Professional Documents
Culture Documents
3.E Hand Over Report - THAI GIANG NAM
3.E Hand Over Report - THAI GIANG NAM
,LTD
NOTED BY MASTER
NOTED BY CHIEF ENGINEER
14 . CALORIFIER UNIT
- In good condition
- Maintenance works base on PMS
15 . COOKING APPARATUS
- In good condition
- Maintenance works base on PMS
16 . GRAY WATER SYSTEM
- In good condition
- Maintenance works base on PMS
17 . MOTORS
- In good condition
- Maintenance works base on PMS
- Monthly grease up :
. AP2: Motor of Steering gear, Incinerator, Sewage Air blower, ME, FO 2nd filter, ME
LO pumps, Crane motor
. WB3: ECR Air conditioners, Galley Air conditioners, Acc Air conditioners (1
week)
. Biotac: Rudder carrier
- Remark:
.Megger test shall be conducted at every 6 month
. Everyday turn stand by pumps
18 . SPARE PART
- Record spare part consumption in inventory after used
- Order spare follow inventory
- All items will be hand over directly.
19 . REMARK: The following CMS items to be carried-out accordingly in 2023
and to be credited during vessel’s annual survey( choose 1 to overhaul in 2023 or docking).
19 . DAILY REPORT
Time of report:
All lines clear -> Run up -> Noon -> … -> Noon -> Stand by Arrival -> Drop anchor -> Heave up
anchor -> 1st line on shore -> Morning report (0800) -> Noon -> All lines clear.
Bon voyage !