope it design that particularly leverages operate together when peak cooling
reminds you to look beyond the “safety efficiency and operating cost is capacity is needed.
of equals” and leads you to creative “partitioning.” Partitioning is deciding
solutions that deliver better how many chillers to use to produce The following example illustrates
performance at a better cost. the design capacity. A plant with a another way to apply asymmetry: by
capacity of 3,000 tons could be unequally dividing hours of operation
comprised of two 1,500-ton chillers, rather than tons of cooling. It relates
asymmetry (ay sim’ i tree), n. Lack of three 1,000-ton chillers, or four 750-ton the core decisions that shaped the final
balance or symmetry. chillers. Even six 500-ton chillers are a design for an actual 3,000-ton chilled
symmetry (sim’ i tree), n. …²A
possible solution. water plant. More importantly, it
relationship of characteristic illustrates how asymmetry affords
correspondence, equivalence, or Notice that all of the cited examples greater design flexibility and can, in
identity among constituents of an divide the total design capacity of the turn, lead to more efficient, cost-
entity or different entities. ³Beauty as plant equally between the chillers. effective systems.
a result of balance or harmonious
arrangement.
Partitioning a plant symmetrically is
common design practice, and it does
from The American Heritage offer a number of advantages: it
Dictionary of the English Language, requires just one chiller selection; it A Case in Point
Third Edition.
simplifies system design, control and The designer began by equally
installation; and it allows any chiller to partitioning the plant’s capacity among
back up any other chiller. While four 750-ton chillers. He did everything
What does symmetry—or the lack of symmetry reduces the complexity of “by the book”; he even used energy
it—have to do with chilled water plant design and installation, it also simulation software to compare the
systems? Consider the complex overlooks opportunities to improve respective life cycle costs of electrically
process that transforms a client’s efficiency, operating costs … even driven and gas-powered chillers.
requirements into a chilled water plant. installed cost. Developing a cooling load profile for the
To arrive at a final design, the design system was paramount to that effort. (It
team must solve many problems. The Selecting identical chillers limits the was also of greater value than
nature or requirements of the ability to optimize more than one estimates of life cycle cost at this stage
application dictate some solutions; for design goal by establishing a single set of the design process.) The system
example, the power source or method of selection criteria. Employing an load profile revealed a peak load of
of heat rejection to use. Other solutions asymmetrical design—in this case, by 3,000 tons and 6.4 million ton-hours of

© 1999 American Standard Inc. All rights reserved Volume 28, No. 4 ■
cooling annually. If the chillers share the
Table 1–An All-Electric Solution
load equally, each 750-ton chiller must
Chiller Characteristics Annual Operation, Per Chiller
produce 1.6 million ton-hours of cooling Average
Designation Capacity Power Run Time Cooling Cooling Cost
annually; see Table 1.
Chillers 1–4 750 tons ea. electricity 2,600 hr 1.6 million ton-hr $0.058/ton-hr

Minimum-billing demand (ratchet)


clauses can dramatically impact utility
costs, as in this case. The local utility specific application.) Dividing the Table 2 summarizes the operating costs
costs of $125 per kilowatt of demand, cooling load equally between all four of these alternatives; the already
annually, and $0.05 per kilowatt-hour of chillers meant an annual, per-chiller negligible difference between them
consumption certainly figured into the operating expense of $38,800 for was even less when the cost of
prerequisites established by the design consumption plus $53,625 for demand, condenser pumps and cooling towers
team. (Note: So-called “blended” or $92,425. Without accounting for the was included. From the standpoint of
electric cost data is not suitable for this cooling tower and pumps, the average energy, there was no clear-cut winner;
type of analysis.) Among these cooling cost was $0.058 per ton-hour. the all-electric-chiller solution was
prerequisites was a minimum neither more nor less affordable than
performance standard of 0.58 kW per The design team also explored the the all-absorption-chiller solution.
ton for electrical chillers. possibility of gas-powered cooling,
hoping to take advantage of existing Asymmetrical Operation. Based on
With that in mind, the team initially steam-producing boilers. For that experience, the design team theorized
considered a 750-ton, centrifugal chiller alternative, the team evaluated a that closer study of the annual load
with full-load performance of 429 kW 750-ton absorption chiller with a COP profile would reveal a “point of
and an NPLV of 0.485 kW. (Defined by of 1.21, which became 0.968 when asymmetry” in the distribution of
ARI Standard 550/590–1998, the NPLV combined with the 80-percent operating hours at various load
rating is a “blended” estimate of efficiency of the boilers. With gas conditions; in other words, significantly
stand-alone chiller performance based consumption budgeted at $0.45 per fewer hours would be logged above a
on weighted averages. Expect therm, each absorption chiller would certain capacity than below it. (See
significant differences between ARI- incur an annual operating cost of Figure 1 and Table 3.) If true, that
rated performance and the actual $89,256 for an average cost of $0.056 distinction would let the team establish
performance of a specific chiller in a per ton-hour. different selection criteria:

■ Chillers selected to operate below


“Swing-Chiller” Design the point of asymmetry would show
This popular design for chilled-water time, it may require different selection an attractive payback for ultra-high
systems is usually achieved by unequally criteria than the “large” chiller which efficiency.
dividing the total plant capacity between seldom experiences loads below
the chillers. In a simple, two-chiller plant, 50 percent. ■ Chillers selected to operate only
for example, the designer may size one when the plant load was above the
chiller to handle about two-thirds of the Analysis software such as System
Analyzer™, TRACE®, or DOE-2 is point of asymmetry would show
plant capacity. Usually, this represents the
load condition at which most hours of invaluable for modeling system and marginal payback for efficiency, but
plant operation will be spent. individual chiller load profiles, and for might still be selected to reduce first
comparing various alternatives based on cost or achieve other design goals.
By base loading the “large” chiller (see energy and economic performance.
schematic at right), the initial premium
paid for high-efficiency performance can The chiller-plant load profile revealed an
be quickly recovered. 900 annual cooling requirement of
“Swing”
Chiller 6,385,000 ton-hours. But what would
The “small” chiller acts as the swing
chiller. It is used when plant demand 600 happen if the chillers were not
exceeds the capacity of the “large,” high- operated equally? For example, there
efficiency chiller. It’s also used in lieu of “Large” Chiller
were 4,740 hours when the cooling
300 (high efficiency) “Swing”
the “large” chiller when cooling demand is Chiller load required the operation of at least
low (e.g., at night and on weekends). Given
the fact that the swing chiller is likely to 0 tons
one chiller. Conversely, only 990 hours
0 hrs 1,000 2,000 3,000 required all four chillers. Starting the
operate at light loads for several hours at a

■ 2 Trane Engineers Newsletter — Vol. 28, No. 4


Chiller 1, they represented more than
Table 2–Comparison of Energy Costs
74 percent of the operating cost for
Local Utility Rate Electric Chillers a Absorption Chillers b
Chiller 4.
Electricity consumption $0.05/kWh $38,800 —
demand $125/kW/yr $53,625 —
The decision to use absorption chillers
Gas $0.045/therm — $89,256 raised two issues: first cost and
Total $92,425 $89,256 performance. In this example,
Cooling cost c $0.058/ton-hr $0.056/ton-hr performance was considered irrelevant
a
Rated full-load performance for the selected centrifugal chiller is 429 kW; part-load performance is 0.485 kW.
because Chiller 3 and Chiller 4 account
b
The selected absorption chiller has a COP of 1.21; when the boiler efficiency (80 percent) is taken into account, its for less than one-third of the plant’s
performance is 0.968.
c
Cooling costs shown here exclude accessories. chilled water production. But the matter
of cost remained. To address that
concern, the designer arranged the
chillers sequentially and without team reduced the cost of operating chillers in series, with the absorption
rotation yielded the run times and Chiller 1 by 30 percent! machines upstream of the centrifugal
production capacities shown below: chillers. The absorption chiller selection
Hybrid Opportunity. What about could then be based on a warmer
Table 3 Chiller 3 and Chiller 4? Chiller 4 is leaving chilled-water temperature, i.e.,
Chiller Run Time Cooling Production required only 990 hours each year, yet 50°F rather than 42°F. This design
1 4,740 hr 2,595,000 ton-hr bears the same demand charge. (Figure 2, page 4) substantially reduced
2 2,850 hr 1,852,000 ton-hr Producing only 652,000 ton-hours, its the cost of the absorption chillers and
3 1,890 hr 1,286,000 ton-hr average cooling cost is $0.131 per ton- greatly improved the COP. In the end, it
4 990 hr 652,000 ton-hr
hour. Chiller 3 “clocks in” at $0.070 per also proved to be an irresistible option.
ton-hour. (NPLV was not used in this But the design team didn’t settle on
While each chiller was subject to the that combination without first
calculation because Chiller 3 and
same demand charge of $53,625, entertaining other ideas for Chiller 3
Chiller 4 operate only at conditions
energy consumption differed radically. and Chiller 4.
when cool condenser water is unlikely.)
Consider Chiller 1. It would consume
$62,856 of electricity to produce A gas-engine-driven generator was
Recall the absorption chiller considered
roughly 2.6 million ton-hours of cooling among the alternatives considered in
earlier? Its average cooling cost of
annually. When the demand charge of lieu of absorption chillers. In that
$0.056 made gas-powered cooling an
$53,625 was taken into account, the scenario, Chiller 3 and Chiller 4 were
excellent candidate for Chiller 3 and
operative cost of cooling for Chiller 1 electric centrifugal chillers, but each
Chiller 4. (See Table 4, page 4.) Why?
was $0.045 per ton-hour. chiller received power from a gas-
While demand charges were only
47 percent of the cost of operating engine-driven generator during on-peak
By virtue of substantial hours of
operation, Chiller 1—and Chiller 2, for
that matter—proved to be excellent
Figure 1–Annual Load Profile
candidates for reselection at a higher
efficiency. (The cost-add for better 3,000

performance can be justified with lower


2,280 hours
energy costs.) The new selection was a (27.5%)
2,250
750-ton, centrifugal chiller with full-load
performance of 383 kW and an NPLV of
0.412 kW per ton. An energy analysis Cooling
Capacity, 1,500
confirmed that the price tag to reduce Tons Point of Asymmetry
the average operating cost by $0.019
per ton-hour (from $0.058 to $0.039)
750
was a sound investment.
7,590 hours
(72.5%)
By injecting asymmetry into a
0
symmetrical plant design, the design 0 1,000 2,000 3,000 4,000 5,000
Hours of Operation

“providing insights for today’s HVAC system designer” 3 ■


A publication of
The Trane Company
Worldwide Applied Systems Group
La Crosse, WI 54601-7599

Table 4–A Hybrid Solution a


Chiller Characteristics Annual Operation, Per Chiller
Average
Designation Capacity Power Run Time Cooling Cooling Cost
Chiller 1 750 tons electricity 4,740 hr 2.6 million ton-hr $0.039/ton-hr
Chiller 2 750 tons electricity 2,850 hr 1.8 million ton-hr $0.049/ton-hr
on the principle of asymmetrical design,
Chiller 3 750 tons gas 1,890 hr 1.3 million ton-hr $0.056/ton-hr
where one set of chillers tackles the
Chiller 4 750 tons gas 990 hr 652 thousand ton-hr $0.056/ton-hr
problem of overall plant efficiency, while
a
Chiller 3 and Chiller 4 are absorption chillers powered by 125-psig steam from a gas-fired boiler. If electric centrifugal chillers a second set of cooling devices is
were used instead, the average cooling cost would be $0.070 and $0.131 per ton-hour, respectively.
assigned the task of minimizing
demand charges. Series chiller
times. Adding a gas-engine generator so was the ability to provide emergency arrangements and low-flow designs are
meant a substantial capital investment. cooling in case of a power outage. also critical ingredients to the success
Leasing was deemed a more attractive of hybrid applications.
option since the engine-generator The design team considered thermal
package might only be required five or storage before eventually choosing a A Postscript. Utility rates influenced
six months of the year. (Leasing and plant design that combined absorption the decision to use a hybrid plant
temporary siting also solve certain and electrical chillers. Ice storage can design, once asymmetry helped
space problems.) be attractive for small chilled water establish two distinct design goals.
systems, especially when paired with Consider the effect of a deregulated
Another issue was the added air-cooled chillers. (“Small” describes a utility market in which electricity that
maintenance expense engines incur building not large enough to require might cost less than $0.02 per kilowatt-
(for example, a major overhaul is more than two chillers.) The capital cost hour at times of low demand skyrockets
required every 20,000 hours); however, and space requirement of ice storage is to $1 or more during on-peak periods.
running hours in this application were more readily managed when ice What could be more appropriate for an
low, i.e., less than 700 hours annually. capacity is limited to less than half of asymmetrical utility rate structure than
design cooling capacity. an asymmetrical plant design? ■
Note: While Chiller 3 and Chiller 4 run
1,890 and 990 hours, respectively, only
By Don Eppelheimer, applications
700 of those hours were likely to occur
engineer, and Brenda Bradley,
on-peak and impact demand charges. The “Moral” of This Story information designer, The Trane
During other periods, it was still less
Gas-powered chillers, absorption Company.
expensive to operate these two chillers
chillers, or ice—located upstream of
with purchased power. The flexibility to
electrical chillers—are all examples of To comment on this article, send a note
run Chiller 3 and Chiller 4 from gas or
what is termed a combination or to The Trane Company, Engineers
purchased electricity was very valuable;
“hybrid” chilled water plant. The Newsletter Editor, 3600 Pammel Creek
success of these plants is predicated Road, La Crosse, WI 54601, or via e-mail
from www.trane.com. Check the
electronic bookstore for informative
Figure 2–Series Arrangement Improves Absorption-Chiller Performance Trane publications on chilled water
plants and other commercial HVAC
Leaving Water
Temperature Capacity COP
systems. Back issues of recent
58˚F 50˚F
Engineers Newsletters are available on
42˚F 40°F 0.88 1.19
44°F 1.00 1.24 our Web site, too.
Electric 50°F 1.12 1.29
Absorption Chiller Centrifugal Chiller

Trane believes the facts and suggestions presented here to be accurate. However,
Printed on recycled paper as part of final design and application decisions are your responsibility. Trane disclaims any
The Trane Company’s recycling program. responsibility for actions taken on the material presented.

■ 4 ENEWS-28/4

You might also like